- London Array
The London Array is a planned offshore
wind farm in the outerThames Estuary in theUnited Kingdom . Of 1gigawatt capacity, it is expected to become the world's largest offshore wind farm. [ [http://www.londonarray.com/ London Array official site] ]The site is seven miles off the
North Foreland on theKent coast in the area of Long Sand andKentish Knock , [ [http://www.londonarray.com/wp-content/boundaries-limits.pdf London Array boundary map (PDF)] ] and will cover 90 square miles betweenMargate in Kent andClacton in Essex.The completed wind farm will consist of 341
wind turbine s of around 3 MW to 7 MW rated capacity, [ [http://www.londonarray.com/about/offshore-components/turbines/ London Array official turbine information] ] which will provide an average power output of 350 MW at the smallest proposed turbine size. The higher rated turbines to be installed at the latter stages of construction and would provide considerably more power. The proposers say this is enough to power a quarter of the homes inGreater London or the entire counties ofKent andEast Sussex . The wind farm was planned to be built by London Array Limited, a consortium of Shell WindEnergy Ltd,E.ON UK Renewables andDONG Energy , [ [http://www.londonarray.com/about/ London Array project introduction] ] at a cost of £2bn. The original cost was around £1bn. [http://green.itweek.co.uk/2007/10/thames-array-ge.html Murray J, "Thames Array gets planning green light", "BusinessGreen blog", 2007-10-05] ]In May 2008, Shell announced that it was pulling out of the project, leaving the consortium in disarray. [ [http://www.ft.com/cms/s/0/e2a5b99c-16ea-11dd-bbfc-0000779fd2ac.html Shell pulls out of key wind power project] , "
Financial Times ", 01 May 2008] However it was announced in July that E.ON UK and DONG Energy would buy Shell's stake. [cite news
url=http://www.londonarray.com/category/press-releases/
title=E.ON and DONG Energy become 50:50 partners in world’s largest offshore wind farm
publisher=The London Array
accessdate=2008-08-16] It is not known what effect this will have on the timetable for the project.The turbines are to be assembled at
Port Ramsgate .Progress and timetable
*
18 December 2006 —planning permission for turbines granted, but siting of onshore substation is being contested [ [http://www.bloomberg.com/apps/news?pid=20601109&sid=a_7CFf7ycMPU&refer=home Voss, S, "Giant Wind Farm Pits English Town Against Shell, E.ON", Bloomberg, 2006-12-15] ]
*2007 —planning permission for onshore substation granted
*2008 —first turbines expected [ [http://news.bbc.co.uk/2/hi/uk_news/england/kent/6188133.stm "Offshore wind farms get go-ahead", BBC News, 2006-12-18] ]
*2010 —completion date estimate as of 2007See also
*
Thanet Offshore Wind Project - a 300 MW consented offshore wind farm in the Thames Estuary
*Greater Gabbard - a 500 MW consented offshore wind farm in the Thames Estuary
* Kentish Flats [http://www.kentishflats.co.uk] - a 90 MW operational offshore wind farm in the Thames Estuary
*Wind power in the United Kingdom References
External links
* [http://www.globalpolicy.org/socecon/envronmt/climate/2007/1011sea.htm A Sea Change: The Wind Farm Revolution]
Wikimedia Foundation. 2010.