In the spring of 1970, the
Vermont legislature passed [http://www.nrb.state.vt.us/lup/statute.htm Act 250] , known as the Land Use and Development Act.Development pressures resulting from the opening of two interstate highways (I-89 andI-91 ) made access to the state much easier for year-round visitors, creating community concerns including road congestion, increased environmental problems, burden on local services, and risingtaxes . GovernorDeane C. Davis (Republican) appointed a study commission in 1969 to develop a statewide law to address these concerns, as no environmental regulations orland-use controls existed.The law created nine District Environmental Commissions to review large-scale development projects using 10 criteria that are designed to safeguard the environment, community life, and aesthetic character of the state. They have the power to issue or deny a
permit to real estate developers for any project that encompasses more than 10 acres (40,000 m²), or more than 1 acre (4,000 m²) for towns that do not have permanentzoning and subdivision bylaws. The law also applies to any development project with more than 10 housing units or housing lots; and may also apply for construction proposed above convert|2500|ft|m of elevation. Act 250 also created the Vermont Environmental Board to review appeals coming from District Commission rulings.Ten Criteria
The 10 Criteria [http://www.nrb.state.vt.us/lup/publications/nrb1.pdf [1] are as follows:
*1. Will not result in undue water or airpollution .Included are the following considerations: (A)Headwaters ; (B) Waste disposal (includingwastewater andstormwater ); (C) Water Conservation; (D) Floodways; (E) Streams; (F) Shorelines; and (G)Wetlands .
*2. Has sufficient water available for the needs of the subdivision or development.
*3. Will not unreasonably burden any existing water supply.
*4. Will not cause unreasonablesoil erosion or affect the capacity of the land to hold water.
*5. Will not cause unreasonably dangerous or congested conditions with respect tohighways or other means oftransportation .
*6. Will not create an unreasonable burden on theeducational facilities of the municipality.
*7. Will not create an unreasonable burden on themunicipality in providing governmental services.
*8. Will not have an undue adverse effect onaesthetics , scenic beauty, historic sites or natural areas, and 8(A) will not imperil necessary wildlife habitat orendangered species in the immediate area.
*9. Conforms with the Capability and Development Plan which includes the following considerations: (A) The impact the project will have on the growth of the town or region: (B) Primaryagricultural soils; (C) Productiveforest soils; (D) Earth resources; (E) Extraction of earth resources; (F)Energy conservation ; (G) Private utility services; (H) Costs of scattered developments; (J) Public utility services; (K) Development affecting public investments; and (L)Rural growth areas.
*10. Is in conformance with any local or regional plan or capital facilities program.The 10 criteria have changed little since the adoption of Act 250 in 1970. Efforts have been made over the years to make the permitting process work more efficiently, along with performance standards. Today, the District Commissions receive between 600 and 800 applications per year, and hold hearings on an average of 20% of these. They have an approval record of 98%, but this rate includes plans modified during the hearing process, with conditions typically attached to permits when granted.
Act-250 jurisdiction attaches forever to permits, except to permits for quarries and logging at elevations over convert|2500|ft|m. These permits are allowed to close when the work required to complete them is complete. Unfortunately. there is not sufficient funding to support personnel to verify proper completion of the required activity, so the Act-250 office must rely on the permit applicant to truthfully verify completion.
District Commissions
* District 1:
Rutland County
* District 2:Windham County , southernWindsor County
* District 3: northernWindsor County , Orange County
* District 4:Chittenden County
* District 5: Washington County andLamoille County
* District 6: Franklin County andGrand Isle County
* District 7:Caledonia County , Orleans County and Essex County
* District 8:Bennington County
* District 9:Addison County Source: ACT 250: A Guide to Vermont's Land Use Law. State of Vermont Environmental Board, Montpelier, VT (USA), November 2000.