- Cost overrun
-
A cost overrun, also known as a cost increase or budget overrun, is an unexpected cost incurred in excess of a budgeted amount due to an under-estimation of the actual cost during budgeting. Cost overrun should be distinguished from cost escalation, which is used to express an anticipated growth in a budgeted cost due to factors such as inflation.
Cost overrun is common in infrastructure, building, and technology projects. A comprehensive study of cost overrun published in the Journal of the American Planning Association in 2002 found that 9 out of ten construction projects had underestimated costs. Overruns of 50 to one hundred percent were common.[improper synthesis?] Cost underestimation was found in each of 20 nations and five continents covered by the study, and cost underestimation had not decreased in the 70 years for which data were available.[1] For IT projects, an industry study by the Standish Group found that the average cost overrun was 43 percent; 71 percent of projects were over budget, exceeded time estimates, and had estimated too narrow a scope; and total waste was estimated at $55 billion per year in the US alone.[2]
Many major construction projects have incurred cost overruns. The Suez Canal cost 20 times as much as the earliest estimates; even the cost estimate produced the year before construction began underestimated the project's actual costs by a factor of three.[1] The Sydney Opera House cost 15 times more than was originally projected, and the Concorde supersonic aeroplane cost 12 times more than predicted.[1] When Boston's "Big Dig" tunnel construction project was completed, the project was 275 percent ($11 billion) over budget.[3] The Channel Tunnel between the UK and France had a construction cost overrun of 80 percent, and a 140-percent financing cost overrun.[3]
Contents
Causes
Three types of explanation for cost overrun exist: technical, psychological, and political-economic. Technical explanations account for cost overrun in terms of imperfect forecasting techniques, inadequate data, etc. Psychological explanations account for overrun in terms of optimism bias with forecasters. Scope creep, where the requirements or targets rises during the project, is common. Finally, political-economic explanations see overrun as the result of strategic misrepresentation of scope or budgets.
All three explanations can be considered forms of risk. A project's budgeted costs should always include cost contingency funds to cover risks (other than scope changes imposed on the project). As has been shown in cost engineering research,[4] poor risk analysis and contingency estimating practices account for many project cost overruns. Numerous studies have found that the greatest cause of cost growth was poorly-defined scope at the time that the budget was established. The cost growth, or overrun of the budget before cost contingency is added, can be predicted by rating the extent of scope definition, even on complex projects with new technology.[5]
Professor Bent Flyvbjerg of Oxford University and Martin Wachs of University of California, Los Angeles have shown that big public-works projects often have cost overruns due to strategic misrepresentation—"that is, lying", as Flyvbjerg defines the term.[6]
Cost overrun is typically calculated in one of two ways: either as a percentage, namely actual cost minus budgeted cost, in percent of budgeted cost; or as a ratio of actual cost divided by budgeted cost. For example, if the budget for building a new bridge was $100 million, and the actual cost was $150 million, then the cost overrun may be expressed by the ratio 1.5, or as 50 percent.
Reference class forecasting was developed to eliminate or reduce cost overrun.[7]
List of projects with large cost overruns
Australia
Brazil
Canada
- Pickering Nuclear Generating Station
- Montreal Olympic Stadium
- Rogers Centre (formerly SkyDome)
Denmark
Egypt
Japan
Malaysia
North Korea
Panama
Sweden
United Kingdom
- Humber Bridge
- Millennium Dome
- National Programme for IT
- Scottish Parliament Building
- TAURUS (share trading)
United States
- Big Dig[3]
- Denver International Airport
- Eastern span replacement of the San Francisco–Oakland Bay Bridge
- F-22 Raptor
- Joint Strike Fighter Program
- NPOESS
- Paw Paw Tunnel
- V-22 Osprey
- Hubble Space Telescope
Multinational
See also
- Admissible heuristic
- Benefit shortfall
- Cost underestimation
- Megaproject
- Optimism bias
- Reference class forecasting
- Scope creep
- Strategic misrepresentation
References
- ^ a b c d e Flyvbjerg, Bent; Holm, Mette Skamris; Buhl, Søren (Summer 2002). "Underestimating Costs in Public Works Projects: Error or lie?". Journal of the American Planning Association (Chicago: American Planning Association) 68 (3): 279–295. ISSN 0194-4363. http://flyvbjerg.plan.aau.dk/JAPAASPUBLISHED.pdf. Retrieved 2010-10-16.
- ^ Standish Group (2004). CHAOS Report (Report). West Yarmouth, Massachusetts: Standish Group.
- ^ a b c d e Flybjerg, Bent (2005-12-01). Policy and Planning for Large Infrastructure Projects: Problems, causes, cures (Report). Policy Research Working Papers. 3781. World Bank Publications. pp. 4–5. WPS3781. http://go.worldbank.org/6G2FJ40OG0.
- ^ Hackney, John W. (1991). Humphreys, Kenneth K.. ed. Control and Management of Capital Projects. American Association of Cost Engineers (2nd ed.). New York: McGraw-Hill. ISBN 9780070012592. OCLC 123212738.
- ^ Merrow, Edward W.; Phillips, Kenneth E.; Myers, Christopher W. (September 1981). Understanding Cost Growth and Performance Shortfalls in Pioneer Process Plants. Rand. ISBN 0-8330-0352-6. RAND Document R-2569-DOE. http://health.rand.org/pubs/reports/2006/R2569.pdf.
- ^ Westneat, Danny (2009-04-26). "Tunnel's cost may fool us all". Seattle Times (Seattle: Seattle Times). http://seattletimes.nwsource.com/html/dannywestneat/2009123442_danny26.html. Retrieved 2010-10-16.
- ^ Flyvbjerg, Bent (2008-01-01). "Curbing Optimism Bias and Strategic Misrepresentation in Planning: Reference class forecasting in practice". European Planning Studies (Routledge) 16 (1): 3–21. doi:10.1080/09654310701747936. ISSN 0965-4313. http://www.sbs.ox.ac.uk/centres/bt/Documents/Curbing%20Optimism%20Bias%20and%20Strategic%20Misrepresentation.pdf.
Further reading
- Flyvbjerg, Bent; Bruzelius, Nils; Rothengatter, Werner (2003). Megaprojects and Risk: an anatomy of ambition. Cambridge, UK: Cambridge University Press. ISBN 9780521009461. http://books.google.com/books?id=RAV5P-50UjEC&printsec=frontcover#v=onepage&q&f=false.
External links