- Oklahoma City Crosstown Expressway
-
Oklahoma City Crosstown Expressway Route information Length: 4 mi (6 km) Major junctions West end: Agnew Ave. East end: Byers Ave. Highway system The Oklahoma City Crosstown is an elevated four mile (6 km) stretch of Interstate 40 that dissects downtown Oklahoma City from Agnew Avenue to Byers Avenue. It is owned and maintained by the Oklahoma Department of Transportation (ODOT). It is the primary east–west artery through Oklahoma City, and serves an unofficial dividing line between north and south Oklahoma City (the official dividing line for address purposes is [Reno Avenue]). While the Crosstown designed to withstand about 76,000 vehicles a day,[1] it is currently used by nearly 120,000 vehicles a day. The Crosstown was completed in the 1960s using an engineering process commonly termed as "fracture critical",[2] a process that has not been used since the 1970s because it does not provide redundancies.[3] According to Brian Windsor, an ODOT structural engineer, without redundant support, the failure of a single beam creates the risk of total collapse of that section of bridge.[4] The entire stretch of the Crosstown is elevated, and at some points, the elevation is as much as 50 feet (15.2 m). Other safety problems of the existing Crosstown include falling chunks of concrete and a lack of shoulders or breakdown lanes. In an August 2007 poll sponsored by The Oklahoman, nearly ⅔ of respondents indicated that they were "afraid to drive across the Crosstown bridge in Oklahoma City".[5]
Contents
I-40
Main articles: Interstate 40 and Interstate 40 in OklahomaConstructed nearly fifty years ago, Interstate 40 (I-40) stretches from Wilmington, North Carolina to Barstow, California. The highway roughly traces the path of historical U.S. Route 66 west of Oklahoma City.[6]
Oklahoma City Crosstown
The Oklahoma City Crosstown is the busiest of Oklahoma's many aging bridges. According to a 2006 report, Oklahoma leads the nation with 6,299 "structurally deficient" bridges.[7] Attention to the Crosstown project increased after the collapse of a stretch of I-35 in Minneapolis, Minnesota on August 1, 2007. At that time, ODOT released a statement indicating that the condition of the Crosstown was "deteriorating", but that it "remained safe."[8] Concerns about whether the Crosstown will last until its 2012 replacement date increased on September 23, 2007, when a hole in the Crosstown resulted in closure of all but one lane and created significant traffic delays.
Project status
In May 2002, federal funding was secured to finance replacement of the Oklahoma City Crosstown. Rather than replace the existing structure, a new stretch of I-40 will be constructed about five blocks south of the current location. Initial estimates of the Crosstown replacement project were that the project would take 8 years with a completion date of 2010,[9] and would cost $360 million dollars.[10] The most recent revision to this estimate was released in July 2007, and indicated that the project will be completed in 2012 and will cost $557 million. The ground-level boulevard to replace the current Crosstown bridges is no longer included in the cost estimates. The new Crosstown will have ten lanes for traffic traveling at 70 miles per hour (110 km/h), despite the current speed limit of 60 mph. It is being designed to carry 170,000 vehicles per day, and will have shoulders for disabled vehicles. Over 95% of current traffic on the Crosstown is through traffic, not transferring to or from downtown streets.
