Mariinsky Theatre Second Stage

Mariinsky Theatre Second Stage
Construction progress as of June 2009

The Mariinsky Theater Second Stage is a planned second part of a theatre complex which will be made up of the original 1860 Mariinsky Theatre and the 2007 Mariinsky Theatre Concert Hall. The Second Stage is currently under construction and is being financed by the federal budget. Throughout construction, which began in 2003, various changes have had to be made and this has led to an increase in expenses.

The post-modernist French architect Dominique Perrault won a much-publicised contest for his design for a new home for the theatre,[1] which is to be located adjacent to the current building. At the same time, the historic original structure had been due to undergo a complete renovation and this was planned to begin in the Autumn 2006.

After seeing projected costs rise to $244 million (U.S.) from $100 million, the Russian government announced in November 2008 that it was killing the Perrault plan. The Russian Prime Minister Vladimir Putin overruled both Valery Gergiev (the artistic director of the Mariinsky Theatre) and the Minister for Culture, announcing in early June 2009 that there would be a new competition to solicit proposals. 15 proposals were received, a list which was then shortened to five. "We wanted to give the impression that although we were in a tense situation and we didn't want to delay forever ... no one felt like it was the best way to simply sit down quietly and say, 'You are a great architect; just come and do it,'" Mr. Gergiev explained.[citation needed]

With a budget of €295-million (about US $452-million), all of which will be paid by the Russian government with a completion date of no later than December 2011, the Canadian firm, Diamond and Schmitt Architects[2], prevailed over four other finalists, one of which came from Germany and three from Russia. The building has been hyped as "Russia's most important building project in 70 years". As noted by Mr. Diamond, (it is) "the first major opera house to be built in Russia since the Czars." [3]

Building construction history

At the end of the design competition for The Second Stage of the Maryinsky Theater in 2003, 11 proposals had been received. The winner was well-known French architect Dominique Perrault with «a gold cocoon» (an external cover of a building of the wrong form from glass and aluminium).

By 2005 experts discovered that detailed proposals presented by the competition winner did not meet Russian building codes. They failed to include sections relating to water supply, drainage, and ventilation [4]. The result was that in 2007, FGU ("Northwest management on building, reconstruction and restorations") terminated the contract with the French architectural firm.

However, in June of that year the new general contractor, "Joint-Stock Company "NPO" Georeconstruction-fundamentproekt", in a short space of time removed all 286 obstacles shown on the working drawings of Perrault. As had become clear, the winning design was far from that presented when it won the international competition. In particular, it was necessary to make changes - based on the Saint Petersburg climate - in order to strengthen load-bearing structures above which the gold cuplola would be located. As a result, the building would not look so open to the air.[5] By July, the project had been simplified as much as possible, and it was determined that it would "not intrude so much into the existing city environment", Gergiev said.[6] The height of the building was reduced and other elements were also reconsidered.

In 2008 the foundation work for the building of the theatre continued, but by April, it was found that the consistency of the soil under the construction area was unpredictable. (Later builders have compared the properties of the soil to those of sour cream). In order to overcome these problems, the builders strengthened the consistency of the soil to a depth of 12 to 14 metres and, as a result, cost estimates had to be increased.[7] Also, the builders informed the authorities that the construction of a glass dome, as planned by Dominique Perrault's architectural firm, was impossible. Therefore that part of the project would have to be changed.[8]

By June, the project had a new local architect partner, KB ViPS Architects, a firm working on high-rise and underground construction, and it became the third firm to work on the building.[9]

During 2009 foundation work was completed. Valery Gutovsky, the director of KB ViPS Architects, a specialist in high-rise and underground construction, became the new head of construction for the project.[10], and on 29 May Vladimir Putin held a meeting at which he confirmed that the building would be completed in 2011 at the cost estimated in the published budget.[11]

On 28 July the result of the last competition was announced, the winner being KB ViPS Architects, a specialist in high-rise and underground construction.[12] Within a month, a contract was signed with that company and construction proceeded, with some parts of the building then reaching a height 5 metres.[11] At the same time, according to Valery Gutovsky, the project was to be submitted to the town-planning council of St. Petersburg in October 2009 and to Glavgosekspertiza ("The General State Expert Review Department of the State Committee for Construction, Housing and Utilities" which was authorized to perform the state expert review of all projects by spring 2010.[10]. The construction cost was estimated at 8.5 billion roubles.[10]

