Float (project management)

Float (project management)

In project management, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to:Fact|date=December 2007
* subsequent tasks (free float)
* project completion date (total float)

An activity that has a total float equal to zero is said to be a 'critical activity', which means that a delay in the finish time of this activity will cause the entire project to be delayed by the same amount of time.Fact|date=December 2007A critical activity typically has free float equal to zero, but an activity that has zero free float may not be on the critical path.

Example

Consider the process of replacing a broken pane of glass in the window of your home. There are various component activities involved in the project as a whole; obtaining the glass and putty, installing the new glass, choosing the paint, obtaining a tin of paint, painting the new putty once it has set, wiping the new glass free of finger smears etc etc.

Some of these activities can run concurrently e.g. obtaining the glass, obtaining the putty, choosing the paint etc., while others are consecutive e.g. the paint cannot be bought until it has been chosen, the new putty cannot be painted until the window is installed and the new putty has set. Delaying the acquisition of the glass is likely to delay the entire project - this activity will be on the critical path and have no float, of any sort, attached to it and hence it is a 'critical activity'. A relatively short delay in the purchase of the paint may not automatically hold up the entire project as there is still some waiting some time for the new putty to dry before it can be painted anyway - there will be some 'free float' attached to the activity of purchasing the paint and hence it is not a critical activity. However a delay in choosing the paint in turn inevitably delays buying the paint which, although it may not subsequently mean any delay to the entire project, does mean that choosing the paint has no 'free float' attached to it - despite having no free float of its own the choosing of the paint is involved with a path through the network which does have 'total float'.

ee also

List of project management topics

References

*


Wikimedia Foundation. 2010.

Игры ⚽ Нужно решить контрольную?

Look at other dictionaries:

  • Milestone (project management) — Within the framework of project management, a milestone is the end of a stage that marks the completion of a work package or phase, typically marked by a high level event such as completion, endorsement or signing of a deliverable, document or a… …   Wikipedia

  • Float — or floating may refer to the following:Float* Float (fishing), a bite indicator used in angling * Float, a Cascading Style Sheets attribute. * Float (parade), a decorated vehicle or platform, animal or man drawn or motorized, used in a festive… …   Wikipedia

  • Project network — Network Chart redirects here: for the 1980s and early 1990s British radio show of that name, see The Network Chart Show. A project network is a graph (flow chart) depicting the sequence in which a project s terminal elements are to be completed… …   Wikipedia

  • Project planning — is part of project management, which relates to the use of schedules such as Gantt charts to plan and subsequently report progress within the project environment. [cite book | author = Harold Kerzner | year = 2003 | title = Project Management: A… …   Wikipedia

  • Comparison of relational database management systems — Programming language comparisons General comparison Basic syntax Basic instructions Arrays Associative arrays String operations …   Wikipedia

  • Database Management Library — DBL Database Management Library Developer(s) ROCHA, Rodrigo C. O. Initial release July 2010 (2010 07) Stable release 1.0 / July 2, 2010; 15 months ago (2010 07 02) …   Wikipedia

  • Strategic management — is a field that deals with the major intended and emergent initiatives taken by general managers on behalf of owners, involving utilization of resources, to enhance the performance of firms in their external environments.[1] It entails specifying… …   Wikipedia

  • Program Evaluation and Review Technique — For other uses, see Pert (disambiguation). PERT network chart for a seven month project with five milestones (10 through 50) and six activities (A through F). The Program (or Project) Evaluation and Review Technique, commonly abbreviated PERT, is …   Wikipedia

  • Critical path method — PERT chart for a project with five milestones (10 through 50) and six activities (A through F). The project has two critical paths: activities B and C, or A, D, and F – giving a minimum project time of 7 months with fast tracking. Activity E is… …   Wikipedia

  • Comparison of Tryton and Open ERP — Tryton is a community fork of the commercial open source project OpenERP and began development in November 2008. This article compares both projects from technical, business and conceptual perspectives. Subject Tryton OpenERP Language Python… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”