Hallandsås Tunnel

Hallandsås Tunnel

The Hallandsås Tunnel ( _sv. Hallandsåstunneln), also known as the Hallandsås Ridge Tunnel or Scanlink, is a railway tunnel under construction in Sweden. The planned length is 8.5 km (5.3 miles). It will be located on the Västkustbanan (West Coast Railway), on the section between Ängelholm and Halmstad in southwestern Sweden. When finished, it will connect the city of Gothenburg, Sweden with Malmö, Sweden. Today there is a single track, curvy, steep railway over the ridge. The project was conceived by the European Round Table of Industrialists and the Swedish Railway Administration in the 1980s.

The construction began in 1992, and the traffic opening was originally planned for 1995. However, construction was plagued by major difficulties concerning large amounts of water seeping in from surrounding rock. Only small a fraction of this water leakage had been forseen. Additionally, a scandal broke out when it was learned that a poisonous sealing compound called "Rhoca-Gil" was used during construction. This substance was linked to the death of nearby livestock. Rhoca-Gil contains acrylamide, a toxic chemical that is mutagenic and possibly carcinogenic. The main contractor, Skanska, took no special precautions for the sealant. Also, it did not tell its own workers or the local population of the risks. By October 1997, local cattle and fish started dying. In addition, workers were becoming ill. The local press started an investigation. After tests were done showing the high levels of acrylamide contamination, the site was declared a high risk zone and the sale of agricultural products from the region was banned. The main contractor, Skanska, along with Rhone-Poulenc and Swedish Railways all had criminal charges brought against them. Some senior executives resigned as a result. Construction was halted in late 1997.

In 2005 construction resumed with a new completion date estimated at 2012, later updated to 2015. At the restart there were some delays which may again push back the completion date. The builders however, believe that they will be able to make up for lost time during construction.

Cost overrun has been large. The cost was expected in 1992 to be SEK 1 billion. The cost from 1992 to 1997 was in reality more than SEK 2 billion, for less than half the tunnel length. Since the remaining cost at the beginning of 2005 was calculated to be more than SEK 4 billion, there has been much debate and hesitation as to whether to halt or resume work. The total cost is likely to reach over SEK 10 billion before the project is finished, according to the latest calculation.

External links

* [http://www.banverket.se/pages/4439/Skanska-Vinci%20eng.pdf Information from Skanska and Banverket describing how the tunnel was built]


Wikimedia Foundation. 2010.

Игры ⚽ Нужен реферат?

Look at other dictionaries:

  • Hallandsås — is a horst on the border between the Swedish counties Skåne and Halland.It is part of a geological formation that includes an island in the sea outside the village of Torekov near Båstad called Hallands Väderö . The geological formation continues …   Wikipedia

  • Hallandsås — Der Hallandsåsen von Norden Der Hallandsåsen ist ein bis zu 226 m hoher Höhenzug im Süden Schwedens. Das Gebiet mit Reichsinteresse[1] bildet die natürliche Trennlinie zwischen den historischen Provinzen (auch „Landschaft“, schwedisch landskap)… …   Deutsch Wikipedia

  • Hallandsastunnel — Baustelle am Südportal des Hallandsåstunnels Der Hallandsåstunnel ist ein derzeit im Bau befindlicher Tunnel in Schweden. Er soll ab 2015 den Bahnverkehr der Västkustbanan zwischen Göteborg und Lund durch den südschwedischen Höhenzug Hallandsåsen …   Deutsch Wikipedia

  • Hallandsåstunneln — Baustelle am Südportal des Hallandsåstunnels Der Hallandsåstunnel ist ein derzeit im Bau befindlicher Tunnel in Schweden. Er soll ab 2015 den Bahnverkehr der Västkustbanan zwischen Göteborg und Lund durch den südschwedischen Höhenzug Hallandsåsen …   Deutsch Wikipedia

  • Cost overrun — A cost overrun, also known as a cost increase or budget overrun, is an unexpected cost incurred in excess of a budgeted amount due to an under estimation of the actual cost during budgeting. Cost overrun should be distinguished from cost… …   Wikipedia

  • Rhoca-Gil — is a type of industrial sealant produced by Rhône Poulenc, used in the construction of tunnels to block the passage of groundwater into the tunnel. The sealant begins as a liquid, is then injected into cavities which need to be sealed, and… …   Wikipedia

  • Liste des épisodes de Superstructures — Cet article recense la liste des épisodes de la série télévisée Superstructures. Sommaire 1 Épisodes 1.1 01. Les Tours Petronas 1.2 02. Tau Tona: la plus grande mine d or …   Wikipédia en Français

  • Mega construcciones — Extreme Engineering Título Mega construcciones Género Documental Presentado por Danny Foster País de origen   …   Wikipedia Español

  • Hallandsåstunnel — Baustelle am Südportal des Hallandsåstunnels Der Hallandsåstunnel ist ein derzeit im Bau befindlicher Tunnel in Schweden. Er soll ab 2015 den Bahnverkehr der Västkustbanan zwischen Göteborg und Lund durch den südschwedischen Höhenzug Hallandsåsen …   Deutsch Wikipedia

  • Västkustbanan — Ligne Västkustbanan Ligne de Lund à Göteborg via Helsingborg La gare de Båstad Pays …   Wikipédia en Français

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”