More recently, the Crosstown project has come under serious controversy. In an era of fluctuating energy prices and changing circumstances, several citizen's groups are challenging the project. Devon Energy announced in March 2008 it would construct a one million square foot office tower in the center of a revitalized downtown to house between 2,000 and 3,000 of its employees.[11] The Devon location will be ten blocks away from the interstate instead of four blocks, resulting in increased congestion on slower downtown streets during rush hour. Under current construction plans, part of Oklahoma City's Union Station railyard would be sacrificed to make space for the freeway, leading to concerns that this would disable the station from use in future light rail, commuter rail or traffic circulation use. An unprecedented ruling in June 2008 by the Federal Surface Transportation Board held that the BNSF railway made fraudulent representations in their request for abandonment of the freight line that would enable the Crosstown, and denied the abandonment. However, in May 2009 the final decision from the STB reversed the earlier ruling, allowing the ODOT to move ahead with their plans.[12]
ODOT has not sought to redirect semitrailers off the existing I-40 stretch of deteriorating overpasses. ODOT Director Gary Ridley said the current I-40 will "absolutely" survive through 2012, the new completion target date for the realignment, adding, "If we felt there was anything wrong that would cause us concern, we would close it, and we wouldn't think twice about it."[13] However, in a filing with STB, Ridley urged a quick ruling because "new serious issues including cracks in fracture critical members are constantly being discovered and repaired. The condition and obsolescence of the existing bridges constitutes serious concern for the Department."[14] Other highway connections, running east and west, include I-240 and I-44.
- NOTE: Speed Limit on I-40 is 55 mph in construction zones through downtown Oklahoma City.
Project timeline
- January 1996 — Citizens advisory committee formed.[15]
- December 1998 — ODOT chooses route for new Crosstown[16]
- February 7, 2001 — Formal public hearing held at the Myriad Convention Center.[16]
- May 12, 2002 — ODOT announces federal funding secured.[17]
- May 13, 2002 — Kick off meeting/groundbreaking.
- March 20, 2003 — Acquisition of all occupied residential property completed.[18]
- 2004 - Railroad and utility relocations were to have begun.[19]
- August 1, 2005 — Construction contract awarded to Muskogee Bridge Company.[20]
- 2007 - Construction was to have been completed on new alignment for I-40.[19]
- January 2007 - Surface Transportation Board approves railway abandonment application of Burlington Northern/Santa Fe (BNSF).[21]
- July 2007 — The first section of the new Crosstown Expressway — Three sections, including two 80-foot (24 m) long bridges and one railroad bridge were completed.[22]
- May 2007 - The State Convention of the Oklahoma Democratic Party adopted a resolution calling for a moratorium on construction and the appointment of a special commission to "consider alternatives that would preserve the Union railyard before any more public money is spent on this project."[23]
- August 1, 2007 — Collapse of I-35 bridge in Minnesota
- September 20, 2007 — Hole in Crosstown closed all but one lane of traffic and created significant traffic delays.
- November 29, 2007 - Hole in Crosstown closed all but one lane of westbound traffic east of Robinson Avenue.[24]
- March 14, 2008 - Hole in Crosstown closed all but one lane of westbound traffic.[citation needed]
- March 28, 2008 - Hole in Crosstown closed all but one lane of westbound traffic from the I-235 junction to Classen Boulevard.[25]
- June 5, 2008 - Surface Transportation Board reopens railway abandonment case and declares it void due to false statements made by BNSF.[21]
- July 15, 2008 - BNSF files petition with STB for relocation (instead of abandonment) of existing railway.[26]
- August 20, 2008 - Hole in I-40 - Closed lanes [27]
- September 20, 2008 - ODOT Director Gary Ridley announced no funds are available to tear down the existing Crosstown Expressway as originally planned. He estimated the cost of demolition and removal to be an additional $100 million.[28]
