Nuclear Liabilities Fund

Nuclear Liabilities Fund

The Nuclear Liabilities Fund (formerly the Nuclear Generation Decommissioning Fund) is a fund of the UK Government to provide arrangements for funding certain long-term costs for the decommissioning of eight nuclear power stations formerly owned by British Energy. Responsibility for the Fund within government lies with the Shareholder Executive, on behalf of the Department of Energy and Climate Change.[1]

The Fund is owned by the Nuclear Trust, a public trust under Scottish Law. It consists of five trustees, three appointed by the Secretary of State for Energy and Climate Change and two by the owners of the nuclear power stations, now EDF Energy. The trustees are also directors of the Fund as well as owning the ordinary share capital of the Fund.[2]

Contents

History

The Nuclear Generation Decommissioning Fund was established on 28 March 1996 by the UK Government as part of the preparations for the privatisation of British Energy. It covered the nuclear power stations owned by the company on 20 March 1996, comprising seven advanced gas cooled reactor (AGR) stations and one pressurised water reactor (PWR) station. The obligations of the Fund were set out in an agreement known as the Nuclear Decommissioning Agreement. The Fund had an initial endowment of £232m and thereafter received £4m a quarter from British Energy, adjusted each year in line with RPI.[3]

On 14 January 2005, following the restructuring of British Energy after it required financial assistance from the government, the original agreement was terminated. It was replaced by the Contribution Agreement (CA) and the Nuclear Liabilities Funding Agreement (NLFA). Broadly, these agreements resulted in the following:[4]

  • The renaming of the Fund as the Nuclear Liabilities Fund.
  • Changes in decommissioning arrangements set out in the CA and the NLFA, such that the Fund continued to have the object of discharging the decommissioning liabilities of British Energy but also certain contracted and uncontracted nuclear liabilities. The Secretary of State agreed to fund these liabilities to the extent that they might exceed all the assets of the Fund.
  • British Energy continued to pay quarterly contributions of £6m but in addition the Fund received £275m in 7% Guaranteed Bonds issued by British Energy, entitlement to 65% of British Energy’s free cashflow in each year and £150k per tonne in respect of fuel loaded at Sizewell B.
  • The Trustees ceased to have responsibility for adequacy. The newly created Nuclear Decommissioning Authority (NDA) became responsible for determining liabilities. A first review of the Fund was to be carried out in January 2015 by the Fund and at each ten year anniversary thereafter or at any time after 2015 on the instigation of the Secretary of State.

Part of the Fund’s interest in British Energy was realised on 31 May 2007, when it converted approximately 30% of its entitlement to British Energy’s free cashflow into 450m British Energy shares. These were immediately sold to investors at a price of 520p per share, raising £2,340m.[5]

On 19 January 2009, the Fund sold its remaining 36% interest in British Energy following the takeover of the company by EDF Energy.[6] The sale raised a further £4,421m, taking the total Fund value at that date to £8,300m. This is to be invested to fund the long term decommissioning costs of EDF's eight former British Energy nuclear stations, plus certain other contracted and un-contracted nuclear liabilities relating to the assets as they arise.

See also

References

External links



Wikimedia Foundation. 2010.

Игры ⚽ Поможем решить контрольную работу

Look at other dictionaries:

  • Nuclear power in the United Kingdom — United Kingdom energy related articles Government energy policy Energy use and conservation Nuclear power Solar power Wind power Energy efficiency in …   Wikipedia

  • Nuclear Decommissioning Authority — The Nuclear Decommissioning Authority (NDA) is a non departmental public body of the United Kingdom formed by the Energy Act 2004. It came into existence in late 2004, and took on its main functions on 1 April 2005. Its purpose is to deliver the… …   Wikipedia

  • Nuclear power debate — For nuclear energy policies by nation, see Nuclear energy policy. For public protests about nuclear power, see Anti nuclear movement. Three of the reactors at Fukushima I overheated, causing meltdowns that eventually led to hydrogen explosions,… …   Wikipedia

  • National Nuclear Laboratory — The National Nuclear Laboratory (informally NNL, formerly Nexia Solutions) is a UK government owned, commercially operated nuclear services technology provider covering the whole of the nuclear fuel cycle. It is fully customer funded and operates …   Wikipedia

  • Office for Nuclear Regulation — The Office for Nuclear Regulation (ONR) is the regulator for the civil nuclear industry in the United Kingdom.[1] Created on 1 April 2011, the ONR is formed from the merger of the Health and Safety Executive s Nuclear Directorate (the Nuclear… …   Wikipedia

  • Chapelcross nuclear power station — Chapelcross nuclear power station, prior to demolition of the cooling towers Country Scotland Coordinates …   Wikipedia

  • Oldbury Nuclear Power Station — Oldbury Nuclear Power Station …   Wikipedia

  • Dungeness Nuclear Power Station — Dungeness A Nuclear Power Station Dungeness A …   Wikipedia

  • British Energy — Infobox Company company name = British Energy plc company company type = Public foundation = 1995 location = East Kilbride, Scotland, UK key people = Adrian Montague, (Chairman) William Coley, (CEO) industry = Energy products = electricity… …   Wikipedia

  • Sellafield — Aerial view of the site …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”