Rosenheim–Kufstein railway

Rosenheim–Kufstein railway

The Rosenheim–Kufstein railway (German: Bahnstrecke Rosenheim–Kufstein) is a 32 kilometre-long double-track main line of the German railways. It connects the Munich–Salzburg line at Rosenheim with the line to Innsbruck, thus connecting Germany, Salzburg and eastern Austria with Innsbruck and the Brenner line to Italy and the Arlberg line to far western Austria. The line is part of the Line 1 of Trans-European Transport Networks (TEN-T). It is electrified at 15 kV, 16.7 Hz.

Rosenheim–Kufstein railway
Route number: 950
Line number: 5702
Line length: 31.862
Gauge: 1435
Voltage: 15 kV 16.7 Hz AC
Maximum speed: 140
Stations and structures
Legend
Straight track
Line from Munich
Junction from left
Line from Mühldorf am Inn
Junction from right
Mangfall Valley line from Holzkirchen
Station on track
0.0 Rosenheim
Junction to left
Line to Salzburg
Junction from left
Rosenheim curve from Salzburg
Non-passenger station/depot on track
2.0 Rosenheim south
Stop on track
6.1 Pfraundorf (Inn)
Station on track
7.9 Raubling
Unknown BSicon "eABZrf"
To Nicklheim
Station on track
13.4 Brannenburg Wendelstein Railway (closed 1961, narrow gauge)
Stop on track
15.8 Flintsbach
Non-passenger station/depot on track
17.6 Fischbach (Inn)
Track change
24.7 Oberaudorf crossover
Stop on track
25.0 Oberaudorf
Station on track
30.5 Kiefersfelden Wachtl Railway (narrow gauge)
Restricted border on track
31.9 GermanyAustria border
Station on track
Kufstein
Straight track
Lower Inn Valley railway to Innsbruck

Contents

History

A treaty between Austria and Bavaria signed on 21 June 1851 regulated the access of each state to the other in relation to the building of railways. As there was no direct rail link between Vienna and the Tyrol at that time, Bavaria agreed in Article 1 that it would build a railways from Munich to the border at Salzburg and from Rosenheim to the border at Kufstein. Austria committed itself under Article 2 to build a railway from Salzburg to Bruck an der Mur and from Kufstein to Innsbruck.[1] The line was opened on 5 August 1858 as part of the Bavarian Maximilian’s Railway.[2]

Route

The line runs from Rosenheim in a southerly direction. After leaving Rosenheim station it joins the southern end of the Rosenheim loop (or Rosenheim curve). The curve was opened on the 8 February 1982 and connects the line with the line from Salzburg, bypassing the station. The line also connects in Rosenheim station with the line from Mühldorf and the Mangfall Valley line from Holzkirchen.[2]

To the south the line passes through the Inn valley. A standard gauge line once ran from Raubling station to a peat works at Nicklheim. The narrow gauge Wendelstein Railway ran from Brannenburg station until 1961 when it was cut back to Waching in order to avoid several level crossings. Another narrow gauge line, the Wachtl Railway, still connects the cement plant near Kiefersfelden station with limestone quarries at Wachtl, just inside Austria in the municipality of Thiersee. Since 1991 a tourist service, called the Wachtl Express, has operated on the line from time to time. Between Kiefersfelden and Kufstein the line crosses the border into Austria; the border station serves Kufstein. After Kufstein the line becomes the Lower Inn Valley railway and leads on to Innsbruck.[2]

Operations

The route is part of the northern access to the Brenner railway to Italy and is thus part of the Berlin–Palermo railway axis. Non-stop travel time between Rosenheim and the border at Kufstein is 15 minutes, but due to temporary speed restrictions in most cases trains take longer. There is an hourly regional train service to Innsbruck, which requires a change in Kufstein. Every two hours a EuroCity (EC) train operate on the route through Innsbruck and the Brenner Pass to Italy. Every two hours Austrian Federal Railways runs Vienna–Salzburg–Innsbruck–Vorarlberg express trains over the line from South Rosenheim to Kufstein, but they do have no stops on the line. Although there are additional passenger services, there is still no regular-interval hourly service between Salzburg and Innsbruck. Currently, there are 32 scheduled services passenger services each day on the line. In addition approximately 20 freight trains operate each working day.[2]

