Design-build (or design/build, and abbreviated D–B or D/B accordingly) is a project delivery system used in the construction industry. It is a method to deliver a project in which the design and construction services are contracted by a single entity known as the design–builder or design–build contractor. In contrast to "design–bid–build" (or "design–tender"), design–build relies on a single point of responsibility contract and is used to minimize risks for the project owner and to reduce the delivery schedule by overlapping the design phase and construction phase of a project. "DB with its single point responsibility carries the clearest contractual remedies for the clients because the DB contractor will be responsible for all of the work on the project, regardless of the nature of the fault".[1]

The traditional approach for construction projects consists of the appointment of a designer on one side, and the appointment of a contractor on the other side. The design–build procurement route changes the traditional sequence of work. It answers the client's wishes for a single-point of responsibility in an attempt to reduce risks and overall costs. It is now commonly used in many countries and forms of contracts are widely available.

Design–build is sometimes compared to the "master builder" approach, one of the oldest forms of construction procedure. Comparing design–build to the traditional method of procurement, the authors of "Design-build Contracting Handbook noted that: “from a historical perspective the so-called traditional approach is actually a very recent concept, only being in use approximately 150 years. In contrast, the design–build concept – also known as the "master builder" concept—as been reported as being in use for over four millennia."[2]

Although the Design-Build Institute of America (DBIA) takes the position that design–build can be led by a contractor, a designer, a developer or a joint venture, as long as a the design–build entity holds a single contract for both design and construction, some architects have suggested that architect-led design–build is a specific approach to design–build.

Contents

Design–build contractor

The "design–builder" is often a general contractor, but in many cases a project is led by a design professional (architect, engineer, architectural technologist or other professional designers). Some design–build firms employ professionals from both the design and construction sector. Where the design–builder is a general contractor, the designers are typically retained directly by the contractor. Partnership or a joint venture between a design firm and a construction firm may be created on a long term basis or for one project only.

Until 1979, the AIA American Institute of Architects' code of ethics and professional conduct, prohibited their members from providing construction services. However today many architects in the United States and elsewhere aspire to provide integrated design and construction services, and one approach towards this goal is design–build. The AIA has acknowledged that design–build is becoming one of the main approach to construction. In 2003, the AIA endorsed "The architect's guide to design–build services",[3] which was written to help their members acting as design–build contractors. This publication gives guidance through the different phases of the process: – Design services – Contracts – Management – Insurances – Finances –

Design–build institutes


In 1993, the Design-Build Institute of America (DBIA)[4] was formed. Its membership is composed of design and construction industry professionals as well as project owners. DBIA promotes the value of design–build project delivery and teaches the effective integration of design and construction services to ensure success for owners and design and construction practitioners. The Design-Build Institute of America is an organization that defines, teaches and promotes best practices in design–build.

The Canadian Design-Build Institute (CDBI), describes itself as "The recognized voice of Design-Build practitioners in Canada, promoting and enhancing the proper utilization of Design-Build method of procurement and contracting"[5]

Debate on the merits of design–build vs. design–bid–build

The rise of design–build project delivery has threatened the traditional hierarchies and silos of the design and construction industry. As a result, a debate has emerged over the value of design–build as a method of project delivery. A recent example of this type of debate can be seen in the June 2011 issue of Construction Digital.[6]
Critics of the design–build approach claim that design–build limits the clients’ involvements in the design and allege that contractors often make on design decisions outside their area of expertise. They also suggest that a designer—rather than a construction professional—is a better advocate for the client or project owner and/or that by representing different perspectives and remaining in their separate spheres, designers and builders ultimately create better buildings.
Proponents of design–build counter that design–build saves time and money for the owner, while providing the opportunity to achieve innovation in the delivered facility. They also note that design–build allows owners to avoid being placed directly between the architect/engineer and the contractor. Under design–bid–build, the owner takes on significant risks because of that position. Design–build places the responsibility for design errors and omissions on the design–builder, relieving the owner of major legal and managerial responsibilities. The burden for these costs and associated risks are transferred to the design–build team.
The cost and schedule reduction and decreased litigation associated with design–build project delivery have been demonstrated repeatedly. Researches on Selecting Project Delivery Systems[7] by Victor Sanvido and Mark Konchar of Pennsylvania State University found that design–build projects are delivered 33.5% faster than projects that are designed and built under separate contracts (design-bid-build). Sanvido and Konchar also showed that design–build projects are constructed 12% faster and have a unit cost that is 6.1% lower than design-bid-build projects. Simliar cost and times savings were found in a comparison study of design–build, and design-bid-build for the water/wastewater construction industry, a peer-reviewed paper authored by Smith Culp Consulting that will be published in July 2011 by the American Society of Civil Engineers.[8] A benchmarking and claims study by Victor O. Schinnerer, one of the world's largest firms underwriting professional liability and specialty insurance programs, found that, from 1995–2004, only 1.3% of claims against A/E firms were made by design–build contractors.

