New-construction building commissioning

New-construction building commissioning

Building commissioning is the process of verifying, in new construction, that all the subsystems for HVAC, plumbing, electrical, fire/life safety, building envelopes, interior systems (example laboratory units), cogeneration, utility plants, sustainable systems, lighting, wastewater, controls, and building security achieve the owner's project requirements as intended by the building owner and as designed by the building architects and engineers.

Building commissioning is a quality-focused process necessary for both non-complex and complex modern construction projects. Normally the initial commissioning team and a team leader (typically known as the commissioning authority) is involved from project initiation through one year of occupancy. There is an on-going building enhancing and commissioning program and team for the life of the building. While the service methodology can vary from owner to owner and project to project, the basic formula for a successful building commissioning process involves a synergy team from pre-design to develop the owner's project requirements (OPR), commissioning scope and plan, including benchmarks for success, review of design design documents and checklists for achieving the Owner's Project Requirements (OPR), development of checklists and verifying a sample of construction checklists and submittals, developing training needs and evaluating training delivered by the contractors, witnessing and verifying construction phase tests, and periodic site observations during the construction phase, and performing commissioning functional testing as the project nears completion. While the practice of building commissioning process is still fairly new in the construction industry, it has quickly become common practice as building owners and developers try to get more out of their investment. The commissioning process main goal is to improve a project from the design phase through post construction and occupancy.

Contents

Commissioning Authority (CxA) or Commissioning Agent (CxA)

The Commissioning Authority or Commissioning Agent (CxA) is generally (and preferably) contracted directly to the building owner as a third-party independent representative to ensure unbiased performance of the CxA. The CxA may be (but not preferred) a subcontractor (or employee) of the building owner, architect, design engineer, test and balance contractor, or other trade contractor (i.e. HVAC/mechanical, electrical, fire protection, security, etc.) for specific trade testing. It is highly recommended by most all industry experts and standards that the CxA be a independent third-party consultant directly contracted to the building owner, and reporting directly to the building owner. It is also highly recommended that the CxA be contracted early in the project planning stages, included in design charrettes, and maintained throughout the design, construction, and final acceptance of the project at a minimum. Having the CxA on the team early provides opportunity to identify possible operation, installation, testing, and performance issues long before they become a construction issue. The CxA works closely with the owner's representative, building/facility operating engineer, architect, design engineer, general contractor, and all trade subcontractors. The CxA typically is responsible for leading and managing the project commission process (design and/or construction) and works closely with the design, construction, and operation teams in a co-operative work environment that focuses on teamwork throughout the building's design, construction, and post construction.

A CxA's ability to add value to a project is rooted in their ability to create positive working relationships with all parties involved and not pointing fingers when issues arrise. It is important that the CxA clearly identifies the communication processes/streams, the project goals and expectations (from the OPR), and the team member responsibilities. A CxA has to be able to give open constructive criticism while also being able to listen attentively. The CxA's primary goal is to provide a completed and properly operating product to the building owner and occupant/user.

The CxA's work and performance of service is equally or primarily in the background performing design, submittal, O&M Manual reviews and development of testing and commissioning processes for the project, as well as documenting the commissioning efforts. The CxA attends design and construction meetings, performs site construction observations, observes factory equipment testing, directs and observes functional performance testing of systems and equipment. The CxA typically does not actually perform the hands-on testing, as these are actually performed by the manufacturer, vendor, or trade contractors, and directed and observed by the CxA utilizing testing procedures and expected performance outcome previously identified by the CxA during the commissioning document development process.

