Cross Florida Barge Canal

Cross Florida Barge Canal
One of the two completed sections of the Barge Canal, looking west from the SR 19 bridge south of Palatka.
A map of the Cross Florida Barge Canal as planned and built.
One of the supports for the never completed bridge, in Santos in the US 441 median.

The Cross Florida Barge Canal was a canal project to connect the Gulf of Mexico and the Atlantic Ocean across Florida for barge traffic. Two sections were built but the project was cancelled, mainly for environmental reasons. It is now a protected green belt corridor, one mile (1.6 km) wide in most places. Named after the leader in the opposition against the canal, Marjorie Harris Carr, it is known as the Marjorie Harris Carr Cross Florida Greenway.

Contents

Route

The planned route of the canal followed the St. Johns River from the Atlantic coast to Palatka, the valley of the Ocklawaha River to the coastal divide, and the Withlacoochee River to the Gulf of Mexico. About 28% of the 107-mile (172 km) project was built—the cross-country section 29°32′15″N 81°44′48″W / 29.5375°N 81.74667°W / 29.5375; -81.74667 from the St. Johns River to the Oklawaha River, part of the route along the Oklawaha, and a small section 29°00′46″N 82°39′54″W / 29.01278°N 82.665°W / 29.01278; -82.665 at the Gulf of Mexico end up to the dammed Lake Rousseau.

Bridges and other infrastructure

All the bridges over the St. Johns River north of the canal are high enough for ships, or have movable sections. High bridges were built over the canal, as well as several over the Ocklawaha River where it was not widened to the canal. The following major roads, railroads, and locks and dams cross the path of the canal:

  • Buckman Lock (formerly St. Johns Lock)
  • SR 19 (high bridge)
  • Rodman Dam (south of the canal on the Ocklawaha River, forming Lake Ocklawaha along the canal)
  • Eureka Dam (unfinished)
  • CR 316 (high bridge)
  • SR 40, Bert Dosh Memorial Bridge (high bridge)
  • CR 314 (no bridge)
  • SR 35 (no bridge)
  • SR 464 (no bridge)
  • Florida Northern Railroad (no bridge)
  • CSX S-Line (no bridge)
  • US 27-301-441 (SR 25/SR 500) (no bridge, but several unused supports in the median)
  • CR 475 (no bridge)
  • I-75 (SR 93) (no bridge; recently built land bridge over I-75 for trail users)
  • SW 49th Avenue (no bridge; recently built underpass for trail users)
  • CR 484 (no bridge)
  • SR 200 (no bridge)
  • CSX line (low bridge over the existing Withlacoochee River)
  • US 41 (SR 45), Brittan Alexander Bridge (low bridge over the existing Withlacoochee River)
  • Inglis Lock (Inglis Dam is south of the canal on the Withlacoochee River, forming Lake Rousseau along the canal)
  • US 19-98 (SR 55) (high bridge, duplicate currently under construction)

Between Lake Rousseau and the Ocklawaha River, discontinuous, unwatered excavations mark the canal's planned path, along with different vegetation patterns on the land acquired for the project (as seen from the air).

History

The idea of such a canal was first proposed by Philip II of Spain in 1567. It was repeatedly considered over the years but found to be economically unviable. Secretary of War John C. Calhoun once again proposed a canal in 1818 in order to solve the losses due to shipwrecks and piracy. The Florida Railroad, finished on March 1, 1861, served a similar purpose, connecting the Atlantic Ocean at Fernandina to the Gulf of Mexico at Cedar Key.

In the 1930s, regional politicians lobbied the federal government to fund canal construction as an economic recovery program, and president Franklin D. Roosevelt allocated emergency funds in 1935. Local opponents of the canal protested that the canal would deplete Florida's aquifers, and work was stopped a year later.

Work was reauthorized in 1942 as a national defense project, with dams and locks to protect the underground water supply. Support for the project from Washington was sporadic, and funds were never allocated to USACE to actually start construction.

Planning was once again given the go-ahead in 1963 with support from president John F. Kennedy, who allocated one million dollars to the project. The next year, Lyndon Johnson set off the explosives that started construction. It was hoped that the canal, along with the St. Johns-Indian River Barge Canal, would provide a quicker and safer route across Florida by 1971.

Opponents subsequently campaigned against the canal on environmental grounds, and the project stopped again in January 1971. It was officially cancelled in 1991. The right-of-way was turned over to the state and became the Marjorie Harris Carr Cross Florida Greenway, named in honor of the woman who led opposition to the canal.