Growth of design–build method

A 2011 study analyzing the design–build project delivery method in the United States shows design–build was used on more than 40 percent of non-residential construction projects in 2010, a ten percent increase since 2005. The study was commissioned by the Design-Build Institute of America (DBIA) and was completed by RSMeans Reed Construction Data Market Intelligence.[9]

A study from the US Department of Transportation claims that: "Design-build delivery has been steadily increasing in the U.S. public building sector for more than 10 years, but it is still termed experimental in transportation. To date, under Special Experimental Project 14 (SEP-14) the FHWA has approved the use of design–build in more than 150 projects, representing just over half of the States. The European countries visited have used design–build delivery for a longer time than the United States and provided the scan team with many valuable insights. The primary lessons learned on this scan tour relate to the types of projects utilizing design–build, the use of best-value selection, percentage of design in the solicitation, design and construction administration, third-party risks, the use of warranties, and the addition of maintenance and operation to design–build contracts."[10]

Criticisms of design–build

During the design–build procedure, the contractor is deciding on design issues as well as issues related to cost, profits and time exigencies. When the traditional method of construction procurement dissociates the designers from the contractors’ interests, design–build does not. On this ground it is thought that the design–build procedure is poorly adapted to projects that require a complex and elaborated design for aesthetical or technical purposes.

A notable design–build project that received significant criticism, not only for excessive cost but for environmental issues, was the Belmont Learning Center. The scandal involved alleged contaminated soil that caused significant delays and massive cost overruns[11] In Los Angeles, District Attorney Steve Cooley, who investigated the Los Angeles Unified School District’s Belmont project, produced a final investigative report, released March 2003.[12] This report concluded that the design–build process caused a number of issues relating to the Belmont scandal:

  • Design–build does not make use of competitive bidding where prospective builders bid on the same design.
  • Criteria to select contractor is subjective and difficult to evaluate and to justify later.
  • The design and price selected arouses public suspicion, true or not.
  • This can lead to loss of public confidence.

It concluded the “design–build” approach and “mixed-use concept” together caused controversy, uncertainty, and complexity of the Belmont project which helped increased the potential for project failure.

While the Belmont investigation cleared the Los Angeles Unified School District of any criminal wrongdoing, the task force recommends strict oversight, including written protocols, a vigorous Office of the Inspector General, and other recommendations if it decides to continue to use the design–build approach.

As of 2009 and on, the Los Angeles Unified School District has vigorously started a campaign to use design–build approach in many of their projects, led by their ex-Chief of Facilities, James Sohn.[13] It is also important to note that during that time, the ex-Superintendent of LAUSD, Ramon C. Cortines, working with the LAUSD Board of Education, whose president is Monica Garcia, actively tried to cut the Office of Inspector General by 75% (compromising on 25%) and subsequently removed the Inspector General Jerry Thornton after he produced critical audits that showed misuse of construction funds.[14] Both James Sohn and Ramon C. Cortines would leave the district in 2011. Specifically, James Sohn would leave within days of the Los Angeles Times investigative reporting of government abuse and waste of construction funds in his prior employment with the Los Angeles Community College District.[15]