The CxA typically prepares a commissioning specification and commissioning plan during the project design phase. The design engineer also may develop the commissioning specification (and rarely the commissioning plan) in situations where the CxA has not been so contracted, or brought into the design team during the design process. The commissioning plan is a live document that outlines the commissioning processes and expectation based on the Owner's OPR, the design engineer's basis of design (BOD) and the project construction document (drawings and specifications). The commissioning plan is modified as the commissioning process progresses throughout the design, construction, and final acceptance of the facility. The functional performance test procedures are typically developed by the CxA with assistance of the trade contractors, vendors, and manufacturers based on the design engineer's contract documents. These same parties and the design engineer, and owner's representative (typically the facility operating engineer) review the functional performance test procedures and expected outcomes prior to testing. The systems, equipment, items, processes, modes, and sequences of operations to be tested by the CxA (contractors or others) should be detailed and identified in the design engineer's construction documents (drawings and specifications), the construction request for proposal (RFP), the contractors bid submission, the commissioning specifications, the commissioning plan, and the contractors submittals. Of utmost importance, often neglected by contractors, are the equipment/systems "installation and operations manuals" (IOM or IO&M) "specific to the project" (not generic). The IOM's along with complete, and very detailed, sequence of operations (SOO) and control drawings/documents submittal "specific to the project" (not generic) are of utmost imporatance to the CxA to perform the review and develop proper testing procedures. Timely delivery of these documents to the CxA is important to facilitate the CxA ample time to review, develop test, obtain reviews, and implement changes prior to scheduling of any testing.

Building Management Systems (BMS) or Building Automation Systems (BAS)

Building management systems (BMS) or building automation systems (BAS) provide control of the building systems. These typically include heating, ventilating, air-conditioning and refrigeration (HVAC/R), electrical power, lighting, fire suppression and alarm, and security systems, etc. Building controls also have the ability to monitor and control systems to improve performance, conserve energy, conserve water, and control lighting. The greater control provides the ability to improve a buildings performance, environmental impact, and the user/occupant's environment. Direct digital controls (DDC) with real time monitoring and history provide the ability to acquire system data realtime or with trend-logging, or trending, (over a predetermined period of time) to observe performance, issues/troubles, and identify possible improvements to operations and maintenance.

Building systems and equipment (HVAC, electrical, etc.) operate via the control systems (BAS, BMS, and similar) based on a designed sequence of operations (SOO) typically developed by the design engineer (specification) and modified during the submittal process by the trade contractors and reviewed and approved by the design engineer). This SOO is also reviewed by the CxA who utilizes the SOO to develop the functional performance test procedures. The functional performance test procedures are typically developed by the CxA with assistance of the trade contractors, vendors, and manufacturers, reviewed by same, and the design engineer. The systems, equipment, items, processes, modes, and sequences of operations to be tested by the CxA (contractors or others) should be detailed and identified in the design engineer's construction documents (drawings and specifications), the construction request for proposal (RFP), the contractors bid submission, and the commissioning specifications and commissioning plan. The commissioning specification and commissioning plan are typically developed by the CxA during the design phase of the project.

The CxA works closely with the controls contractor to verify the control programming and identifies corrective issues during reviews and the functional performance testing. By performing the functional performance testing it is often, if not always, found where there are difficiencies in the systems or control and identifies items for improvement. Each and every point and sequence is typically not required to be tested by the CxA. The contractors typically hold the responsiblity of testing and verifying each and every point and sequence, and the CxA performs a test of a sample of the items after the contractors have tested, repaired and verified. Re-Testing of the same, or another sampling, by the CxA is often required to re-verify deficiencies identified during the initial testing.

The integrated operations and performance of the many building systems such as HVAC, life/fire safety, domestic water, power, CO2 ventilation, and similar provide a complex and important performance for the facility and it's occupants. Functional performance testing to verify proper operation prior to occupancy it extremely important. Testing of existing facilities is performed similarly by re-commissioning (commissioning of a building/system/equipment that has been previously commissioned) and retro-commissioning (commissioning of an existing building/system/equipment that has not been previously commissioned). Assurance of performance and operation by the CxA's commissioning verification of the facility typically provides a better operating, performing, and comfortable environment for the owner and occupants.

