- U.S. Route 48 in West Virginia
The
U.S. Route 48 designation has not yet been applied in West Virginia due to major segments of highway either under construction or under planning. The designation will follow Corridor H fromInterstate 79 in Weston eastward toVirginia .West Virginia's segment of Corridor H crosses very mountainous terrain, some of the most rugged in the eastern United States and crosses two major rivers. There are more than 1000 historic structures, five historic districts, two Civil War battlefields and other archaeological sites within five miles (8 km) of Corridor H, and the highway will cross through two national forests. There are over 50 species of plants and animals that are protected under the
Endangered Species Act and more than 150 native trout streams, thousands of acres of wetlands and high mountain bogs, areas of karst terrain, abandoned coal mines and numerous recreational facilities within the Corridor H study area.History
Weston to Elkins
Corridor H was originally envisioned as an Appalachian Regional Development corridor highway that was to run from
Weston, West Virginia to Strasburg orNew Market, Virginia viaElkins, West Virginia . This proposed four-lane highway soon became one of the most controversial APD corridor highways inWest Virginia that would lead to numerous legal (and political) battles within the state. The state was forced to deal with numerous Environmental and economic issues, a battle that would continue for 40 years.The route was to follow
U.S. Highway 33 from Weston toSeneca Rocks, West Virginia , where two proposals called one alignment to follow a new alignment over North Fork Mountain and Foremost Mountain toNew Market, Virginia , while another proposal called for an alignment paralleling WV 55/VA 55 toStrasburg, Virginia . A timeline of construction completions are as followed: Release Date Report. West Virginia Department of Transportation. August 2003.]
* "1972": Milepost 19.62 to 20.61 opened to traffic. This was at theInterstate 79 interchange in Lewis county.
* "1975": Corridor H was extended further east from milepost 20.61 to 23.62 at Homer and county route 15 in Lewis county.
* "1976": A six-mile (10 km) segment was opened to traffic from milepost 23.62 at Homer and county route 15 in Lewis county to the Upshur county line (MP 27.04), and from milepost 0 to 1.22 in Upshur county near Lorentz. Also completed was the "racetrack" portion of Corridor H east of Elkins, from Canfield to Bowden. A northern bypass of Elkins was to connect the "racetrack" to portions of Corridor H west of the city. This bypass was never constructed.
* "1979": Three-miles were completed in Upshur county from milepost 1.22 to 4.35 near Lorentz.
* "1991": A three-mile (5 km) section of highway opened from milepost 4.35 near Lorentz to 8.31 at Buckhannon in Upshur county.
* "1994": The longest section of Corridor H from Weston to Elkins opened from milepost 8.31 to 15.40 in Upshur county, continuing into Barbour county from mileposts 0 to 4.43, and into Randolph county from mileposts 0 to 4.17. The total mileage for the final Weston to Elkins segment came in at convert|15.69|mi|km.Approximately convert|40|mi|km was completed from Interstate 79 at Weston to Elkins.
Elkins to the Virginia state line
Another convert|7|mi|km|sing=on segment was completed from Canfield to Bowden just east of Elkins and was dubbed the "racetrack" for its vast improvement over the old alignment and its isolation from other four-lane highways. A northern bypass of Elkins was to connect the two segments of Corridor H, however, it was never constructed as the segments east of Bowden were met with intense opposition. Meanwhile, an alignment following
U.S. Highway 33 to Seneca Rocks and then WV 55/VA 55 toStrasburg, Virginia was favored within theWest Virginia Department of Transportation .In 1981, the West Virginia Department of Transportation began planning for a new alignment east of Bowden along
U.S. Highway 33 and WV 55/VA 55."Corridor H Alternatives." Corridor H Alternatives Inc. 1999. 31 May 2005 [http://www.users.cloud9.net/~kenner/cha/CHhistory.html] .] "Corridor H Pro." West Virginia Department of Transportation 20 March 2003. December 2000 [http://www.wvcorridorh.com/route/timeline.html] .] A Draft Environmental Impact Statement (DEIS) was issued. Funding issues, however, caused the project to be put on hold until 1990. No Final Environmental Impact Statements or Record of Decisions were completed.In 1990, the project was resurrected and a reevaluation of the Corridor H alignment east of Bowden was conducted. A new DEIS was prepared and all corridors considered in the 1981 DEIS were studied equally. Scoping meetings were held that October. The purpose and need documentation was completed in March 1992 and a Corridor Selection Draft Environmental Impact Statement (CSDEIS) was completed in October.
