Hickory Log Creek

Hickory Log Creek

Hickory Log Creek is a stream which runs from northest and north-central Cherokee County, Georgia, south-southwest to the northeastern part of Canton, the county seat. It is a tributary of the Etowah River, which it meets shortly after crossing under Riverstone Parkway (formerly Ball Ground Highway and Georgia 5).

Dam and reservoir

Hickory Log Creek Dam is a 180 foot high roller compacted concrete dam just north of the Riverstone business district in Canton, and just west of Bluffs Parkway. The City is partnered with the Cobb County-Marietta Water Authority (CCMWA) to build the dam. Hickory Log Creek Reservoir is a drought contingency reservoir provides an additional source of drinking water for the area.

The dam is approximately 950 feet or 290 meters wide, and 180 feet or 55 meters high, making it one of largest dams in the state of Georgia not built by the Corps of Engineers or Georgia Power. Construction was completed December 2007, and filling of the reservoir will take another two years. [cite web
url = http://www.hickorylogcreek.com/
title = Hickory Log Creek Dam and Reservoir
year = 2007
] This, however, greatly depends on the drought which is currently affecting the region.

The reservoir covers 411 acres or 1.66 square kilometers when full, and offers 15 miles or 24 kilometers of shoreline. At capacity, it will hold about six billion gallons or nearly 22.8 billion liters of water. It is permitted for a withdrawal of 39 million gallons or 147.6 million liters per day, which will be shared by Canton and CCMWA. In addition to the dam and reservoir, the project also includes an intake and pump station, plus a pipeline to transport water between the reservoir and the Etowah River.

Several miles or kilometers of the creek will be submerged, and convert|411|acre|km2 of native and mostly hardwood trees are being clear-cut for the lake. It will also receive runoff directly from Bluffs Technology Park, an industrial park constructed immediately to the lake's east along Bluffs Parkway, in what is now forested and very hilly area just west of Interstate 575.

Partnership

The City of Canton and the CCMWA formed their partnership to meet the long-term water supply needs of the region. All costs of the project are being split 25/75, proportionately to the amount of water to be used by each. 25% of the water will go to Canton, and 75% to Cobb and the parts of the neighboring counties it sells to: south Cherokee, Paulding, and Douglas. This is partially an interbasin water transfer, since most of Cobb, Douglas, and southwest Paulding are in the Chattahoochee River basin.

The CCWSA purchased Pilgrim's Pride's discharge permit to be able to build a new northwest Cherokee sewage treatment plant. The Georgia Environmental Protection Division approved a northeast Cherokee waste water treatment plant, even though it flows to the same lake that cannot accept any additional load because non-point source pollution has maxed-out its capacity. In light of this, the GAEPD has tightened restrictions on emmissions from existing WTPs in the basin to prevent further non-point source pollution into Lake Allatoona.

Pump station

Because the creek is not very large, the pump station will ultimately pull water from the Etowah River and pump it into the Hickory Log Creek Reservoir. A 54 inch diameter ductile iron pipe connects the intake to the pump station (located behind the Waffle House on old highway 5) and then a 42-inch (107cm) diameter pipe, slightly more than a mile or 1.6 km long, will connect the pump station to the reservoir.

Equipment will include 3-28MKM, five-stage fresh-water verticle turbine pumps, each capable of producing 9028 gallons or 34,171 liters per minute, at 247 or 75.3 meters, at 880 RPM. The units are powered by 700-horsepower (522-kilowatt mechanical force) high-inertia motors.

Water usage

The reservoir supplements the city’s existing raw water supply, the Etowah River. Water from the reservoir will go to residents who use the city’s water service and CCMWA’s numerous wholesale customers in the region. Currently, the city serves approximately 6100 customers, and the reservoir is forecast to help Canton continue to meet its water supply needs through 2050, even factoring in growth projections.

Alabama permit challenge

The reservoir was given a permit by the Corps in 2004, as it is in the headwaters of ACT river basin, its water later flowing into the Coosa River and in turn the Alabama River and Mobile Bay. Despite being nearly complete in late October 2007, the state of Alabama amended its complaint in U.S. federal court against the Corps, trying to force it to revoke the permit and start the entire process over again, giving more consideration to its downstream effect on Alabama.