System degradation

It is estimated by Texas A&M researchers that as much as 20%[1] of the energy used in an average commercial building is waste associated with poorly operated systems.

Buildings systems underperform for several reasons:

  1. They were never properly configured
  2. The design did not account for all sources of building efficiency
  3. The building is not properly maintained
  4. The use of the building has changed over time

(CxA) Commissioning Authority or Commissioning Agent

An "independent third-party commissioning agent" has been highly regarded as providing benefit to most every project. To provide any benefit the facility, systems, and equipment must be thoroughly designed, submitted to, and approved by a responsible, thorough, professional architectural and engineering design team to function correctly. The design team incorporates the documented owner's program of requirements (OPR) which identifies the owner's systems, equipment, materials, control, and performance expections. The design team identifies and documents the project basis of design (BOD) which specifically identifies the OPR items, how each was implemented in the design (or modified), and the final design basis for systems, equipment, materials, control, and performance expections.

The fast track nature of the design and construction process (experience in current day 2011) often leads to missed planning, design, and even construction items. Items missed during the design and construction process can often be identified by the CxA during development of the functional performance test procedures or during functional performance testing.

The commissioning team, led by the CxA, has a primary objective of verifying proper installation, operation, and performance based on the project design (BOD) and the OPR. The commissioning of the facility, systems, and/or equipment provides verification, identifies issues/discrepancies, and if designed and constructed properly, ultimately enhances the facility total quality, control, performance, and efficiency which in turn provides increased sustainability.

References

  1. ^ Texas A&M System Energy Systems Lab – Continuous Commissioning

External links


Wikimedia Foundation. 2010.

Игры ⚽ Нужно сделать НИР?

Look at other dictionaries:

  • Building Commissioning — is the process of ensuring, in new construction, that all the subsystems for HVAC, Plumbing, Electrical, Fire/Life safety, and Building Security are operating as intended by the building owner and as designed by the building architects and… …   Wikipedia

  • Building regulations in England and Wales — Building regulations are statutory instruments that seek to ensure that the policies set out in the relevant liegislation are carried out and Building regulations approval is required for most building work in the UK. Building regulations that… …   Wikipedia

  • Building Schools for the Future — (BSF) is the name of the UK Government s investment programme in secondary school buildings in England. The program is very ambitious in its costs, timescales and objectives, with politicians from all parties supportive of the principle but… …   Wikipedia

  • New York City Opera — The New York City Opera (NYCO) is an American opera company located in New York City. The company, called the people s opera by New York Mayor Fiorello La Guardia, was founded in 1943 with the aim of making opera financially accessible to a wide… …   Wikipedia

  • Green building in the United States — The United States has established several sustainable design organizations and programs in green building.The U.S. Green Building Council (USGBC) is a non profit trade organization that promotes sustainability in how buildings are designed, built …   Wikipedia

  • Proposed new 49ers stadium — New 49ers Stadium (Measure J) Location San Francisco Bay Area (Santa Clara, California) Opened 2015 (estimated) Owner TBA Operator San Francisco 49ers Surface …   Wikipedia

  • Offshore construction — Offshore wind farm …   Wikipedia

  • Ariel Rios Federal Building — The Ariel Rios Federal Building is located in the Federal Triangle in Washington, D.C., across 12th Street from the Old Post Office, which the new building was designed to replace. The New Post Office, as the Rios Building was originally known,… …   Wikipedia

  • Business and Industry Review — ▪ 1999 Introduction Overview        Annual Average Rates of Growth of Manufacturing Output, 1980 97, Table Pattern of Output, 1994 97, Table Index Numbers of Production, Employment, and Productivity in Manufacturing Industries, Table (For Annual… …   Universalium

  • arts, East Asian — Introduction       music and visual and performing arts of China, Korea, and Japan. The literatures of these countries are covered in the articles Chinese literature, Korean literature, and Japanese literature.       Some studies of East Asia… …   Universalium

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”