Notes

  1. ^ "Competition winner - Dominique Perrault - Opera House Mariinsky II - Saint Petersburg, Russia", 7 July 2003. Original design plans and photos of the model from arcspace.com retrieved 2 August 2009
  2. ^ Diamond + Schmitt Architects website, in English
  3. ^ James Adams, "From Toronto with love, a new theatre for St. Petersburg: Diamond + Schmitt describes its plan for the Mariinsky Theatre in St. Petersburg as ‘a contemporary version of the St. Petersburg cityscape' ", The Globe and Mail (Toronto), 29 July 2009, on theglobeandmail.com
  4. ^ "The project of the second stage of the Maryinsky Theater is not accepted by "Glavgosekspertiza" Russian: Проект второй сцены Мариинского театра не принят в Главгосэкспертизе " (in ru). Radio Rossii, Saint Petersburg. Official website. 2005-12-30. http://www.rtr.spb.ru/radio_ru/radio_2005/news_detail.asp?id=2130. Retrieved 2009-08-01. 
  5. ^ Jasinskaja Russian: Анастасия Ясинская, Anastasia (2007-07-16). "Building anatomy: the Mix of French with Nizhniy Novgorod Russian: Анатомия здания: Смесь французского с нижегородским" (in ru). The appendix "the Real estate. Business walls" (Vedomosti). http://www.vedomosti.ru/newspaper/article.shtml?2007/07/16/129310. Retrieved 2009-08-01. 
  6. ^ "The Mariinsky Theatre-2 was reduced in height so as not to intrude so much on the city landscape, and it is less likely to be structurally unsoundRussian: Мариинка-2 стала ниже, чтобы не портить городской ландшафт, и меньше, чтобы не провалиться под землю" (in ru). Echo of Moscow. 2007-07-27. http://www.echomsk.spb.ru/content/store/default.asp?shmode=2&ids=438&ida=56087&idt=news. Retrieved 2009-08-01. 
  7. ^ "The second stage of the Maryinsky Theater has again risen in price Russian: Вторая сцена Мариинского театра снова подорожала" (in ru). Business Petersburg. 2008-04-02. http://spb.dp.ru/Default2.aspx?ArticleID=bec982e4-5824-4dec-bdcf-ceb76c8ec22f&ref=rss. Retrieved 2009-08-01. 
  8. ^ "At the second stage Mariinsky – problems with a dome Russian: У второй сцены Мариинского – проблемы с куполом" (in ru). Business Petersburg. 2008-04-30. http://www.dp.ru/a/2008/04/30/U_vtoroj_sceni_Mariinskog. Retrieved 2009-08-02. 
  9. ^ "Mariinsky. Second stage Russian: МАРИИНСКИЙ. Вторая сцена" (in ru). Information-service resource "Nevastroyka.Ru". http://www.nevastroyka.ru/1/44/. Retrieved 2009-08-02. 
  10. ^ a b c "The Mariinsky theatre-2 project will go in Glavgosekspertiza in the spring of 2010 Russian: Проект Мариинки-2 отправится в Главгосэкспертизу весной 2010 года" (in ru). kvadrat.ru. 2009-08-27. http://kvadrat.ru/news/27082009_proekt_mariinki2_otpravitsja_v_glavgosjekspertizu_vesnoj/. Retrieved 2009-08-30. 
  11. ^ a b "Mariinsky-2 has grown 5 metres in height Russian: Мариинка-2 выросла на 5 метров" (in ru). City (fontanka.ru). 2009-08-21. http://www.fontanka.ru/2009/08/18/120/. Retrieved 2009-08-21. 
  12. ^ "The winner of the competition for the second stage of the Mariinsky is named Russian: Назван победитель конкурса по второй сцене Мариинского" (in ru). Fontanka.ru. 2009-07-28. http://www.fontanka.ru/2009/07/28/088/. Retrieved 2009-08-02. 

External links


Wikimedia Foundation. 2010.

Игры ⚽ Поможем решить контрольную работу

Look at other dictionaries:

  • Mariinsky Theatre — Address 1 Theatre Square City Saint Petersburg Country Russia …   Wikipedia

  • theatre — /thee euh teuhr, theeeu /, n. theater. * * * I Building or space in which performances are given before an audience. It contains an auditorium and stage. In ancient Greece, where Western theatre began (5th century BC), theatres were constructed… …   Universalium

  • Timeline of largest projects in the Russian economy — Moscow International Business Center under construction …   Wikipedia

  • Sadler's Wells Theatre — Sadler s Wells redirects here. For the racehorse, see Sadler s Wells (horse). Coordinates: 51°31′46″N 0°06′22″W / 51.529444°N 0.106111°W …   Wikipedia

  • Valentina Matviyenko — Валентина Ивановна Матвиенко Matviyenko at the World Economic Forum in Davos, Switzerland; 2007 Chairman of the Federation Council …   Wikipedia

  • Municipal Theatre of Santiago — The Municipal Theatre of Santiago The Teatro Municipal is the most important stage theatre and opera house in Santiago, Chile. History and overview The Chilean government ceded a significant parcel of land in downtown Santiago to the municipality …   Wikipedia

  • performing arts — arts or skills that require public performance, as acting, singing, or dancing. [1945 50] * * * ▪ 2009 Introduction Music Classical.       The last vestiges of the Cold War seemed to thaw for a moment on Feb. 26, 2008, when the unfamiliar strains …   Universalium

  • La Bayadère — ( The Temple Dancer ) (RussianБаядерка Bayaderka ) is a ballet, originally staged in four acts and seven scenes, choreographed by the balletmaster Marius Petipa to the music of Ludwig Minkus. It was first performed by the Imperial Ballet at the… …   Wikipedia

  • Marius Petipa — Maestro Marius Ivanovich Petipa, Premier Maître de Ballet of the St. Petersburg Imperial Theatres. St. Petersburg, 1887. Birth name Marius Alphonse Petipa …   Wikipedia

  • Le Corsaire — is a ballet typically presented in three acts, with a scenario originally created by Jules Henri Vernoy de Saint Georges, loosely based on the poem The Corsair by Lord Byron. Originally choreographed by Joseph Mazilier to the music of Adolphe… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”