Construction delay

Construction delay

Construction delays in residential and light construction are often the result of miscommunication between contractors, subcontractors, and property owners. These types of misunderstandings and unrealistic expectations are usually avoided through the use of detailed critical path schedules, which specify the work, and timetable to be used, but most importantly, the logical sequence of events which must occur for a project to be completed. Delays in construction projects are frequently expensive, since there is usually a construction loan involved which charges interest, management staff dedicated to the project whose costs are time dependent, and ongoing inflation in wage and material prices.

However, in more complex projects, problems will arise that are not foreseen in the original contract, and so other legal construction forms are subsequently used, such as change orders, lien waivers, and addenda.

In construction projects, as well in other projects where a schedule is being used to plan work, delays happen all the time. It's what is being delayed that determines if a project, or some other deadline such as a milestone, will be completed late.

Before analyzing construction delays, a clear understanding of the general types of delays is necessary. There are four basic ways to categorize delays:

  • Critical or Non-Critical
  • Excusable or Non-Excusable
  • Concurrent or Non-Concurrent
  • Compensable or Non-Compensable

Before determining the impact of a delay on the project, one must determine whether the delay is critical or non-critical. Additionally, all delays are either excusable or non-excusable. Both excusable and non-excusable delays can be defined as either concurrent or non-concurrent. Delays can be further broken down into compensable or non-compensable delays.

Economic historian Robert E. Wright argues that construction delays are caused by bid gaming, change order artistry, asymmetric information, and post contractual market power. Until those fundamental issues are confronted and resolved, many custom construction projects will continue to come in over budget, past due, or below contract specifications, he claims.[1]

See also

External links

  • Construction Risk.com Resource for information on latest trends in project delays and construction claims

References

  1. ^ Robert E. Wright, Fubarnomics: A Lighthearted, Serious Look at America's Economic Ills (Buffalo, N.Y.: Prometheus, 2010), 69-82.

Wikimedia Foundation. 2010.

Игры ⚽ Нужна курсовая?

Look at other dictionaries:

  • Construction — For other uses, see Construction (disambiguation). In large construction projects, such as this skyscraper in Melbourne, cranes are essential. In the fields of architecture and civil engineering, construction is a process that consists of the… …   Wikipedia

  • Delay Insensitive Minterm Synthesis — Invented by David E. Muller, the DIMS (Delay Insensitive Minterm Synthesis) system[1] is an asynchronous design methodology making the least possible timing assumptions. Assuming only the Quasi Delay Insensitive delay model the generated designs… …   Wikipedia

  • Submittals (construction) — Submittals in Construction Management are shop drawings, material data, and samples. Product data submittals, samples, and shop drawings are required primarily for the architect and engineer to verify that the correct products will be installed… …   Wikipedia

  • North Ocean Shipping Co Ltd v Hyundai Construction Co Ltd — The Atlantic Baron Court High Court Citation(s) [1979] QB 705 Case opinions Mocatta J Keywords Duress North Ocean Shipping Co Ltd v Hyundai Construction Co …   Wikipedia

  • European Pressurized Reactor — The EPR (or US EPR for the United States specific design) is a third generation pressurized water reactor (PWR) design. It has been designed and developed mainly by Framatome (now Areva NP) and Electricité de France (EDF) in France, and Siemens… …   Wikipedia

  • Portland Aerial Tram — City Portland, Oregon Country United States Operated by Oregon Health Science University Type …   Wikipedia

  • Committee of 100 on the Federal City — The National Capitol Columns at the National Arboretum, saved by the Committee of 100 on the Federal City in 1959. The Committee of 100 on the Federal City, locally referred to as the Committee of 100, is a private, nonprofit membership… …   Wikipedia

  • Temple architecture (LDS Church) — On December 27, 1832 two years after the organization of Latter Day Saint church the movement s founder, Joseph Smith, Jr., reported receiving a revelation that called upon church members to restore the practice of temple worship. The Latter Day… …   Wikipedia

  • Hoover Dam Bypass — Infobox Bridge bridge name = Hoover Dam Bypass caption = An artist s rendering of the bypass, due for completion in September 2009 official name = Mike O Callaghan Pat Tillman Memorial Bridge carries = crosses = Colorado River locale = maint = id …   Wikipedia

  • Echelon Place — Location Las Vegas Strip Casino type Land based Owner Bo …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”