This particular filing was likely in reaction to Georgia's aggressive actions to keep more water during the drought (in this case, particularly Lake Allatoona not far downstream), but is part of the so-called "tri-state water war" that has been ongoing in court since 1990.

Construction info

The dam is constructed using roller-compacted concrete or RCC. Overall, the dam's design called for the use of about 225,000 cubic yards or 172,000 cubic meters of RCC. ASI Constructors produced the RCC on-site in a Johnson-Ross batch plant, utilizing aggregate from the nearby Lafarge quarry in Ball Ground, and cement from Signal Mountain Cement Co. Fly ash was also utilized in the mix design. The six-yard plant typically produced about 350 cubic yards or 268 cubic meters of RCC per hour.

The mix was delivered to the dam via a conveyor system, manufactured, installed and maintained by Rotec Industries. An initial conveyor run of about 700 feet or 213 meters carried the mix from the plant up the hill to a transfer station; from there, a second conveyor transported the mix along the top of the dam to a "tripper". The tripper, which could be positioned along the second conveyor's run, diverted the RCC from the distribution conveyor and discharged it onto the working surface at the desired location.

As the RCC was discharged by the tripper, it was spread in 12-inch (30cm) lifts by a bulldozer. Initially, during placement of the first lifts of RCC, a small Komatsu D21A bulldozer was used for maximum maneuverability. Then, as RCC placement continued and placement rates increased, the team switched to a larger Caterpillar D5MXL and then to an even larger Deere 850 dozer outfitted with wings on the blade. Toward the top of the dam, as the working area began to narrow, the Cat D5MXL was again called into service.

As the dam's elevation increased, the columns supporting the second stage of the conveyor system were raised using hydraulic jacks. Typically, the conveyor was raised about every two days. As the support columns were jacked up, they left behind openings in the RCC which provide drainage or ventilation to the gallery.

After being spread by the dozer, the RCC was compacted by a pair of Ingersoll Rand rollers — a DD125 and, for working close to the edge forms, a DD24. Additionally, vibratory plate compactors were used to compact the mix near the edge forms and around various penetrations.

On the downstream side of the dam, the RCC face will be visible. To enhance the appearance of those faces, the construction team utilized so-called grout-enriched RCC to yield a smoother face. This involved placing uncompacted RCC along the form edges, applying a neat cement grout onto the RCC surface, then vibrating the grout into the RCC to enhance a narrow zone of RCC and thus yield a smooth formed face. Komatsu and Deere loaders were used to transport the facing concrete from ready mix trucks to the locations where it was used.

Much work happened behind the scenes before actual construction on the project began, such as evaluating the dam site and designing the various structures: the dam, intake and pump station, and a pipeline. During the design and construction phases, the project will underwent review by the city, CCMWA and Georgia Safe Dams, which is a program managed by the state Environmental Protection Division. The schedule also included time to hire construction companies to build the projects. [cite web
url = http://www.acppubs.com/article/CA6449514.html
title = Article by Dixie Contactors
year = 2007
]

Multiple cranes

Because of the location and layout of the site, a key factor in maintaining production was ensuring that materials and equipment could be delivered to the dam construction crew where and when they were needed.

To that end, the team utilized four large cranes on the project — a Kobelco 100-ton crane on one end of the dam, a Liebherr 120-ton crane on the other end, a Manitowoc 4100 on the downstream side, and a Manitowoc 888 on the upstream side — as well as smaller cranes and lifts elsewhere as needed. Having multiple cranes on-site allowed maximum lifting flexibility at any point on the dam. [cite web
url = http://www.acppubs.com/article/CA6449514.html
title = Article by Dixie Contactors
year = 2007
]

Form work

The dam is designed with a flat and vertical upstream face and a stepped downstream face. Its downstream steps were formed using wood forms, creating steps with a height of three feet (90cm). On the upstream side, the team used precast stay-in-place concrete form panels — typically measuring 16 feet by 6.5 feet with a thickness of 5 inches (488×198&times13cm) — to define the face of the dam. The inside face of each of these panels is lined with an impervious geomembrane. Crews fabricated and cast these panels at an on-site precast yard.

To anchor these upstream forms during RCC placement and compaction, permanent anchors extending back into the RCC were attached to the inside face of each form panel. Additionally, temporary exterior steel stiffbacks were installed to provide additional support. Overall, the design utilizes close to 1,100 of the panels.