In 1993, a revised EIS was published with a new route to go north from Elkins to Moorefield and then into
Virginia . Many citizens, however, felt that improving existing routes would be a better alternative. Of the 4,000 comments written in 1995 at public meetings, over half opposed the new Corridor H alignment. They cited the damage to two national forests, 41 streams, historical sites, Civil War battlefields, farms and Main Street businesses. For some, the costs outweighed the benefits.In October 1994, an Alignment Selection Draft Environmental Impact Statement (ASDEIS) was issued. The DEIS focused on alignment selection within the preferred corridor identified within the CSDEIS.
In April 1996, a Federal Environmental Impact Statement (FEIS) was issued that consisted of a revised version of the ASDEIS along with some of the CSDEIS. In September, a Record of Decision was issued on the preferred alignment east of Bowden.
Phase 1: Elkins to Kerens
In October 1998, the first contract for Corridor H's construction east of Elkins was awarded from US 33 to US 219.
A convert|5.48|mi|km|sing=on segment of Corridor H opened to traffic on August 12, 2002. [Corridor H Press Room. 5 August 2002. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/080802_wise.html] .] [Corridor H Route - Elkins to Kerens. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/route/map1.html] .] This segment of four-lane expressway stretches from CR 11 west of Elkins to CR 7 near Kerens and includes one interchange in the project for
U.S. Highway 219 . This was finished under six contracts totaling $87.6 million. The then GovernorBob Wise celebrated the historic opening with SenatorRobert C. Byrd and Transportation Secretary Fred VanKirk.On August 19, a three-mile (5 km) segment was dedicated from CR 1 to CR 23/4 that was constructed under two contracts totalling $24.1 million. This completed the nine-mile (14 km) phase one segment.
Phase 2: Kerens to Parsons
This convert|13.5|mi|km|sing=on segment of Corridor H travels through Randolph and Tucker counties; more specifically from county route 7 near Kerens to a future
U.S. Highway 219 interchange approximately two-miles east of Parsons. Proceeding northward from county route 7, it would have a span at Wilmouth Run and county route 3. The alignment then turns more northeastward, entering theMonongahela National Forest , crossing the South Branch of Hadix Run Road andU.S. Highway 219 . It has one final water crossing atCheat River before concluding at county route 219/4.In Parson's, a public informational meeting was held on September 26, 2000. Alignments were studied and a Settlement Agreement allowed construction to continue on segments in Hardy and Randolph counties. It was also chosen to avoid the Corricks Ford Battlefield.
Alternative "DF" was chosen as the preferred alternative for the highway and in October 2001, the Federal Highway Administration gave the go-ahead for the Supplemental Draft Environmental Impact Statement. [Corridor H Route - Kerens to Parsons. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/route/map2.html] .] The Federal Environment Impact Statement was completed in April 2002 with the Record of Decision approved in June of that year.
The Department of Highways received approval for the Supplemental Final Environmental Impact Statement in October 2002. The commenting period was extended 60 days to February 25, 2003. The Amended Record of Decision was approved on May 12, 2003.
Six consultants were hired to provide the final design for the convert|13.5|mi|km|sing=on segment of Corridor H from Kerens to Parsons. Final design has not yet been completed, with construction scheduled to begin in mid-2011.
