Regional Fast Rail project

Regional Fast Rail project

The Regional Fast Rail project was a State Government initiative in Victoria, Australia, to decrease travel times on parts of the Victorian regional railway network. Launched on September 5 2000, the project involved the upgrading of tracks linking Ballarat, Bendigo, Geelong, and the Latrobe Valley to Melbourne, the state capital, as well as the introduction of 38 high-speed "VLocity" diesel multiple-unit trains built by Bombardier.

Project overview

Part of the Linking Victoria program, the Regional Fast Rail project was described as "possibly the biggest single upgrade to regional railway lines in 120 years", [cite web|url=http://www.abc.net.au/stateline/vic/content/2006/s1736643.htm|title=ABC - 'Fast rail or rail farce' - September 8 2006|accessdate=2007-07-26] including:
*delivery of 38 new VLocity trains (with additional trains later ordered) [cite web
url=http://www.dpc.vic.gov.au/domino/Web_Notes/newmedia.nsf/8fc6e140ef55837cca256c8c00183cdc/70fd92e6291cad24ca25737400805ee5!OpenDocument
title=Media Release: EXTRA CARRIAGES TO BOOST CAPACITY ON REGIONAL TRAINS
publisher=www.dpc.vic.gov.au
accessdate=2008-04-03
]
*upgrade of 500 km of track
*installation of 400 new and upgraded railway signals, along with the Train Protection & Warning System
*installation of more than 460,000 concrete sleepers
*upgrade of 170 level crossings
*introduction of new rail safety systems
*the development of new train timetables with improved services
*new fibre optic signalling that provides broadband opportunities in regional areas

Trains

To provide for the faster services, an existing order for 2-carriage VLocity DMUs was altered to increase the top speed and to increase the number of the trains to 38. [cite web|url=http://www.audit.vic.gov.au/reports_mp_psa/psa1602.html|title=Victorian Auditor Generals Office - 'DELIVERING REGIONAL FAST RAIL SERVICES'|accessdate=2007-07-26]

Services on all four RFR lines plus other lines outside the scope of the project are provided by the VLocity trains, the older Sprinter DMUs, and A class, N class and P class locomotive-hauled "N sets" and "H sets". As each of these trains have different top speeds, timetables are designed with particular services being run by particular types of trains.

Services

The VLocity trains began running to the slower schedules from December 2005, and 160 km/h services began on the Geelong, Ballarat, and Bendigo lines on 3 September 2006. On the Traralgon line, 160 km/h services began on 15 October 2006, although in both cases a few selected services ran to slightly faster schedules for a week or so beforehand. [cite web|url=http://www.legislation.vic.gov.au/domino/Web_Notes/newmedia.nsf/955cbeae7df9460dca256c8c00152d2b/ec2eec689a918182ca2572090025a7d8!OpenDocument|title=DoI media release - 'NEW GIPPSLAND RAIL TIMETABLE TAKES OFF TODAY'|accessdate=2007-07-26]

As well as reduced journey times, the new timetables also increased the frequency of services, with off-peak trains arriving up to once per hour. Additional trains, with varying consist lengths to suit demand, are also scheduled to operate during the peak, with one service each peak designated as a "flagship" service with the shortest journey time.

Line by line

Geelong line

Fast Rail services were officially launched on the Geelong line on February 3 2006. [cite web|url=http://wongm.fotopic.net/c848826.html|title=V/line - First VLocity Services to Geelong|accessdate=2007-07-26]

The double-track Geelong line had the track and signalling upgraded to allow for VLocity trains running at 160 km/h between Werribee and Geelong. These works were carried out in various stages between 2004 and 2006. The Geelong line already comprised two bidirectional tracks between Newport and North Geelong. 160 km/h operation is only provided for on the East track for down trains and the West track for up trains.

Ballarat line

The Ballarat line was the first line to see V/Line's new VLocity in service on December 22 2005. [cite web|url=http://wongm.fotopic.net/c802268.html|title=V/line - First Day of VLocity Revenue Operation (Ballarat)|accessdate=2007-07-26]

Track and signalling was upgraded to allow for VLocity trains running at 160 km/h between Deer Park West Junction and Ballarat. In addition, some deviations were built to ease curves or, in one case, to provide a considerably shorter route (the original route was retained, however, to provide a passing loop).

Bendigo line

Track and signalling was upgraded on the Bendigo line to allow for VLocity trains running at 160 km/h between Sunbury and Bendigo. Also, bidirectional signalling was provided between Sunbury and Kyneton. Between Kyneton and Bendigo the double-track line was singled to allow for better clearances past heritage structures, although retaining some sections of double track in the form of long crossing loops. The crossing loops were provided with bidirectional signalling, but only one of the two tracks was upgraded for 160 km/h running.

Traralgon line

Track and signalling on the Traralgon line was upgraded to allow for VLocity trains running at 160 km/h between Pakenham and Traralgon. Bidirectional signalling was also provided on the double-track sections between Pakenham and Bunyip, and between Longwarry and Moe. However, only the former up track (now called the South track) was upgraded for 160 km/h running; VLocity trains are limited to 130 km/h on the former down track (now North track).

