- FX Date Conventions
In
foreign exchange market s there are four key dates to consider when tradingcurrency options in a particular currency pair:
* Horizon – the date on which the trade originates (usually today)
* Spot – the date on which the initial transfer of funds takes place
* Expiry – the date on which instrument expires
* Delivery – the date on which the final transfer of funds generated from the maturity of the instrument takes placeThese dates can be summarised on the following timeline:
Calculating Spot Dates
The
spot date is always calculated from the horizon date (T). There are two possible cases:
#Spot is T+1 day if the currency pair is USD/CAD. In this case T+1 must be a business day and also not a US holiday. If an unacceptable day is encountered, move forward one day and test again.
#Spot is T+2 days otherwise. The calculation of T+2 must be done by considering each currency within the pair separately. For USD there must be one clear working day between the horizon date and the spot date and for all non-USD currencies there must be two clear working days between the horizon date and the spot date.Also, in all cases, no money clears on US holidays, meaning that neither spot nor delivery can take place.
Calculating Expiry and Delivery Dates
Time to expiry is usually quoted either as “overnight” or in terms of a number of days, weeks, months or years. In general, the expiry date can be any weekday, even if it is a holiday in one, or both of the currencies, except
January 1 . There are differing conventions depending on the period involved:;OvernightFor overnight trades, the expiry date is the next week-day day after the horizon date, and the delivery date is calculated from the expiry date in the same way as spot is calculated from the horizon date. This will result in an expiry date that is before the spot date.
;Days and WeeksFor a trade with a time to expiry of v days, the expiry date is the day v days ahead of the horizon date (unless it is a weekend or
January 1 in which case we roll forward until we have a weekday) and for a trade with time to expiry of x weeks, the expiry date is the day 7 x days ahead of the horizon date (unless it is a weekend orJanuary 1 in which case we roll forward until we have a weekday). The delivery date is then calculated from the expiry date in the same way as the spot date is calculated from the horizon date.Months
For a trade with time to expiry of y months, the expiry date is found by first calculating the spot date, then moving forward y months from the spot date to the delivery date. If the delivery date is a non-business day or a US holiday, move forward until an acceptable delivery date is found. Finally, calculate the expiry date using an “inverse spot” operation, e.g. find the expiry date for which the delivery date would be its spot. When finding the expiry date from the delivery date, there must be one clear business day and one weekday (not including
January 1 ) in any applicable non-USD / non-CAD currency.Years
For a trade with time to expiry of z years, the expiry date is found by first calculating the spot date, then moving forward z years from the spot date to the delivery date. If the delivery date is a non-business day or a US holiday, move forward until an acceptable delivery date is found. Finally, calculate the expiry date using an “inverse spot” operation, e.g. find the expiry date for which the delivery date would be its spot. When finding the expiry date from the delivery date, there must be one clear business day and one weekday (not including
January 1 ) in any applicable non-USD / non-CAD currency.pecial Cases
There are two special cases involving trades that take place around the end of the month and we are trading in month multiples. One defines “target month” to lie x months forward from spot if time to expiry is x months, e.g. if in February, and the time to expiry is three months, the target month is May.
# If the spot date falls on the last business day of the month in the currency pair then the delivery date is defined by convention to be the last business day of the target month e.g. assuming all days are business days: if spot is at 30th April, a one month time to expiry will make the delivery date May 31st. This is described as trading “end-end”.
# If the spot date falls before the end of the month but the resultant delivery date is beyond the end of the target month then the delivery date is defined by convention to be the last business day of the target month. For example, assuming all days are business days: if the spot date is 30th January, a one month time to expiry implies delivery date 30th February - however, this doesn’t exist and the expiry date becomes 28th February (in a non-leap year).ee also
*
Currency trading
*Futures contract
*Futures exchange
*Options trading
Wikimedia Foundation. 2010.