- Baltimore Belt Line
The Baltimore Belt Line was constructed by the
Baltimore and Ohio Railroad (B&O) in the 1890s to connect the railroad's newly constructed line toNew York City with the rest of the railroad atBaltimore, Maryland . It included the Howard Street Tunnel, theMount Royal Station and the first mainline railroad electrification in the United States.Origins
The B&O's original connection to New York in Baltimore was through surface street transfers to the
Philadelphia, Wilmington and Baltimore Railroad (PW&B), pulled by horses along Pratt Street between the B&O'sCamden Station and the PW&B'sPresident Street Station .Herbert W. Harwood, Jr., "Impossible Challenge". Baltimore, Md.: 1979. (ISBN 0-934118-17-5)] In 1884, the PW&B was purchased by thePennsylvania Railroad , cutting off the connection. The B&O built a new line to connect to thePhiladelphia and Reading Railroad , in turn connecting with theCentral Railroad of New Jersey for B&O's New York service. The combination also provided a connection to theStaten Island Railway , which served as the terminal switching company for the B&O's New York freight service.Construction
Connecting the new line to the rest of the system was a considerable engineering challenge. A new surface line across the center of town was politically impossible and prohibitively expensive; building around the outskirts of town would have required massive
regrading and bridging, as the terrain is extremely hilly and the line would cut across every watershed flowing into the harbor. As a temporary expedient, traffic was handled through Baltimore oncarfloat s, but it was clear that a direct connection would have to be built.The route chosen started from the existing end of track at Camden station, at the west end of the Inner Harbor. Atunnel was constructed directly under Howard Street, heading north until just before it crossed the existing PRR line.At the north portal of the tunnel, Mount Royal station was constructed. The track then curved around to the east, passed through six other (much shorter) tunnels, continued across town, finally heading southeast to meet the already constructed line just north of the Canton neighborhood. The cost of construction drove the railroad into bankruptcy shortly after the line opened.
Initially there were plans to build three new stations, but concern for interference with freight haulage and expense reduced this to a single station at Mount Royal, which opened on
September 1 ,1896 . Lower-level platforms were added at the east end of B&O's Camden Station in 1897.Herbert H. Harwood, Jr., "Royal Blue Line". Sykesville, Md.: Greenberg Publishing, 1990. (ISBN 0-89778-155-4)]Howard Street Tunnel
The Howard Street Tunnel, originally a convert|1.4|mi|km|1|sing=on| long tunnel under Howard Street in downtown Baltimore, took four and a half years to build (1890-95) and was the longest tunnel on the B&O's system. [Harwood, "Royal Blue Line", p. 86. In the mid-1980s, the tunnel's original length of 1.4 miles or convert|7340|ft|m|0 was extended an additional three-tenths of a mile (480 m) further south of its original Camden Station portal when the B&O successor
CSX Transportation 's mainline track east of theB&O warehouse was covered over for construction of Interstate 395 (ref: Stephen J. Salamon, David P. Oroszi, and David P. Ori, "Baltimore and Ohio – Reflections of the Capitol Dome". Silver Spring, Md.: Old Line Graphics, 1993 (ISBN 1-879314-08-8), pp. 26–28).] The tunnel is brick-lined with iron-arched centerings. At the time of completion it was considered innovative for its use of electicity for illumination and powering oflocomotive s. The tunnel is listed on theNational Register of Historic Places . [United States. National Park Service. Washington, DC. [http://www.nps.gov/nr/ National Register of Historic Places.] Listed 1973-07-02. No. 73002187.]Electrification
By this time the