Criticisms

Criticisms of the project have centred on the cost, the lack of time savings, and the removal of one track from part of the Bendigo line. The State Opposition have dubbed the project the Farce Rail Project. [cite web|url=http://www.theage.com.au/news/national/equipment-blamed-for-train-troubles/2007/03/28/1174761568071.html|title=The Age - 'Equipment blamed for train troubles' - March 29, 2007|accessdate=2007-07-26]

Costs

The Government originally hoped that most of the cost of the project would be borne by the private sector. However, when this support failed to materialise, [cite web|url=http://www.dtf.vic.gov.au/domino/Web_Notes/MediaRelArc02.nsf/ebfd7a9e83f839b34a2568110023b2e3/5a5dd8804e30cd084a256a5e001deeff!OpenDocument&Click=|title=DoI media release - 'EXPRESSIONS OF INTEREST CALLED FOR ON FAST RAIL PROJECT' - May 31, 2001|accessdate=2007-07-26] the Government decided to pay for the entire project themselves. In addition the project ran overtime and over budget. [cite web|url=http://www.theage.com.au/news/national/fast-trains-strike-costly-sound-hitch/2005/10/10/1128796469419.html|title=The Age - 'Fast trains strike costly sound hitch' - October 11, 2005|accessdate=2007-07-26]

Time savings

The original promise was for trains to run to Geelong in 45 minutes, Ballarat in 60 minutes, Bendigo in 80 minutes, and Traralgon in 90 minutes. [cite web|url=http://www.audit.vic.gov.au/reports_mp_psa/psa1602.html|title=Victorian Auditor Generals Office - 'DELIVERING REGIONAL FAST RAIL SERVICES'|accessdate=2007-07-26] However, this was soon changed to add four minutes to each journey. In the current V/Line timetables, it takes the Traralgon service 111 minutes to the city. [cite web|url=http://www.vline.com.au/travellingwithvline/timetables/timetables.html#eastern|title=V/Line Eastern Region Timetables|accessdate=2007-07-26]

However, even these times were only for a few trains each day that would run express between Melbourne and the respective regional cities. Furthermore, the number of trains what would run to these schedules was cut to one each way each day. [cite web|url=http://www.vline.com.au/travellingwithvline/timetables/timetables.html|title=V/Line Timetables|accessdate=2007-07-26] Even though most journey times are now faster than before the project, the public impression is that time savings are minimal. [cite web|url=http://www.theage.com.au/news/in-depth/riding-the-rails/2006/09/12/1157826941501.html?page=fullpage|title=The Age - 'Riding the rails' - September 13, 2006|accessdate=2007-07-28]

Bendigo line singling

The removal of one track from much of the Bendigo line has also been the source of much criticism, [cite web|url=http://www.ptua.org.au/allies/brag/|title=Bendigo Better Rail Action Group|accessdate=2007-07-28] although the original plans for crossing loops was altered to allow for longer crossing loops. [cite web|url=http://www.dpc.vic.gov.au/domino/Web_Notes/newmedia.nsf/b0222c68d27626e2ca256c8c001a3d2d/cc4932f92392b214ca256de10078b4f8?OpenDocument|title=DoI media release - 'LONG DOUBLE TRACK SECTIONS TO PROVIDE FOR HIGH-QUALITY SERVICES ON BENDIGO RAIL LINE' - November 17 2003|accessdate=2007-07-26]

A spokesman for the Better Rail Action Group has claimed that the reason for eliminating the double track is to save costs, rather than for technical reasons. [cite web|url=http://www.ptua.org.au/allies/brag/SingleMindedMania.pdf|title=Andrew McLean - Single-minded Mania|accessdate=2007-07-28]

References

ee also

*High-speed rail in Australia
*Rail transport in Victoria
*Operation Phoenix
*New Deal

External links

* [http://www.doi.vic.gov.au/DOI/Internet/transport.nsf/AllDocs/AB72CE7E732DC450CA2571F80006286D?OpenDocument Regional Fast Rail project] on the Department of Transport website


Wikimedia Foundation. 2010.

Игры ⚽ Нужно сделать НИР?

Look at other dictionaries:

  • Rail transport in Victoria — Infobox rail railroad name = Railways of Victoria logo filename = logo size = system map caption = Victorian railway network, passenger lines in colour, freight only lines in grey marks = locale = Victoria, Australia start year = 1854 end year =… …   Wikipedia

  • High-speed rail in Australia — Australia is a country without any high speed rail (200 km/h or above). [cite web url=http://www.uic.asso.fr/gv/article.php3?id article=14 title=General definitions of highspeed publisher=International Union of Railways accessdate=2008 08 13]… …   Wikipedia

  • History of rail transport in Australia — This article is part of the history of rail transport by country series Following the British model, Australians generally assumed in the 1850s that railways would be built by the private sector. Private companies built railways in the then… …   Wikipedia

  • Geelong V/Line rail service — Geelong railway line, Victoria Line details Opened 1857 Length 81 km (50.3 mi) Stations 13 …   Wikipedia

  • Ballarat V/Line rail service — Ballarat railway line, Victoria Line details Tracks Double track to Deer Park West, single track with loops beyond. Used by V/Line, freight Service pattern Interurban Rolling stock Sprin …   Wikipedia

  • List of regional railway stations in Victoria — This is a list of the currently operating Victorian regional railway stations serviced by V/Line operated trains. The stations make up 7 radial passenger train lines, which all operate out of Southern Cross Station in Melbourne, Australia, with 2 …   Wikipedia

  • Inter-city rail — services are express train passenger services which cover longer distances than commuter trains.AfricaInter city services are reasonably well developed in North Africa, although sometimes prone to delay or interrupted by civil disturbances.… …   Wikipedia

  • Moreton Bay Rail Link — Website queenslandrail.com.au Technical Line length …   Wikipedia

  • High-speed rail in China — This article is about high speed rail in the People s Republic of China. For high speed rail in the Republic of China (Taiwan), see Taiwan High Speed Rail. High speed rail (HSR) trains in China A China Railways CRH1 train in Guangzhou. CRH1 is… …   Wikipedia

  • List of tram and light-rail transit systems — The following is a list of cities that have tram / light rail systems as part of their public transport system. See also: * List of United States Light Rail systems by ridership * List of town tramway systems * List of rapid transit systems *… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”