References

  1. ^ “Construction Contracts: Law and management” by John Murdoch and Will Hughes, published in 2007 by “Taylor & Francis E-library”, fourth edition, United Kingdom ISBN 0-203-96574-4 simultaneously published in USA ISBN 978-0-415-39368-3 and Canada ISBN 978-0-415-39369-0
  2. ^ "Design-Build Contracting Handbook", by Robert Frank Cushman & Michael C. Loulakis, published in 2001 by Aspen Law & Business, USA ISBN 0-7355-2182-4
  3. ^ "The architect's guide to design–build services" By G. William Quatman & Ranjit Dhar, published in 2003 by John Wiley & Sons Inc., USA ISBN 0-471-21842-1
  4. ^ The website of the Design Build Institute of America
  5. ^ The website of the Canadian Design-Build Institute
  6. ^ http://www.constructiondigital.com/architectural_design/designbuild-vs-architecture-firms
  7. ^ "Project Delivery Systems: CM at Risk, Design-Build, Design-Bid-Build". Construction Industry Institute Research Report: 133–11. April 1998. 
  8. ^ http://www.prweb.com/releases/2011/6/prweb8563707.htm
  9. ^ http://www.dbia.org/pubs/research/rsmeans110606.htm
  10. ^ US Department of Transportation, Federal Highway Administration, International Programs, Chapter 4 – Contract Administration: Technology and Practice in Europe
  11. ^ [1] Belmont scandal
  12. ^ [2] Los Angeles DA, Steve Cooley final Investigate report on Belmont
  13. ^ [3] James Sohn, Chief of Facilities discussing future of LAUSD Construction
  14. ^ [4] Daily News – LAUSD watchdog office to be cut by 25%
  15. ^ [5] LA Times discussing James Sohn resignation

External links


Wikimedia Foundation. 2010.

Игры ⚽ Нужна курсовая?

Look at other dictionaries:

  • Design-build — (or design/build, and abbreviated D B or D/B accordingly) is a construction project delivery system where, in contrast to design bid build (or design tender ), the design and construction aspects are contracted for with a single entity known as… …   Wikipedia

  • Design, Build and Sell Scheme — (abbreviation: DBSS) was introduced by the Housing and Development Board in 2005. Flats built under the scheme are meant for public housing and developed by private developers. They are built with better designs and in sites such as Tampines, Ang …   Wikipedia

  • Design/Build/Fly — is a radio controlled aircraft competition sponsored by the American institute of Aeronautics and Astronautics (AIAA), Cessna Aircraft Company, and Raytheon Missile Systems. The Office of Naval Research was also a sponsor until 2006. The… …   Wikipedia

  • Design Build Bluff — DesignBuildBLUFF is a non profit organization based in Park City, Utah that designs and builds sustainable housing, and is noted for its award winning and innovative home designs.[1] It is named after Bluff, Utah where their campus facility is… …   Wikipedia

  • design & build — A contract used in the construction industry to cover a situation in which one company takes the responsibility for both the design and building of a major building, such as a school or office block. It brings together the usually separated… …   Big dictionary of business and management

  • Design–bid–build — (or design/bid/build, and abbreviated D–B–B or D/B/B accordingly), also known as Design–tender (or design/tender ) and traditional method, is a project delivery method in which the agency or owner contracts with separate entities for each the… …   Wikipedia

  • Design-bid-build — (or design/bid/build, and abbreviated D B B or D/B/B accordingly), also known as Design tender (or design/tender ), is a project delivery method in which the agency or owner contracts with separate entities for each the design and construction of …   Wikipedia

  • Build To Order — (abbrev: BTO; Chinese: 预购组屋制度) is a Housing and Development Board (HDB) flat allocation system that offers flexibility in timing and location for owners buying a New HDB flats in Singapore. Eligible buyers planning to shift into a new HDB… …   Wikipedia

  • Design Futures Council — Abbreviation DFC Formation 1993 Type Think Tank Purpose/foc …   Wikipedia

  • Design and Architecture High School — Design and Architecture Senior High (DASH) Established 1990 Type Public magnet Principal Dr. Stacey Mancuso …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”