Reference class forecasting

Reference class forecasting

Reference class forecasting predicts the outcome of a planned action based on actual outcomes in a reference class of similar actions to that being forecast. The theories behind reference class forecasting were developed by Daniel Kahneman and Amos Tversky. They helped Kahneman win the 2002 Nobel Prize in Economics.

Kahneman and Tversky (1979a, b) found that human judgment is generally optimistic due to overconfidence and insufficient consideration of distributional information about outcomes. Therefore, people tend to underestimate the costs, completion times, and risks of planned actions, whereas they tend to overestimate the benefits of those same actions. Such error is caused by actors taking an "inside view," where focus is on the constituents of the specific planned action instead of on the actual outcomes of similar ventures that have already been completed.

Kahneman and Tversky concluded that disregard of distributional information, that is, risk, is perhaps the major source of error in forecasting. On that basis they recommended that forecasters "should therefore make every effort to frame the forecasting problem so as to facilitate utilizing all the distributional information that is available" (Kahneman and Tversky 1979b, p. 316).

Using distributional information from previous ventures similar to the one being forecast is called taking an "outside view". Reference class forecasting is a method for taking an outside view on planned actions.

Reference class forecasting for a specific project involves the following three steps:
*1. Identify a reference class of past, similar projects.
*2. Establish a probability distribution for the selected reference class for the parameter that is being forecast.
*3. Compare the specific project with the reference class distribution, in order to establish the most likely outcome for the specific project.

Whereas Kahneman and Tversky developed the theories of reference class forecasting, Flyvbjerg and Cowi (2004) developed the method for its practical use in policy and planning. The first instance of reference class forecasting in practice is described in Flyvbjerg (2006). This was a forecast carried out in 2004 by the UK government of the projected capital costs for an extension of the Edinburgh Tram. The promoter's forecast estimated a cost of £255 million. Taking all available distributional information into account, based on a reference class of comparable rail projects, the reference class forecast estimated a cost of £320 million. Since the Edinburgh forecast, reference class forecasting has been applied to numerous other projects in the UK, including the £15 (US$29) billion Crossrail project in London. After 2004, The Netherlands, Denmark, and Switzerland have also implemented various types of reference class forecasting.

In 2005, the American Planning Association (APA) endorsed reference class forecasting and recommended that planners should never rely solely on conventional forecasting techniques:

"APA encourages planners to use reference class forecasting in addition to traditional methods as a way to improve accuracy. The reference class forecasting method is beneficial for non-routine projects ... Planners should never rely solely on civil engineering technology as a way to generate project forecasts" (the American Planning Association 2005).

Before this, in 2001 (updated in 2006), AACE International (the Association for the Advancement of Cost Engineering) included Estimate Validation as a distinct step in the recommended practice of Cost Estimating (Estimate Validation is equivalent to Reference class forecasting in that it calls for separate empirical-based evaluations to benchmark the base estimate):

"The estimate should be benchmarked or validated against or compared to historical experience and/or past estimates of the enterprise and of competitive enterprises to check its appropriateness, competitiveness, and to identify improvement opportunities...Validation examines the estimate from a different perspective and using different metrics than are used in estimate preparation." (AACE International 2006)

In the process industries (e.g., oil and gas, chemicals, mining, energy, etc. which tend to dominate AACE's membership), benchmarking (i.e., "outside view") of project cost estimates against the historical costs of completed projects of similar types, including probabilistic information, has a long history (Merrow 1990). These companies must make a profit from their asset investments and therefore cannot afford the biases in public and government sponsored infrastructure projects.

