The Betuweroute is a
double track freight railway fromRotterdam to Germany. Betuweroute is the official name, after theBetuwe area through which it passes, but the line is popularly referred to as Betuwelijn, after an older track in the same region. The Germans have christened their part theHollandstrecke . Together they form Project nr. 5 ofTrans-European Transport Networks (TEN-T) [ [http://ec.europa.eu/ten/transport/maps/doc/axes/pp05.pdf Betuweroute and the TEN network] ]History
On
June 16 2007 theNetherlands ' Queen Beatrix presided over the opening ceremony for the section connecting Rotterdam km to mi|160 to the German border. [ [http://www.dutchnews.nl/news/archives/2007/06/first_freight_train_uses_betuw.php First freight train on the Betuweroute] ] Ignoring the TEN-T and bilateral agreements, the Germans will not complete reconstruction of their section before 2015. [ [http://www.dutchnews.nl/news/archives/2007/09/germany_ignores_betuwelijn_rai.php Germany ignores Betuwelijn] ]Preliminary investigations into the future of west-east transport began in 1985 by the "commissie Van Bonden". In 1992 the German and Dutch governments signed the Verdrag van Warnemünde, a treaty on enhancing rail traffic, especially on the tracks from
Amsterdam and Rotterdam toDuisburg . The original plans foresaw three branches towards Germany. However, the northern branch viaOldenzaal was discarded in 1999 and the southernmost track viaVenlo saw the axe in 2004. In the same year, the court forbade the construction of a largelogistics centre nearValburg . Work on the Dutch part of the track began in 1998. Delayed by two years, the railway was finished mid 2007, to a cost of 4.7 billion euro, two times the original budget of 2.3 billion euro, and a fourfold of the initial 1.1 billion euro estimation in 1990.Project management hope 150 freight trains per day will be using the new line within five years. Due to problems with safety equipment, and the unfinished German connection, traffic is still marginal by December 2007. [ [http://www.dutchnews.nl/news/archives/2007/08/betuwe_railway_line_still_not_1.php Marginal use of Betuweroute] ]
Controversy
During its construction many
Dutch people and experts were opposed to the Betuweroute. The Dutch department for transport received 14.000 complaints against the northern branch alone, which was cancelled in 1999. Groen Front (Green Front), one among dozens of activist groups, accounted for 35 confrontations in 1999-2001. [ [https://ssl.direkte-aktie.net/cms/groenfront.php?itemid=668 35 actions by Groen Front against the Betuweroute, 1999-2001] Dutch] The main concerns about the Betuweroute were:* Cost - Even at the original budget of 2.3 billion euro, there was much discussion about economic viability. Initial hope to attract private investors turned out to be totally unfounded. In 2000 the
Algemene Rekenkamer (General Chamber of Auditors) convicted the government on having issued unrealistic forecasts about cost, environmental effects and usage of the Betuweroute, as well as insufficient cost control. They stated that promoting river transportation should have been considered as a realistic alternative. In 2004 theCentraal Planbureau (Bureau for Economic Policy Analysis), concluded that the construction would never pay back.* Landscape - Fears of ravaging the
Groene Hart and theBetuwe . The Groene Hart (Green Heart) of theRandstad is a more or less rural area amidst Holland's largest cities; the Betuwe is a less densely populated green region along the large Dutch rivers. Both feature classic Dutchpolder landscape. The opposition to the original plans forced the construction of additional tunnels, driving the budget further up.* Environmental issues - Worries about noise, spilling of dangerous chemicals and splintered animal
habitat s caused many environmentalists to fiercely resist the new track. In response, extra noise isolating panels, tunnels and wildlife passages were built.* Alternatives - As the Algemene Rekenkamer concluded in its 2000 report, river transport was and still is a realistic alternative. It is cheaper, more flexible, safer and not much slower. The Dutch
barge fleet is the largest and among the most modern in Europe, [ [http://informatie.binnenvaart.nl/document/Marktobservatie_2006_I_nl.pdf River transportation: Market observation 2006] Dutchbarge fleet accounts for more than 50% of total tonnage inRhine and Meuse basins, (p42). And is the most modern, second only to the German fleet, (p55). Dutch] well capable of handling the transport to the German industrial heartland, nearly without any investment by the government. The great Dutch riversMerwede ,Waal and parts ofRijn ,Maas ,IJssel andLek run roughly alongside the Betuweroute. The same goes for the A15 [ [http://nl.wikipedia.org/wiki/Rijksweg_15 A15, Highway parallel to the Betuweroute. Dutch] ] , an excellent albeit congested highway, which parallels the railway for km to mi|95.Several parts of this "Controversy" section are based on a Dutch scientific investigation [ [http://www.werkmarkt.nl/water/HoeSpoort.pdf Rail transport vs. river transport. Scientific investigation on costs, safety, environment.] Dutch]
pecifications and Features
* The route is electrified with
25 kV AC and signalled with the ERTMS2 security system. Electrification complies to new European standards, but current Dutch locomotives can not ride this track, as they use a different voltage. German locomotives use the right voltage, but the German part of the route does not comply with the new European standard security system, severely limiting usablility of the track. First new-spec locomotive delivered toRailion December 2007.* Tunnels, electrification and other parts of the railway are engineered to allow double stacked container trains, although no such trains will be in use for years to come.