Development

The construction of additional tracks to create a four-track line on the Rosenheim–Kufstein section is considered from time to time to cope with the expected increase in traffic after the opening of the proposed Brenner Base Tunnel. Further expansion plans would provide a bypass of Rosenheim, with a branch off the line from Munich at Grosskarolinenfeld and connecting with the Rosenheim–Kufstein line at Brannenburg.

Currently only small projects are underway. These include the elimination of level crossings (most recently at Flintsbach and Brannenburg) and the installation of noise barriers, particularly in towns in the Inn Valley.

References

  1. ^ "ALEX – Historische Rechts- und Gesetzestexte Online; Allgemeines Reichs-Gesetz- und Regierungsblatt für das Kaiserthum Österreich, Jahrgang 1852 (Austrian government gazette 1852)" (in German). Austrian National Library. http://alex.onb.ac.at/cgi-content/anno-plus?apm=0&aid=rgb&datum=18520004&seite=00000103. Retrieved 14 February 2010. 
  2. ^ a b c d Bufe, Siegfried (2009). "Bayerns Tor zum Süden (Bavaria's gateway to the south)" (in German). Eisenbahn Geschichte (Railway History) (36): 36–47. 

Wikimedia Foundation. 2010.

Игры ⚽ Нужно решить контрольную?

Look at other dictionaries:

  • Bavarian Maximilian's Railway — The three Bavarian main lines. The Ludwig South North Railway is shown in red, the Ludwig s Western Railway is shown in blue, and the Maximilian s Railway in green The Bavarian Maximilian’s Railway (German: Bayerische Maximiliansbahn) was as an… …   Wikipedia

  • Kufstein — Infobox Town AT Art = Stadt Name = Kufstein Wappen = Wappen at kufstein.png lat deg = 47 | lat min = 35 | lat sec = 00 lon deg = 12 | lon min = 10 | lon sec = 00 Lageplan = Kufstein.png Lageplanbeschreibung = Bundesland = Tirol Bezirk = Kufstein… …   Wikipedia

  • Munich–Salzburg railway — The Munich–Salzburg railway (German: Bahnstrecke München–Salzburg, line 951 in the official timetable (KBS)) is a 153 kilometre long double track main line of the German railways. It connects Munich with the line to Vienna at Salzburg. At… …   Wikipedia

  • Bahnhof Rosenheim — Ostansicht des Bahnhofs Daten Kategorie 3 …   Deutsch Wikipedia

  • New Lower Inn Valley railway — This article is about the high speed line of the Lower Inn Valley railway. For the existing line, see Lower Inn Valley railway. New Lower Inn Valley railway …   Wikipedia

  • Bahnstrecke Kufstein–Innsbruck — Staatsgrenze nächst Kufstein–Innsbruck Hbf Kursbuchstrecke (ÖBB): 300 Streckennummer: 302 01 Staatsgrenze nächst Kufstein–Wörgl Hbf 101 04 Wörgl Hbf–Innsbruck Streckenlänge: 74,921 km Spurweite: 1435 mm (Normalspur) Streckenklasse …   Deutsch Wikipedia

  • Milan–Bologna high-speed railway — The high speed line next to the Autostrada A1 near Pieve Fissiraga …   Wikipedia

  • Nuremberg–Erfurt high-speed railway — Nuremberg Erfurt high speed line Line length: 107 km (66.5 mi) …   Wikipedia

  • Nuremberg–Munich high-speed railway — The Irlahülltunnel (7,260 m/23,819 ft) is one of the longest and steepest (20 permille) rail tunnels in Germany Line number New line: 5934; Old line …   Wikipedia

  • Naples–Salerno high-speed railway — Legend …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”