Phase 3: Parsons to Davis
Phase III is a nine-mile (14 km) expressway from two miles (3 km) east of Parsons to immediately east of Davis along
West Virginia Route 93 within Tucker county.On December 4, 2002, the Supplemental Draft Environmental Impact Statement was approved after additional Environmental investigations were completed. The additional analysis was a result of the
West Virginia Northern Flying Squirrel , a federally endangered species that was discovered in the vicinity. A public hearing was held on February 6, 2003 at the Blackwater Lodge in Davis, with comments on the meeting turned in by April 22. The Thomas-Davis city council had until June 19 to review the situation. The Supplemental Final Environmental Impact Statement was expected to be approved on the segment in June 2005, with the FHWA expected to sign the Amended Record of Decision in August 2005, however, the discovery of theWest Virginia Northern Flying Squirrel delayed the project; WVDOH had to conduct additional environmental investigations. [Corridor H Route - Parsons to Davis. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/route/map3.html] .] [Corridor H - Davis / Thomas - Public Meetings. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/davisthomas/meetings/2603_pubmeet.html] .]The Supplemental Final Environmental Impact Statement is expected to be approved late 2006 with the Amended Record of Decision being approved in January 2007. Final design has not yet started, with construction scheduled for 2015.
Phase 4: Davis to Bismarck
This convert|16.5|mi|km|sing=on segment of Corridor H stretches through Tucker and Grant counties. The proposed alignment will run from
West Virginia Route 93 , 7/10 of a mile east ofWest Virginia Route 32 near Davis to Bismarck nearWest Virginia Route 42 , just south of the intersection ofWest Virginia Route 42 andWest Virginia Route 93 . The Federal Highway Administration issued a record of decision on March 23, 2001 that cleared the way for design, right-of-way purchases, and construction for this segment. Final design is currently underway; construction is scheduled for 2009. [Corridor H Route - Davis to Bismarck. West Virginia Department of Transportation. 1 Oct. 2006 [http://www.wvcorridorh.com/route/map4.html] .]Phase 5: Bismarck to Forman
Totaling convert|14|mi|km within Grant county, final design on this segment is nearing completion.
The record of decision was issued in July 2001. The original timeline was to begin acquiring right-of-way in June 2003, bid contracts in August 2004 and begin construction in September 2004 with a completion date in September 2006. Greenland Gap activists, however, began documenting the Gap's civil war history and natural features and successfully persuaded the West Virginia Department of Highways to move the alignment 1/4 of a mile away from the Gap. This spared several houses in a neighboring village and reduced the effect the highway would have on the Gap. A one-mile (1.6 km) access road between the village of Greenland and
West Virginia Route 93 was eliminated and an interchange was moved from between Greenland andWest Virginia Route 93 to two miles (3 km) north of Scherr forWest Virginia Route 93 .Construction should begin in spring 2007. [Corridor H Route - Bismarck to Forman. West Virginia Department of Transportation. 1 Oct. 2006 [http://www.wvcorridorh.com/route/map5.html] .]
Phase 6: Forman to Moorefield
The sixth phase in Corridor H's completion from Elkins to the state line, it travels through Grant and Hardy counties for a total length of convert|16|mi|km. This phase also includes three miles (5 km) of upgraded highway from US 220 to WV 55 just east of Moorefield; the mainlines for Corridor H are convert|13.8|mi|km.
The first section of this phase to open was a three-mile (5 km) four-lane highway from US 220 to the WV 55 interchange in November 2005."The Route - Forman to Moorefield." West Virginia Department of Transportation. 1 Oct. 2006 [http://www.wvcorridorh.com/route/map6.html] .] In August 2005, two grade and drain contracts were awarded on both sides of the South Branch Potomac River, with construction beginning that September. Construction is expected to be complete on both contracts by the spring of 2007.
In July 2006, two grade and drain contracts were awarded west of the South Branch Potomac River.
On August 8, 2006, it was announced that convert|1.75|mi|km were to be graded for paving at a cost of $23,747,933. ["Corridor H Rolls Into Grant County." 8 Aug. 2006 West Virginia Department of Transportation. 30 Oct. 2006 [http://www.wvdot.com/13_news/13_news_dtl.cfm?s=659] .] This segment began construction in September and is expected to be complete in August 2008.