Project timeline

  • May 1933 - Canal Authority of the State of Florida was created to construct and maintain a deep-water ship canal across Florida.
  • 1935-1936 – Construction of a ship canal began under the Emergency Relief Appropriations Act of 1935, but work was suspended when Federal funds were depleted.
  • July 1942 – Congress authorized construction of the Cross Florida Barge Canal.
  • February 1964 – The U. S. Army Corps of Engineers began construction of the Cross Florida Barge Canal.
  • 1969 – The Environmental Defense Fund and others filed suit in the U. S. District Court for the District of Columbia seeking temporary and permanent injunction against the construction of the canal.
  • January 15, 1971 – The District Court granted a preliminary injunction halting any further construction activities pending the outcome of the litigation.
  • January 19, 1971 – President Richard Nixon signed an executive order suspending further work on the Barge Canal. When halted, the project was one-third complete and approximately $74 million had been spent on land acquisition and construction.
  • 1979 – Bills filed in Congress to deauthorize the Canal failed to pass.
  • May 22, 1990 - A revised federal bill was filed in the U. S. Senate by Senators Bob Graham and Connie Mack providing, among other things, for a minimum 300-yard wide greenway corridor to be maintained along the former Barge Canal route. This bill was agreed to by the entire Florida Congressional delegation.
  • May 31, 1990 - The Florida Legislature enacted a deauthorization bill conforming to the consensus bill filed in the U. S. Senate. Most of the provisions were not effective until Congress deauthorized the project.
  • October 27, 1990 – Senate Bill 2740 was passed by Congress and sent to the President for signature. The bill deauthorized the Cross Florida Barge Canal project upon acceptance by the Governor and Cabinet of the State of Florida.
  • November 28, 1990 – President George Bush signed SB 2740 into law deauthorizing the Cross Florida Barge Canal project and changing the purpose of the lands to recreation and conservation.
  • January 22, 1991 – The Governor and Cabinet of the State of Florida signed a resolution agreeing to the terms of the Federal deauthorization bill thereby officially deauthorizing the Cross Florida Barge Canal project. This action ultimately led to the creation of the Cross Florida Greenway State Recreation and Conservation Area.
  • 1998 - The Cross Florida Greenway was officially renamed the Marjorie Harris Carr Cross Florida Greenway in honor of the individual who led the fight to stop the Cross Florida Barge Canal project.

External links


Coordinates: 29°32′15″N 81°44′48″W / 29.5374695°N 81.7467501°W / 29.5374695; -81.7467501


Wikimedia Foundation. 2010.

Игры ⚽ Поможем сделать НИР

Look at other dictionaries:

  • Cross-Florida Barge Canal — L une des deux sections du canal, depuis le pont de la SR 19 au sud de Palatka. Le Cross Florida Barge Canal était un projet de canal devant relier le golfe du Mexique à l océan Atlantique via la Floride pour le trafic des barges.… …   Wikipédia en Français

  • Barge Canal — (Florida) may refer to one of two projects:*Merritt Island Barge Canal, in Brevard County, Florida *Cross Florida Barge Canal, a never completed project to connect the St. Johns River to the Gulf of Mexico …   Wikipedia

  • Canaveral Barge Canal — Barge canal, looking towards the Christa McAuliffe Bridge Date of first use January 1, 1965 Locks 1 …   Wikipedia

  • Florida National Cemetery — is a United States National Cemetery located in the city of Bushnell in Sumter County, Florida .Florida National Cemetery is located in the Withlacoochee State Forest, approximately 50 miles north of Tampa in Sumter County, Fla. Withlacoochee… …   Wikipedia

  • Florida Museum of Natural History — Coordinates: 29°38′09″N 82°22′13″W / 29.63583°N 82.37028°W / 29.63583; 82.37028 …   Wikipedia

  • Florida State Road 40 — State Road 40 Route information Maintained by FDOT Length: 91.7 mi[ …   Wikipedia

  • Florida Railroad — The Florida Railroad was the first railroad to connect the east and west coasts of Florida, running from Fernandina to Cedar Key. The line later became part of the Seaboard Air Line Railroad, and, where still in use, is operated by CSX… …   Wikipedia

  • Florida State Road 19 — Infobox road state=FL type= route=19 length mi=89.0 length round=2 length ref=cite web |url=http://www.dot.state.fl.us/planning/statistics/gis/default.htm |title=FDOT GIS data |accessmonthday=June 27 |accessyear=2007 |author=Florida Department of …   Wikipedia

  • U.S. Route 441 in Florida — This article is about the section of U.S. Route 441 in Florida. For the entire length of the highway, see U.S. Route 441. U.S. Highway 441 …   Wikipedia

  • Haulover Canal — Date completed 1887 Status Open Navigation authority U.S. Army Corps of Engineers The Haulover Canal is a waterway north of Merritt Island, Florida, near the former site of Allenhurst, that connects Mosquito Lagoon with the Indian River, and is… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”