*For the section from
Rotterdam to the largeclassification yard Kijfhoek existing track could be reconstructed, but three quarter of the line is new, from Kijfhoek toZevenaar near the German border.* Total length of noise isolating panels on both sides is km to mi|160, the same as the track length.
* Roll bars along the track keep derailed cars from toppling.
* 5 Tunnels and several roofed sections add up to a length of km to mi|20.
* 190 Passages for crossing
wildlife .* 130 Bridges and viaducts, no level crossings. [ [http://www.pieternieuwland.nl/Menu_Items/Vakken/Aardrijkskunde/betuwelijn/ Features of Betuweroute] Dutch]
* Capacity for 10 trains per hour in each direction, if the German safety gear and other infrastructure is updated.
Infrastructure
A lot of infrastructure was built or reconstructed to get the trains rolling. The most striking works:
*container terminal s in Rotterdam: Rail Service CentreMaasvlakte and Rail Service CentreWaalhaven .
* The km to mi|3 longBotlek spoortunnel under Rotterdam harbour replaces the antiquated Botlek bridge, which remains in service as backup and for regional traffic. Space around the tunnel was so constrained that, after completing the first tube, thetunnel boring machine had to be dismantled inside the tube. The parts were then returned to the starting point and reassembled to drill the second tube.
* ReconstructedClassification yard Kijfhoek betweenBarendrecht andZwijndrecht . [ [http://www.sporenplan.nl/html_nl/sporenplan/ns/ns_normaal/kfh.html Track plan Classification yard Kijfhoek] ]
*Barendrecht station, where 9 tracks cross on two levels. The station is part of a km to mi|1.5 long structure, much of it covered under a layer of ground, to keep noise at bay. On top is a new city park.
* Tunnel under Pannerdensch Kanaal nearAngeren . Instead of the projected bridge, a km to mi|2.7 tunnel was bored, to spare landscape and environment. The tunnel entrances were designed to blend with the landscape. The tunnel itself has large lock doors at each end, to prevent a flood on one side of the canal from inundating the region on the opposite bank. Because two endangered animal species were found in the vicinity of the tunnel, a new habitat was laid out for theGreat crested newt and theNatterjack Toad , as this video shows. [ [http://www.betuweroute.nl/files/milieu.wmv Short video about new habitat for the Great crested newt, Dutch spoken] ]Route
The route is a direct line from the
Maasvlakte toZevenaar , connectingEuropoort toGermany .Compared with the previous rail route between
Barendrecht and Elst the main deviations are:
* Line now north of Zwijndrecht andPapendrecht
* Line now north ofGorinchem and south ofLeerdam
* Line now north ofTiel
* From the south side ofElst the line runs straight toZevenaar .Municipalities
Municipalities along Betuweroute:
*
Alblasserdam
*Barendrecht
*Bemmel
*Buren
*Duiven
*Geldermalsen
*Giessenlanden
*Gorinchem
*Graafstroom
*Hardinxveld-Giessendam
*Heerjansdam
*Hendrik-Ido-Ambacht
*Lingewaal
*Neder-Betuwe
*Neerijnen
*Nijmegen
*Overbetuwe
*Papendrecht
*Rijnwaarden
*Rotterdam
*Sliedrecht
*Tiel
*Zevenaar
* ZwijndrechtExternal links
* [http://en.betuweroute.nl/home?setlanguage=en Betuweroute official website]
** [http://www.betuweroute.nl/home/aanleg_&_voortgang/tracekaart/tracekaart2?mode=view Map of route]
* [http://nl.wikipedia.org/wiki/Betuweroute Dutch Wikipedia on Betuweroute]
* [http://nusearch.ilse.nl/searchresults.jspx?search_for=betuwelijn Headlines.] Dutch
* [http://proto.thinkquest.nl/~jrb116/tunnel-1.php Tunnel under Pannerdensch Kanaal] . Dutch
* [http://www.uni-muenster.de/HausDerNiederlande/Zentrum/Projekte/NiederlandeNet/NRW-BeNeLux/einleitungbetuwe.html Decision process and construction of Betuweroute, 1985-2007] GermanReferences
Several parts of this article are based on: cite web| url=http://www.uni-muenster.de/HausDerNiederlande/Zentrum/Projekte/NiederlandeNet/NRW-BeNeLux/einleitungbetuwe.html| title=Decision process and construction of Betuweroute, 1985-2007| language=German|
Wikimedia Foundation. 2010.