During the same month, South Branch Potomac River Bridge contract was awarded. ["DOH Awards $30 Milion for South Branch Bridge." 26 Oct. 2006 West Virginia Department of Transportation. 1 Oct. 2006. [http://www.wvdot.com/13_news/13_news_dtl.cfm?s=664] .] The $30,884,656 contract, located just north of Moorefield, will contain a single eight-span convert|2135|ft|m|abbr=on steel girder bridge over the South Branch of the Potomac and a seven-span crossing over the adjacent flood plain. The bridge will utilize 4,300 tons of steel. Construction began in September with a completion date set for August 1, 2009.
It is anticipated that with the completion of the South Branch Potomac River Bridge, the Forman to Moorefield section will be open to traffic.
Phase 7: Moorefield to Baker
On May 31, 2000, ground was broke on the Moorefield to Baker section of Corridor H. Nearly 1,000 supporters were in presence. ["Governor Underwood and Senator Byrd Break Ground on Corridor H Project." Corridor H Pressroom. 31 May 2000. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/0531_breakground.html] .]
On June 1, 2000, the Advisory Council on Historic Preservation (ACHP) informed the "West Virginia Division of Highways that it has made a determination of the effects of an alternative alignment of Corridor H near Moorefield on historic properties." Sam Beverage, acting Secretary for the Department of Transportation, stated that the Meadows and the P.W. Inkeep House were both to the alignment chosen for Corridor H but would not be impacted.
June 5, 2000 was the starting date for two segments in Hardy county. convert|1.62|mi|km of partial controlled-access highway in the first segment, totaling $20,746,510 included 2,810,416 cubic yards (2,148,717 m³) of excavation, three access roads to farms, two structural plate drainage pipes and a six-span prestressed concrete beam bridge over Lick Run and CR 6."DOH Awards Additional Corridor H Contracts." Corridor H Pressroom. 5 June 2000. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/0605_doh_contracts.html] .]
Another segment at a cost of $12,499,009 was let to construction as well. convert|1.7|mi|km of highway would extend the first segment of Phase 7 to just south of the Baker interchange. This included 1,963,415 cubic yards (1,501,138 m³) of excavation, one farm access road, two structural plate drainage pipes and two out of the four ramps for the Baker interchange.
On August 30, 2000, convert|1.09|mi|km of four-lane divided highway was let to construction. ["WVDOH Announces Letting of Project." Corridor H Pressroom. 30 August 2000. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/083000.html] .] It stretched from CR 23/4 to CR 8 and had a price tag of $11.4 million.
On September 28, 2000, the Department of Transportation announced that the construction of a four-lane partial controlled-access highway connecting
West Virginia Route 55 to the Clifford Hollow Bridge will involve the construction of two bridges and convert|2.21|mi|km of roadway. ["DOH Awards Additional Corridor H Contracts." Corridor H Pressroom. 28 September 2000. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/092800_contracts.html] .] ["WVDOH Announces Lettings of Two Corridor H Projects." Corridor H Pressroom. 1 August 2000. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/080100.html] .] The cost for this segment was $29.6 million. A second project would connect the Clifford Hollow Bridge to county route 1 and involve convert|1.96|mi|km of construction at a cost of $15.2 million.A convert|1.09|mi|km|sing=on segment of roadway was let to construction on October 18, 2000 at a cost of $9,864,718. This segment stretched from CR 23/4 to CR 8. ["DOH Awards Contract for Corridor H." Corridor H Pressroom. 31 May 2000. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/101800_doh_awards_contract.html] .]
The final segment of Phase 7 was let to construction on November 2, 2000 for the Clifford Hollow Bridge at a cost of $17.8 million. It was completed in October 2003.
