Margam Knuckle Yard

Margam Knuckle Yard

Coordinates: 51°33′58″N 3°46′06″W / 51.56613°N 3.76831°W / 51.56613; -3.76831

Margam Knuckle Yard
Margam Moor Shunting Yard - geograph.org.uk - 30365.jpg
Margam Knuckle Yard is located in Neath Port Talbot
{{{alt}}}
Margam Knuckle Yard

Red pog.svg Margam Knuckle Yard shown within Neath Port Talbot
List of places: UK • Wales • Neath Port Talbot

Margam Knuckle Yard (MG) is a railway yard in Margam, South Wales, on the South Wales Main Line, operated by DB Schenker Rail (UK). The yard is the major freight yard of the region, handling all of the rail freight movements from Port Talbot Steelworks, and most of the railfreight traffic around South Wales.

Contents

Background

Duffryn No.1 Yard, 1 June 1962

The development of Port Talbot as an industrial centre started from the turn of the 20th century. The need for iron and steel producers to now import both ore and fuel, brought about the development of Port Talbot Steelworks, Margam Steelworks and associated expansion of the Port of Port Talbot.

In 1894, the Port Talbot Railway and Docks Company had been formed to directly link the port to the various competitive railways, particularly the South Wales Mineral Railway and the Rhondda and Swansea Bay Railway; and the coal mines and ironworks in the surrounding Llynfi and Garw valley areas, via the Duffryn Llynvi and Porthcawl Railway. This facilitated a further extension to the dock facilities in 1898.[1]

The PTR&D had developed extensive railway yards surrounding the docks, particularly the pair of Duffryn Yards, Duffryn No.1 and Duffryn No.2. The PTR&D was absorbed by the Great Western Railway on 1 January 1922.[2]

Port Talbot area railway
Legend
Continuation backward
East to Cardiff Central
Straight track
Stormy Bank
Unknown BSicon "AKRZ-UKu"
M4 motorway
Stop on track
Pyle
Junction to left Track turning from right
Water Street Junction
Unknown BSicon "AKRZ-UKua" Unknown BSicon "AKRZ-UKue"
M4 motorway
Continuation to left Unknown BSicon "KRZu" Junction from right
Goods line to Tondu
Straight track Non-passenger station/depot on track
Margam Knuckle Yard
Junction from left Junction to right
Straight track Non-passenger end station
Port Talbot Steelworks (Port of Port Talbot)
Stop on track
Port Talbot Parkway
Unknown BSicon "AKRZ-UKu"
M4 motorway
Continuation forward
West to Swansea

Development

EWS Class 66 heads towards Margam Knuckle Yard with a load of steel empties

By the 1950s, a combination of factors was bringing about the need for the redevelopment of transport facilities at Margam. The steelworks had integrated under the British Steel Corporation, and the post-war planned Abbey Works had opened in 1951, and was fully operational by 1953.[3]

Further increases in the volume of goods handling at the port were restricted by the docks inability to handle the new bulk carriers, with the old docks unable to accept a ship of greater than 10,000 metric tons deadweight (DWT). In 1966, work commenced on the construction of the new Port Talbot Tidal Harbour, south-west of the existing docks system. Completed in 1970, it was the first dry-bulk cargo terminal in the UK capable of accepting ships in excess of 100,000 metric tons deadweight (DWT).

British Railways was modernising freight distribution, with the former bespoke creation of manually loaded wagons being replaced by larger, bogied bulk-freight wagons that were automatically loaded. This resulted in a need for both larger yards to handle the larger wagons, and fewer yards as high speed freight traffic ran between them to reduce spped of delivery for the customer. BSC was becoming BR's most important customer, with coal quickly traffic falling.

Hence, in 1960 the development and construction of Margam Knuckle Yard on a former landfill site to the west, along the lines of the PTR&D towards the Llynvi and Ogmore Railway, consolidated what was one of a series of new rail yard developments that supported major steel making facilities in the UK. The development at Margam also included the redevelopment of locomotive maintenance facilities, with the co-development of Margam TMD.

Operations

EWS Class 66 climbs Stormy Bank with a full load of Merry-Go-Round coal hoppers, after leaving Margam Knuckle Yard

The strategy of BSC had resulted in an integrated facility plan, with Port Talbot at the centre of steel making system:[4]

  • 4.7million tonnes of raw iron ore used at Port Talbot/Llanwern steelworks
  • 3.0million tonnes of steel produced at Port Talbot
  • Steel output was then taken by railway to:
    • Shotton for coating
    • Trostre for tin plating
    • Ebbw Vale rolling and coating
    • Direct to the Midlands motor industry, via Toton Marshalling Yards

However, British Rails biggest problem was the 1.7million tonnes of raw iron ore required to be transported by rail to Llanwern Steelworks. Marshalling 27 x 100T Iron Ore tipplers, the train was initially headed by 3 x Class 37/0's, which continually caused problems with their couplings. The amount of power was required to climb Stormy Bank, located just west of Margam, where the train would only reach 8 miles per hour (13 km/h) at the top. Eventually replaced by 2 x Class 56's, drivers reported that this combination could reach 12 miles per hour (19 km/h). After experimentation with 2 x refurbished Class 37/7's, the company specially hired-in National Power's newly purchased Class 59/2. By January 2008, EWS was handling all 4.7million tonnes of steel product using either Class 60 or Class 66. With the closure of Margam TMD, locomotive maintenance had moved to Knuckle, with C-Class services and brake tests requiring locomotives to be shipped to Toton TMD.[4]

Margam Knuckle handles other goods shipped through the port, as well as regional traffic including shipments to/from RNAD Trecwn.[4]

The yard is about 1 mile (1.6 km) east of Port Talbot Parkway, with few facilities and no bridges by which rail spotters can see operations.

See also

References

External links


Wikimedia Foundation. 2010.

Игры ⚽ Нужно решить контрольную?

Look at other dictionaries:

  • Margam TMD — was a railway locomotive Traction Maintenance Depot situated in Port Talbot, South Wales. The depot code was MG, which has now been re allocated to Margam Knuckle Yard service point. Built to replace the existing Margam Depot and for the co… …   Wikipedia

  • Port Talbot Steelworks — is an integrated steel production plant in Port Talbot, Wales capable of producing nearly 5 million tonnes of steel slab per annum. The majority of the slab is rolled on site at Port Talbot and at the Newport Llanwern site to make a variety …   Wikipedia

  • Neath Port Talbot — County Borough Bwrdeisdref Sirol Castell nedd Port Talbot Area Total  % Water Ranked 11t …   Wikipedia

  • Neath and Tennant Canal — The exit from Clun Isaf lock, restored in 2007 Original owner Neath Canal Nav Co, Port Tennant Nav Co Principal engineer …   Wikipedia

  • National Cycle Route 4 — (or NCR 4) is a route of the National Cycle Network, running from London to Fishguard. Between London and Fishguard, the route runs through Reading, Bath, Bristol, Newport, Swansea, Llanelli and St David s. Within Wales, NCR 4 forms one of the… …   Wikipedia

  • Celtic Trail cycle route — Marker on the Celtic Trail cycle route (National Cycle Network 47) The Celtic Trail is a network of dedicated cycle routes in the National Cycle Network, crossing West, South and Mid Wales, and covering 377 miles in total. It is divided into east …   Wikipedia

  • Neath railway station — Neath Castell nedd Location …   Wikipedia

  • National Cycle Route 43 — National Cycle Network, Route 43 is part of the National Cycle Network and the Celtic Trail, which connects Swansea with Builth Wells. Most of the route is still awaiting development. As of June 2006, there is a 13 mile section out of Swansea… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”