Christmas Creek mine

Christmas Creek mine
Christmas Creek mine
Location
Christmas Creek mine is located in Australia
Christmas Creek mine
Location in Australia

22.379427°S 119.849593°E / 22.37943°S 119.84959°E / -22.37943; 119.84959Coordinates: 22.379427°S 119.849593°E / 22.37943°S 119.84959°E / -22.37943; 119.84959

Location Pilbara
State Western Australia
Country Australia
Owner
Company Fortescue Metals
Website Fortescue website
ASX FMG
Production
Products Iron ore
Production 16 million tonnes/annum
History
Opened 2009

The Christmas Creek mine is an iron ore mine located in the Pilbara region of Western Australia, 61 kilometres south-south-west of Nullagine, in the Chichester Range.[1]

The mine is fully owned and operated by the Fortescue Metals Group, FMG, and is one of two iron ore mines the company operates in the Pilbara, the other being the Cloud Break mine, located 50 kilometres west of Christmas Creek.[2]

Fortescue is the third-largest iron ore mining company in the Pilbara, behind Rio Tinto and BHP Billiton.[3]

Overview

Iron ore mines in the Pilbara region

Fortescue acquired the Cloud Break and Christmas Creek tenements during 2003. The company began constructing port facilities at Port Hedland in February 2006, followed by a A$3.2 billion capital raising in August 2006 to finance its projects.[4] Construction on the Cloud Break mine began in October 2006[5] and Fortescue began mining at Cloud Break in October 2007.[4] Iron ore production at the mine began in 2008 and, in its first full year of operation, the mine produced 28 million tonnes of iron ore.[2]

The ore from the mine is processed on site. Initially, it was loaded onto trucks and transported to Cloud Break and then on to the coast at Port Hedland through the Fortescue railway, where it is loaded onto ships. Construction on a 280-kilometre-long railway from Cloud Break to the Herb Elliott Port at Point Hedland was begun in November 2006. The line was scheduled to be fully operational within 18 month. A cyclone in March 2007 killed two workers at the project and led to delays. The first train from the mine to the port travelled on 5 April 2008.[6] A 50 km railway linking Christmas Creek to Cloud Break, allowing ore to be taken all the way to the port by rail, opened in December 2010; further improvements to railways are planned.[7]

The mine's workforce is on a fly-in fly-out roster.[8]

Originally, FMG planned to increase the production at Cloud Break to 55 million tonnes through a US$220 million upgrade of the plant, but this had to be abandoned in October 2009 because of funding difficulties through its Chinese investors. Instead, Fortescue decided to develop the Christmas Creek deposit, at a cost of US$360 million, by building a mine and process plant there and linking it to its existing rail network. Christmas Creek is scheduled to produce 16 million tonnes of iron ore in its first year of operation. Fortescue plans to reach an annual production of 95 million tonnes of iron ore by 2012, downgraded from an earlier target of 120 million.[9]

The Christmas Creek operation began transporting ore by truck to Cloud Break for processing in June 2009.[3] Construction on the processing facility began in November 2009 and is expected to be completed within 13 month.[10][11] Commissioning of the new ore processing facility at Christmas Creek is scheduled to begin in February 2011.[12]

References

  1. ^ MINEDEX website: Christmas Creek search result accessed: 6 November 2010
  2. ^ a b Mining Fortescue website, accessed: 9 November 2010
  3. ^ a b Western Australian Mineral and Petroleum Statistic Digest 2009 Department of Mines and Petroleum website, accessed: 8 November 2010
  4. ^ a b History Fortescue website, accessed: 9 November 2010
  5. ^ Work begins on Cloud Break mine ABC News, published: 24 October 2006, accessed: 9 November 2010
  6. ^ Fortescue opens the world's heaviest haul railway Railway Gazette International, published: 14 July 2008, accessed: 6 November 2010
  7. ^ "Railway Gazette: Heavy haul expansion plan approved". http://www.railwaygazette.com/nc/news/single-view/view/heavy-haul-expansion-plan-approved.html. Retrieved 2011-02-13. 
  8. ^ Sucked in The Australian, published: 4 April 2008, accessed: 9 November 2010
  9. ^ "Fortescue Metals Group's China funding flops" The Australian, published: 13 October 2010, accessed: 9 November 2010
  10. ^ Fortescue to spend $360m at Christmas Creek mine to up output The Australian, published: 112 October 2009, accessed: 9 November 2010
  11. ^ Fortescue shares up on FY profit jump The Sydney Morning Herald, published: 26 August 2010, accessed: 9 November 2010
  12. ^ Ore dip fails to slow Fortescue progress The Age, published: 15 October 2010, accessed: 9 November 2010

External links


Wikimedia Foundation. 2010.

Игры ⚽ Поможем решить контрольную работу

Look at other dictionaries:

  • Cloud Break mine — Cloudbreak Mine Cloudbreak Mine in distance 2008 Location …   Wikipedia

  • List of Christmas films — Christmas or Christmas Day is a holiday[1][2][3] generally observed on December 25 (with alternative days of January 6, 7 and 19[4]) to commemorate the birth of Jesus, the central figure of Christianity.[5] …   Wikipedia

  • Christmas in the American Civil War — Santa Claus distributes gifts to Union troops in Nast s first Santa Claus cartoon, (1863) Christmas in the American Civil War (1861–1865) was celebrated in both the United States and the Confederate States of America although the day did not… …   Wikipedia

  • Channar mine — Location …   Wikipedia

  • Marandoo mine — Location …   Wikipedia

  • Mesa A mine — Location …   Wikipedia

  • Mesa J mine — Location …   Wikipedia

  • Mount Tom Price mine — The Mount Tom Price mine Location …   Wikipedia

  • Mount Whaleback mine — The process facility of the mine Location …   Wikipedia

  • Nammuldi mine — Location …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”