A three-mile (5 km) segment of highway from county route 1 to county route 23/9 opened to traffic in August 2002. On November 17, 2002, a five-mile (8 km) section of roadway opened from county route 23/9 to the Baker interchange. With the completion of the Clifford Hollow Bridge in October 2003, the convert|14|mi|km|sing=on segment of Corridor H through Hardy county between Moorefield and Baker was opened to traffic.
Phase 8: Baker to Wardensville
In December 2000, the Federal Highway Administration issued the Record of Decision on this convert|6.7|mi|km|sing=on segment of Corridor H. ["Baker to Wardensville Section of Corridor H Moving Forward." Corridor H Pressroom. 4 December 2000. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/120400_baker_wardensville.html] .]
A construction contract was awarded on October 1, 2001 to construct a segment of Phase 8 from Hanging Rock to county route 23/8 in Hardy county. ["WVDOH Awards Construction Contract for Corridor H." Corridor H Pressroom. 1 October 2001. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/100301_award.html] .] This segment is located just east of the Lost River bridge near McCauley and cost $12,891,522.
Another contract was awarded on December 5, 2001 at a total of $18,549,091 to construct convert|2.68|mi|km of Corridor H from county route 23/8 to the west approach of the Lost River bridge. ["Recent Contract Awards." Corridor H Pressroom. 5 December 2001. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/121901_awards.html] .] Grading and drainage required 3.3 million cubic yards (2,500,000 m³) of earthwork, including over 1 million cubic yards (800,000 m³) of "borrow" material and several convert|60|in|mm|sing=on pipes to carry small streams underneath the roadway. A three-span fabricated steel girder bridge was constructed to carry the four-lane divided highway over Sauerkraut Run.
December 21, 2001 was another important day, as a convert|1.45|mi|km|sing=on section was awarded at a cost of $25,019,472. ["WVDOH Awards Corridor H Contract." Corridor H Pressroom. 21 December 2001. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/122101_wvdohawards.html] .] It stretched from the Baker interchange and extended to the west side of the bridge crossing the Lost River in Hardy county. The remaining two incomplete ramps at the Baker interchange was completed.
On March 4, 2002, the Department of Highways awarded a contract to construct a convert|1.08|mi|km|sing=on segment of Corridor H at a cost of $15,858,045 that extended from Lost River Sinks to county route 23/12. This included landscaping for the historic Hott House as part of the construction mitigation program and involved the construction of a connection to existing
West Virginia Route 55 . This segment required 4.3 million cubic yards (3,200,000 m³) of earthwork, drainage, paving, signing and pavement markings. It was completed in the fall of 2003.The completion of the Lost River Bridge at McCauley signaled the end of construction on phase 8. The segment opened to traffic in mid-October 2006. [Corridor H Route - Baker to Wardensville. West Virginia Department of Transportation. 1 Oct. 2006 [http://www.wvcorridorh.com/route/map8.html] .]
Phase 9: Wardensville to the Virginia state line
This convert|5.5|mi|km|sing=on phase of Corridor H (
US 48 ) stretches from Wardensville toWest Virginia Route 55 at theVirginia state line.As part of the agreement, the Federal Highway Administration and the West Virginia Department of Transportation would defer construction, along with final design and right-of-way acquisition on the convert|5.5|mi|km|sing=on section of roadway between Wardensville and the
Virginia state line for as long as 20 years. This delay could be shortened ifVirginia approves their convert|14|mi|km|sing=on section of Corridor H (US 48 ) between theWest Virginia state line andInterstate 81 , if traffic increases significantly onWest Virginia Route 55 between Wardensville and the state line, or if required to ensue eligibility for Appalachian highway corridor funding.The Amended Record of Decision was approved on May 16, 2003. [Corridor H Route - Wardensville to Virginia. West Virginia Department of Transportation. 1 Oct. 2006 [http://www.wvcorridorh.com/route/map9.html] .]