- September 24, 2008 - The City Council of Norman, Oklahoma, adopted a resolution requesting the Governor to appoint a commission to consider alternatives to removal of the Union Station railyard.[29]
- October 6, 2008 - The City Commission and the Economic Development of Authority of Shawnee, Oklahoma, adopted resolutions requesting Governor Brad Henry, a native of Shawnee, to appoint a commission to consider alternatives to removal of the Union Station railyard. In addition to Norman, the cities of Chickasha and El Reno have also passed similar resolutions.[30]
- October 20, 2008 - The Shawnee City Commission by a 5-2 vote denied a request by ODOT officials to reconsider the resolution.[31]
- April 7, 2009 - Another hole and a loose expansion joint in Crosstown closed all but one lane of westbound traffic between the I-235 junction and Classen Boulevard [32]
- 2012 - Projected completion date for new Crosstown Expressway[1]
Neighborhood displacement
Under the original Environmental Impact Statement, residents of two neighborhoods were to be displaced by construction of the new Crosstown Expressway. Construction resulted in the demolition of 165 properties in the Walnut Grove and Riverside neighborhoods.[33] The realignment will now directly result in reconstruction of 590 acres (2.4 km2) in Phase I and an additional 785 acres (3.18 km2) in Phase II, for a total of 1,375 acres (5.56 km2) in the core of Oklahoma City.[34]
Future land use (Core To Shore)
After the completion of the new I-40 Crosstown, the existing bridge will be demolished. While ODOT is responsible for the relocation of the I-40 Crosstown and the subsequent demolition of the existing structure, the city of Oklahoma City will take the lead in determining the future use of the land currently occupied by the existing crosstown. On June 20, 2006, the Oklahoma City Council [35] announced a $387,000 contract for professional consulting services with the URS Corporation to "to recommend specific actions to facilitate redevelopment within the area impacted by the relocation of the downtown section of I-40, Reno Avenue, new I-40 alignment, Western Avenue and I-35/I-235" [35]
On October 5, 2006, Oklahoma City Mayor Mick Cornett introduced the 'Core to Shore' project team which has the task of "planning and developing the area south of downtown and north of the Oklahoma River where Interstate 40 currently runs."[36] This team consists of community leaders as well as representatives from URS Corp.
References
- ^ a b "OKC I-40 Crosstown". Okladot.state.ok.us. http://www.okladot.state.ok.us/newsmedia/i40-okc/index.htm. Retrieved 2011-09-19.
- ^ Southerland, Paul (2007-08-05). "Crosstown close up". The Daily Oklahoman: p. A11.
- ^ Transportation Resource Board. Development of system fracture analysis methods and inspection standards for fracture critical steel bridges. 12 December 2006. Available at http://rip.trb.org/browse/dproject.asp?n=12670
- ^ The Oklahoman. 2007 August 05 Page 11A
- ^ The Oklahoman. 2007 August 09 Page 2A
- ^ Interstate 40 @ Interstate-Guide.com
- ^ TRIP. 2006. Bridge conditions 2006. http://www.tripnet.org/BridgeConditions2006.pdf
- ^ ODOT. 2007 Crosstown bridge remains safe. 02 August. http://www.okladot.state.ok.us/newsmedia/press/07-000_crosstown_bridge_remains_safe.pdf
- ^ Oklahoma Department of Transportation. n.d. I-40 Crosstown Expressway estimated future timeline. http://www.okladot.state.ok.us/newsmedia/i40-okc/press/Est-Future-Timeline.pdf
- ^ U.S. Office of Management and Budget. 2005. I-40 Oklahoma City Crosstown Expressway earmark. http://www.earmarks.omb.gov/earmarks/earmark_189756.html
- ^ "Devon Energy plans downtown OKC tower". Tulsa World. 2008-03-14. http://www.tulsaworld.com/business/article.aspx?articleID=20080314_5_E3_Devon88676. Retrieved 2011-09-19.
- ^ [1][dead link]
- ^ ://www.forbes.com/feeds/ap/2008/10/06/ap5515823.html">http://www.forbes.com/feeds/ap/2008/10/06/ap5515823.html
- ^ "Surface Transportation Board Filing". Stb.dot.gov. 2009-01-30. http://www.stb.dot.gov/filings/all.nsf/ba7f93537688b8e5852573210004b318/a146e1f4b0d41e8b8525754e00751c99?OpenDocument. Retrieved 2011-09-19.
