- Scotswood Bridge
Infobox Bridge
bridge_name = Scotswood Bridge
caption =
official_name =
locale =Tyne and Wear ,England
carries =Road
Path
crosses =River Tyne
maint =
begin =1964
complete =1967
open =20 March 1967
below =
traffic = Dual Carriageway
design = Steel arch with suspended box girder deck.
toll =
mainspan =
length = convert|138.9|m|abbr=on
width = convert|20.13|m|abbr=on
clearance = convert|7.6|m|abbr=on
coordinates = coord|54.967|-1.690|type:landmark_region:GB|display=inline,titleScotswood Bridge is one of the main bridges crossing the
River Tyne inNorth East England . It links the west end ofNewcastle upon Tyne on the north bank of the river with theMetroCentre andBlaydon on the south bank. It is situated convert|5.2|km|abbr=on upstream of the better known city centre bridges.The Chain Bridge
The first bridge across the river at this location was the Old Scotswood Bridge, or ""The Chain Bridge" as it was known locally. It was a
suspension bridge with two stone towers, from which the road deck was suspended by chains. It was passed by parliament in 1829 and designed by John Green, with construction beginning that year. When it was opened on16 April 1831 it was the first bridge over the River Tyne to be opened during Tyneside's industrial era.The bridge was freed from tolls in 1907. In 1931 the bridge needed to be strengthened and widened. The width was increased from convert|17|ft|abbr=on to convert|19.5|ft|abbr=on with two convert|6|ft|abbr=on footpaths. The suspension cables and decking were also strengthened, allowing the weight limit to be raised to convert|10|t|lk=on|sigfig=4. The bridge eventually proved too narrow for the traffic it needed to carry and its increasing repair costs proved too much. After standing for 136 years, it was closed and demolished in 1967 after its replacement had been completed. [cite web
title = Scotswood Bridge (Chain Bridge)
work = Bridges on the Tyne
publisher =
url = http://www.bridgesonthetyne.co.uk/chain.html
accessdate = 2008-07-02]The Current Bridge
A replacement for the Chain Bridge had been proposed as early as 1941. Permission was finally granted in 1960. A new bridge was designed by
Mott, Hay and Anderson and built byMitchell Construction andDorman Long . Construction commenced on18 September 1964 . It was built slightly to the west of the Chain Bridge, which continued operating during the new bridge's construction. The bridge was opened on20 March 1967 . It is abox girder bridge , supported by two piers in the river and carries adual carriageway road.Scotswood Bridge carried the traffic of the Gateshead A1 western by-pass from 1970 up until the construction of
Blaydon Bridge in 1990. Between June 1971 and January 1974 traffic on the bridge was limited to single file to enable strengthening work to take place, which was needed to address design concerns. It has required further strengthening and repairs a number of times since; between 1979 and 1980, in 1983 and in 1990. [cite web
title = Scotswood Bridge
work = Bridges on the Tyne
publisher =
url = http://www.bridgesonthetyne.co.uk/scots.html
accessdate = 2008-07-09]References
*
Wikimedia Foundation. 2010.