Trouble Brewing
Corridor H Alternatives (CHA) filed a lawsuit, the first for the project since its realignment, in U.S. District Court in November 1996 challenging the Record of Decision for the entire convert|100|mi|km|sing=on Corridor H project.Corridor H Pressroom. 7 February 2000. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/joint%20announcement.html] .] [Corridor H Pressroom. 7 February 2000. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/gov%20announcement.html] .] The lawsuit stated that the Federal Highway Administration (FHWA) violated the National Environmental Protection Act (NEPA) by "failing to consider an improved roadway alternative (IRA) and by failing to prepare a Supplemental EIS to consider the impacts of the Corrick's Ford Battlefield alignment shift." The lawsuit further states that the FHWA "violated laws by issuing a Record of Decision prior to completing the evaluation of Corridor H's impacts" on historic structures and lands. [Corridor H. Stewards of the Potomac Highlands. 2005. 31 May 2005 [http://www.potomacstewards.org/corridorh] .]
In 1997, briefs were filed and oral arguments took place. In October, the U.S. District Court ruled in favor of the
Federal Highway Administration and theWest Virginia Department of Transportation on all counts, however, CHA appealed the ruling to the U.S. Court of Appeals.Briefs were once again filed in 1998 and oral arguments were presented throughout the year. In September, the CHA filed a second lawsuit that challenged the FHWA's findings of "no constructive" use for two properties. In November of that year, the Court system ordered the Department of Transportation to halt construction of Corridor H except for a convert|3.5|mi|km|sing=on section near Elkins.
In 1999, the U.S. Court of Appeals ruled in favor of the FHWA and the West Virginia Department of Transportation on the first lawsuit. On the second lawsuit, the court ruled in favor of CHA, stating that "all studies of historic properties must be completed before construction proceeds." In March, the Court dismissed the second lawsuit without prejudice, and allowed the CHA to file a new lawsuit challenging the decisions of the FHWA and the West Virginia Department of Transportation when Section 106/section 4(f) is complete for the entire Corridor H project. In May, a court order was produced that prohibited the FHWA from proceeding further with Corridor H until they have completed the Section 106 process and issued an amended Record of Decision. There were two exceptions to this however: work was allowed to proceed on the "Northern Elkins Bypass" and design work was allowed to proceed. This was the convert|5.5|mi|km|sing=on segment of Corridor H between Elkins and Kerens, or Phase I.
In December 1999, an agreement was reached. The Corridor H project was to be divided into nine separate projects from
Elkins, West Virginia to theVirginia state line. As stated in the agreement, impacts were to be avoided near Corricks Ford/Shavers Fork Valley andBlackwater Canyon ; the completion of ongoing studies; and the deferment of theWardensville, West Virginia toVirginia state line segment with final design and right-of-way acquisition restricted until specific conditions are met not to exceed 20 years. This delay could be shortened ifVirginia approves their convert|14|mi|km|sing=on section of Corridor H (US 48 ) between theWest Virginia state line andInterstate 81 , if traffic increases significantly on WV 55 between Wardensville and the state line, or if it is required to ensue eligibility for Appalachian highway corridor funding.The agreement also established alternative dispute resolution procedures and that the plaintiffs were to waive the right to bring future lawsuits against the FHWA and the West Virginia Department of Transportation that would seek any further study of any alternative that does not include completing Corridor H as a continuous four-lane highway.
One of the leading firms on the Corridor H project, the Michael Baker Corporation proposed and designed two 20+ acre wetland mitigation sites."Appalachian Highway Corridor H". Michael Baker Corporation. 2004. 31 May 2005 [http://www.mbakercorp.com/knowledge/view.cfm?DOC_ID=560] .] In addition, Baker, in conjunction with the West Virginia Department of Highways and the Federal Highway Administration, developed a "comprehensive mitigation plan for vegetative, water quality, acid drainage and wildlife issues for the entire 100+-mile long project."