See also

*Benefit shortfall
*Cost overrun
*Optimism bias
*Planning fallacy
*Strategic misrepresentation
*Forecasting
*Base rate fallacy
*Daniel Kahneman

References

* [http://www.planning.org/newsreleases/2005/ftp040705.htm American Planning Association, 2005, "JAPA Article Calls on Planners to Help End Inaccuracies in Public Project Revenue Forecasting", news release, April 7.]
* [http://flyvbjerg.plan.aau.dk/Publications2006/Nobel-PMJ2006.pdf Flyvbjerg, B., 2006, "From Nobel Prize to Project Management: Getting Risks Right." Project Management Journal, vol. 37, no. 3, August, pp. 5-15.]
* [http://flyvbjerg.plan.aau.dk/0406DfT-UK%20OptBiasASPUBL.pdf Flyvbjerg, B. and Cowi, 2004, Procedures for Dealing with Optimism Bias in Transport Planning: Guidance Document (London: UK Department for Transport).]
*Kahneman, D. and Tversky, A., 1979a, "Prospect theory: An analysis of decisions under risk." Econometrica, 47, pp. 313-327
*Kahneman, D. and Tversky, A., 1979b, "Intuitive Prediction: Biases and Corrective Procedures." In S. Makridakis and S. C. Wheelwright, Eds., Studies in the Management Sciences: Forecasting, 12 (Amsterdam: North Holland).
*Lovallo, D. and Kahneman, D., 2003, "Delusions of Success: How Optimism Undermines Executives' Decisions," Harvard Business Review, July, pp 56-63
* [http://www.aacei.org/aaceonly/tcm/7.3.shtml AACE International, "Total Cost Management Framework, Section 7.3, Cost Estimating and Budgeting", 2006]
*Merrow, E. and Yarossi, M., "Assessing Project Cost and Schedule Risk", 1990 AACE Transactions. pp H.6.1-7


Wikimedia Foundation. 2010.

Игры ⚽ Поможем написать реферат

Look at other dictionaries:

  • Forecasting — is the process of estimation in unknown situations. Prediction is a similar, but more general term. Both can refer to estimation of time series, cross sectional or longitudinal data. Usage can differ between areas of application: for example in… …   Wikipedia

  • Demand forecasting — is the activity of estimating the quantity of a product or service that consumers will purchase. Demand forecasting involves techniques including both informal methods, such as educated guesses, and quantitative methods, such as the use of… …   Wikipedia

  • Technology forecasting — is forecasting the future characteristics of useful technological machines, procedures or .Important aspectsPrimarily, a technological forecast deals with the characteristics of technology, such as levels of technical performance, like speed of a …   Wikipedia

  • Collaborative Planning, Forecasting, and Replenishment — (CPFR) is a concept that aims to enhance supply chain integration by supporting and assisting joint practices. CPFR seeks cooperative management of inventory through joint visibility and replenishment of products throughout the supply chain.… …   Wikipedia

  • Transportation forecasting — is the process of estimating the number of vehicles or travelers that will use a specific transportation facility in the future. A forecast estimates, for instance, the number of vehicles on a planned freeway or bridge, the ridership on a railway …   Wikipedia

  • Collaborative planning, forecasting, and replenishment — Collaborative Planning, Forecasting and Replenishment (CPFR) is a concept that aims to enhance supply chain integration by supporting and assisting joint practices. CPFR seeks cooperative management of inventory through joint visibility and… …   Wikipedia

  • Economic forecasting — is the process of making predictions about the economy as a whole or in part.Relevant models include * Economic base analysis * Shift share analysis * Input output model See also * Land use forecasting *Reference class forecasting *… …   Wikipedia

  • Optimism bias — is the demonstrated systematic tendency for people to be overly optimistic about the outcome of planned actions. This includes over estimating the likelihood of positive events and under estimating the likelihood of negative events. Along with… …   Wikipedia

  • Risk — takers redirects here. For the Canadian television program, see Risk Takers. For other uses, see Risk (disambiguation). Risk is the potential that a chosen action or activity (including the choice of inaction) will lead to a loss (an undesirable… …   Wikipedia

  • Cost overrun — A cost overrun, also known as a cost increase or budget overrun, is an unexpected cost incurred in excess of a budgeted amount due to an under estimation of the actual cost during budgeting. Cost overrun should be distinguished from cost… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”