- Burrinjuck Dam
Burrinjuck Dam is a convert|92|m|adj=on high, concrete gravity dam on the
Murrumbidgee River nearYass ,New South Wales ,Australia . The Yass andGoodradigbee River s flow into the dam. The dam divides the upper and lower catchment of the Murrumbidgee. [ [http://www.epa.nsw.gov.au/soe/95/9_4.htm NSW Dept of Environment and Conservation - Murrumbidgee River catchment] ]Construction commences
The dam is the
headwater storage for theMurrumbidgee Irrigation Area ("M.I.A."). The dam has a long history, construction having commenced in 1907. Anarrow gauge (610mm) railway was constructed from the state system at Goondah to bring materials, etc, to the site [Australian Railway Historical Society Bulletin, June, July & August, 1987 pp122-142;158-168;176-189] . Due toWorld War I , the dam was not completed until 1928. A majorflood in May, 1925 far exceeded all previously recorded floods and resulted in the dam wall being overtopped to a depth of convert|1|m|ftin1m.Enlargement
A strengthening and enlargement works program was undertaken between 1938 and 1957 (this time delayed by
World War II ) which raised the dam to a height of convert|80|m and provided a maximum spillway discharge capacity about twice the peak discharge of the 1925 flood.A major flood in 1974 eroded unweathered granite from an unlined spillway discharge channel which then resulted in the destruction of a
penstock to the Burrinjuck Power Station. The outlet valves of the dam were also destroyed during the same flood. These events prompted a review of the safety of the dam which recommended a new remedial works program.Upgrade
This project involved raising the existing dam wall by convert|12|m to its present height of 92 metres and installing post-tensioned ground anchor cables to improve the security of the dam during major floods. At the time, the Burrinjuck Dam Flood Security Upgrading project was unprecedented in two respects;
#the post-tensioning force required per metre length of dam crest and,
#the intensity of the flood discharge over the unlined sections of the side channel spillways during the Probable Maximum Flood (PMF).The upgrading works were completed in 1999 at a cost of $79.5 million (AUD).
References
External links
* [http://www.sweetwaterfishing.com.au/Burrinjuck.htm Burrinjuck Dam Fishing Information & Map]
* [http://members.optusnet.com.au/~richardw2/projects.html Richard Woodward's Dam Projects]
* [http://www.stateparks.nsw.gov.au/burrinjuck.html Burrinjuck Waters State Park]
* [http://www.waterinfo.nsw.gov.au/sr/Burrinjuck.html Water levels]
Wikimedia Foundation. 2010.