Not all formwork was on the outside of the dam. The Hickory Log Creek dam includes an inspection/drainage gallery which has been constructed deep within the dam itself. This gallery has a width of convert|7|ft|m and a height of convert|8|ft|m. The walls were formed during RCC placement using removable metal forms; gallery ceiling was constructed using precast reinforced concrete roof panels. Access stairways have also been incorporated into the mass structure. The presence of these openings and passages complicated construction somewhat but allows for easy instrumentation, drainage from the foundation drains and interior inspection of the structure.

Temperature issues

Temperature is a concern during any Dam project, particularly one such as this where such a large volume of roller-compacted concrete or RCC is being placed. RCC produces heat as it hydrates and cures, and that heat can cause cracking if it is excessive.

To avoid overheating problems, RCC placement was scheduled to avoid the heat of day. Placement typically began at about 5PM (17:00) and continued through the night, wrapping up mid-morning before temperatures got too high.

Temperature management was further aided by the fact that most of the aggregate was stockpiled last winter, during cold weather. The core of the aggregate pile remained cool even as the weather warmed — an additional aid in controlling mix temperature. Should ambient temperatures have risen too much, the team had the ability to add liquid nitrogen to the mix to lower the temperature further.

Temperature was also a major factor in determining whether bedding mortar was used between each placement session. Although bedding mortar was used in a narrow zone on the upstream side and at each abutment contact at the beginning of each day's RCC placement, it was only necessary to bed the entire lift if the "degree-hours" (that is, the product of the temperature and time between lifts) exceeded 500 degree hours.

References

External links

* [http://www.hickorylogcreek.com Hickory Log Creek Dam's official website]


Wikimedia Foundation. 2010.

Игры ⚽ Поможем написать курсовую

Look at other dictionaries:

  • Battle Creek, Michigan — Battle Creek redirects here. For other uses, see Battle Creek (disambiguation). Battle Creek, Michigan   City   …   Wikipedia

  • List of dams and reservoirs in the United States — This list is incomplete; you can help by expanding it. The following is a partial list of dams and reservoirs in the United States. There are an estimated 75,000 dams in the United States, impounding 600,000 mi (970,000 km) of river or about 17%… …   Wikipedia

  • List of reservoirs and dams in the United States — There are an estimated 75,000 dams in the United States, blocking 600,000 miles (960,000 km) of river or about 17% of rivers in the nation . [cite web|url=http://www.pcffa.org/dams.htm |title=Dams and salmon |accessdate=2008 02 11] The following… …   Wikipedia

  • Canton, Georgia — Infobox Settlement official name = Canton, Georgia postal code type = ZIP codes postal code = 30114, 30115, 30169 area code = 770 blank name = FIPS code blank info = 13 12988GR|2 blank1 name = GNIS feature ID blank1 info = 0331320GR|3 footnotes …   Wikipedia

  • Etowah River — The Etowah River rises northwest of Dahlonega, Georgia, north of Atlanta. Its name is the Cherokee version of the original Muskogee word Etalwa which means a trail crossing. On Matthew Carey s 1795 map the river was labeled High Town River. On… …   Wikipedia

  • Dawson Forest — is a 10,130 acre (41.0 km2) public use forest located in Dawson County, Georgia, southwest of Dawsonville. It is owned by the city of Atlanta, but is considered a state forest, as it is managed by the Georgia Forestry Commission. It was… …   Wikipedia

  • Cherokee County, Georgia — Location in the state of Georgia …   Wikipedia

  • Andrew Jackson — Infobox President | name=Andrew Jackson nationality=American order=7th President of the United States term start=March 4, 1829 term end=March 4, 1837 predecessor= John Quincy Adams successor= Martin Van Buren order2=1st Territorial Governor of… …   Wikipedia

  • National Register of Historic Places listings in Davidson County, Tennessee — Location of Davidson County in Tennessee This is a list of the National Register of Historic Places listings in Davidson County, Tennessee. This is intended to be a complete list of the properties and districts on the National Register of… …   Wikipedia

  • Forest Hills, Tennessee — Infobox Settlement official name = Forest Hills, Tennessee settlement type = City nickname = motto = imagesize = image caption = image mapsize = 250px map caption = Location of Forest Hills, Tennessee mapsize1 = map caption1 = subdivision type =… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”