Michael Baker Corporation's scientists also completed extensive surveys for endangered plant and animal species. Identified were the buffalo clover, the Indiana bat, the Virginia big-eared bat, Cheat Mountain salamander and the West Virginia northern flying squirrel. Based on this, Baker assisted the Department of Highways and the FHWA in conjunction with the U.S. Fish and Wildlife Service to prepare a biological assessment for the Indiana bat, which resulted in a finding that Corridor H will not adversely affect the habitat. A formal consultation is ongoing for the West Virginia northern flying squirrel.
West Virginia state line to Interstate 81 in Virginia
No work or planning has started on this segment of Corridor H yet.
Virginia will most undoubtedly wait untilWest Virginia completes most of their segments before completing their small segment from theWest Virginia state line toInterstate 81 nearFront Royal, Virginia .In April 2003, new US 48 signs were installed along State Route 55 in
Virginia . [Dunn, Allen Seth. "Re: US 48 signed in Virginia" Online posting. 04 June 2003. 04 June 2003 [http://groups.google.com/groups?q=Dan+US+48+group:misc.transport.road&hl=en&lr=&ie=UTF8&group=misc.transport.road&selm=CFN377327522146991%40news.erols.com&rnum=1] .] While State Route 55 will not be the final alignment of Corridor H through this region, it will be a temporary transition asWest Virginia completes their portions to the state line.Virginia also designated State Route 55 a Virginia Scenic Byway. Plans are in the works with VDOT to maintain the existing facility and continue to make spot improvements.Rails to Trails
The former
Western Maryland Railroad that stretched through easternWest Virginia was opened in 2003, only instead of carrying train cars, it will serve hikers and bikers. ["WVDOH Lets Two Projects in Newest 'Rails to Trails' Effort." Corridor H Pressroom. 15 February 2001. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/021501_rails.html] .] This "rail to trail" project was built in conjunction with the construction of Corridor H. It includes parking areas, restroom facilities, and walking trails. These projects will total approximately convert|20|mi|km and cost around $1.5 million. Two segments that were constructed from Parsons to Montrose and from Montrose to Elkins were awarded on February 20, 2001. It was named the Allegheny Highland Trail.Environmental Measures
The Division of Highways received the Federal Highway Administration's 2001 Environmental Award in the cultural resources category for the educational tools and web sites based on the Reed Farmstead archaeological dig on Corridor H. ["WVDOH Receives National Award." Corridor H Pressroom. 23 April 2001. West Virginia Department of Transportation. 20 March 2003 [http://www.wvcorridorh.com/press/archive/042301_award.html] .]
State Highway Engineer Joe Deneault explained when the 200-year old farm was discovered, the Division of Highways wanted to share the process of how the Hardy County family's home would be uncovered and preserved. "We wanted to share this process with the public," Deneault said. " The Reed Farmstead was an amazing discovery and we decided that a video and web sites would be the best way to share this extensive archaeological dig with area residents. As the project progressed, it was clear that this could be an important educational tool for students as well."
An educational video was produced that illustrated the step-by-step process in the identification and preservation procedures taken by WVDOH. The video was shown for 60 days on the Corridor H web site and a videocassette was mailed to every school teaching grades eighth through twelfth in the state.
The WVDOH also developed two web sites based on the project: [http://www.reedfarmstead.com] , that offers the history of the farm and details about the dig, and [http://www.kidsdigreed.com] , which is an interactive site for children.
The award was presented to the WVDOH and to the two consultants, Michael Baker Jr., Inc. and Charles Ryan Associates, working on this project at a ceremony in Washington, D. C. on April 20.
Future
Maryland and West Virginia have begun the early planning stages of another multi-lane highway, Corridor O, that will connect Corridor H near Moorefield to Interstate 68 near Cumberland, MD. Committees in Cumberland, Keyser, and Moorefield have been created to discuss the highway and thus far several plans have been established but one individual plan has not yet been chosen.
References
External links
* [http://www.wvcorridorh.com/ West Virginia Corridor H from the West Virginia Department of Transportation]
* [http://www.gribblenation.com/wvpics/corrh/ Corridor H from Gribblenation]
Wikimedia Foundation. 2010.