Pennsylvania Railroad line through Baltimore and south had been in operation for twenty years. Due to the built-up nature of the area traversed and the hilly terrain, much of its line through town was in tunnels, which posed severe ventilation problems. Large chimneys were constructed above the Pennsylvania line in a not entirely successful attempt to disperse the fumes from the coal-fired locomotives. However by 1890 electric locomotion was beginning to appear possible, and in 1892 the B&O thus contracted withGeneral Electric (GE) for electric locomotives, powerhouse equipment, and the electricity distribution system. These were delivered beginning in 1895, and the first train pulled by an electric locomotive operated through the Howard Street Tunnel onJune 27 ,1895 . [F.G. Bennick, "B&O was first U.S. railroad to use electric locomotives", "Baltimore & Ohio Magazine", April, 1940.] The grade on the electrified portion was downhill to Camden Station; therefore traffic heading southbound ("westbound", in B&O timetables), from Mount Royal Station, simply drifted through the tunnels. Since the engine was not working, the smoke produced was relatively light. Going upgrade northbound ("eastbound", in B&O timetables) the electric locomotives were coupled to the front of the train at Camden Station and pulled the entire train, including the steam locomotive, through the Howard Street tunnel. When northbound passenger trains stopped at Mt. Royal Station at the north end of the tunnel, the electric locomotive was uncoupled. Northbound freight trains were pulled by electric locomotives for another two miles, until reaching Huntingdon Avenue in east Baltimore. There the steam locomotive closed its cylinder cocks, took up the load, and the electric locomotive uncoupled on the fly, accelerating ahead to a pocket siding between the tracks.General Electric installed
rotary converter s in B&O's powerhouse near Mt. Royal Station, having a combined capacity of 5,000 kW to convert 13,200-volt, 3 phase, 25-cycle AC to 675 volts DC. In 1936, these rotary converters were replaced by mercury arc rectifiers. [J.H. Davis, "B&O Substation for Main Line, through Baltimore", "Baltimore & Ohio Magazine", April, 1940.]Initially power was supplied through a unique system in which a pickup shoe rode in a channel above and to one side of the track. This proved vulnerable to contamination from coal smoke, and after a short time it was replaced by a conventional
third rail system. When the Howard Street track was made into a gantlet to allow higher clearances, the pickup contacts on one side were mounted on swinging arms to accommodate the varying distance to the third rail. The electrification was finally discontinued in 1952 when dieselization made it unnecessary.Latter day operation
Throughout much of its history until the end of passenger trains in 1958, the line had relatively low passenger traffic, averaging six daily New York–Washington trains each way. Freight traffic was also limited by the scarcity of online industry east of Baltimore and B&O's lack of a connection across the
Potomac River at Washington, D. C., to the southern railroads. The massive Pennsylvania main line carried most traffic to the northeast. In 1976, however, this line becameAmtrak 'sNortheast Corridor (NEC), and its role as a freight line became relatively minor. The 1987 accident at Chase, Maryland involving aConrail locomotive led to further reductions in freight traffic on the NEC. The Belt Line (now operated byCSX Transportation (CSXT) is therefore a key link in what has now become the principal rail freight line from Baltimore to Philadelphia and beyond.Howard Street Tunnel fire
On
July 18 ,2001 , a 60-car CSXT freight derailed in the Howard Street Tunnel, sparking a fire that burned for six days and blocked traffic for much longer. TheHoward Street Tunnel fire called attention to the Belt Line, both as a risk to the surrounding structures and as a link in rail traffic. CSXT has implemented various improvements to increase the integrity of the link, but is limited by the shallow depth of the bore (only three feet below the surface at the south end) and the instability of the surrounding soil.ee also
*
Royal Blue (B&O train)
*Railroad electrification in the United States References
* " [http://www.nrhs.com/spot/howard_street_tunnel/index.html The Howard Street Tunnel- Moving the Freight Through Baltimore] ", Smith, Jeffrey, "The National Railway Bulletin", Volume 66, Number 5, 2001
* "Baltimore's Unseen Artery: A Brief History of the Baltimore Belt Railroad and Its Howard Street Tunnel", Lee, J. Lawrence, ASCE Civil Engineering Conference and Exposition 2004
*"B&O Power: Steam, Diesel and Electric Power of the Baltimore and Ohio Railroad 1829 - 1964", Sagle, Lawrence W., Alvin F. Staufer, 1964
Wikimedia Foundation. 2010.