- ^ http://www.okladot.state.ok.us/newsmedia/i40-okc/press/Time-Line-of-Events.pdf
- ^ a b http://www.okladot.state.ok.us/newsmedia/i40-okc/press/I-40_Crosstown_History.pdf
- ^ http://www.okladot.state.ok.us/newsmedia/i40-okc/press/Crosstown-NR5-13.pdf
- ^ http://www.okladot.state.ok.us/newsmedia/i40-okc/press/Benchmark_With_Crosstown_Property_Acquisition.pdf
- ^ a b http://www.okladot.state.ok.us/newsmedia/i40-okc/press/Est-Future-Timeline.pdf
- ^ http://www.okladot.state.ok.us/newsmedia/i40-okc/press/080105_I40_Crosstown_First_Construction.pdf
- ^ a b Walter Jenny Jr.. "I-40 plan may derail » Opinion". The Edmond Sun. http://www.edmondsun.com/opinion/local_story_165210442.html?keyword=secondarystory. Retrieved 2011-09-19.
- ^ McNutt, Michael. 2007. Paving the way. The Daily Oklahoman 06 July. Section A Page 15.
- ^ http://www.okdemocrats.org/Websites/okdemocrats/Images/ODPStateResolutionsAdopted-2007.pdf
- ^ [2][dead link]
- ^ Officials: I-40 Crosstown Down To 1 Lane Due To Hole - Oklahoma City News Story - KOCO Oklahoma City
- ^ "Justia Regulation Tracker Abandonment exemption: BNSF Railway Co., - Surface Transportation Board - 58711–58712 [E8–23616]". Regulations.justia.com. http://regulations.justia.com/view/122973/. Retrieved 2011-09-19.
- ^ POSTED: 5:17 pm CDT August 20, 2008 (2008-08-20). "I-40 Reopens After Crews Patch Bridge - Oklahoma City News Story - KOCO Oklahoma City". Koco.com. http://www.koco.com/news/17247180/detail.html?rss=okl&psp=news. Retrieved 2011-09-19.
- ^ "Funding OK'd in Crosstown highway planMoney is still needed to tear down old one, department official says.". Newsok.com. 2008-09-20. http://newsok.com/funding-okd-in-oklahoma-citys-crosstown-highway-plan/article/3300390. Retrieved 2011-09-19.
- ^ "Norman council is backing Union Station resolutionGroup approaches towns to gain support". Newsok.com. 2008-09-25. http://newsok.com/article/3302312/. Retrieved 2011-09-19.
- ^ Gire, Amanda (2008-10-09). "Groups pass resolutions for rail yard - Shawnee, OK - The Shawnee News-Star". News-star.com. http://www.news-star.com/localnews/x1985678055/Groups-pass-resolutions-for-rail-yard. Retrieved 2011-09-19.
- ^ Gire, Amanda (2008-10-21). "Rail proposal gets another look - Shawnee, OK - The Shawnee News-Star". News-star.com. http://www.news-star.com/localnews/x635406324/Rail-proposal-gets-another-look. Retrieved 2011-09-19.
- ^ POSTED: 11:57 am CDT April 7, 2009 (2009-04-07). "Lanes Along I-40 Near Downtown, Del City Back Open - Oklahoma City News Story - KOCO Oklahoma City". Koco.com. http://www.koco.com/news/19117427/detail.html. Retrieved 2011-09-19.
- ^ ODOT. 2003. ODOT hits benchmark with I-40 crosstown property acquisition. Press Release 03-018. 20 March. http://www.okladot.state.ok.us/newsmedia/i40-okc/press/Benchmark_With_Crosstown_Property_Acquisition.pdf
- ^ "City of Oklahoma City | Core to Shore". Okc.gov. http://www.okc.gov/planning/coretoshore/faq.html. Retrieved 2011-09-19.
- ^ a b The City of Oklahoma City Journal of Council Proceedings Regular City Council Meeting June 20, 2006 http://www.okc.gov/council/council_library/minutes/060620.pdf
- ^ Core to Shore Steering Committee Meeting Synopsis, October 05 2006
External links
Categories:- Interstate 40
- State highways in Oklahoma
Wikimedia Foundation. 2010.