Summit Railway Station

Summit Railway Station

Infobox Station
name=Summit
type=New Zealand Government Railways Department regional rail


image_size=
image_caption=
address=
coordinates= coord|41|8|41.29|S|175|11|48.93|E|type:railwaystation_region:NZ
line=Wairarapa Line
other=
structure=
platform=
levels=
tracks=
parking=
bicycle=
baggage_check=
passengers=
pass_year=
pass_percent=
pass_system=
opened=1878-10-12
closed=1955-10-30
rebuilt=
electrified=
ADA=
code=
owned=Railways Department
zone=
former=
services=
mpassengers=

Summit railway station was located at the apex of the Wairarapa Line over the Rimutaka Ranges in the Wellington region of New Zealand’s North Island and served as a place for trains to be marshalled for a descent down the Incline or for Fell locomotives to be extricated from a train that had ascended the Incline. It did not have a platform or other passenger facilities, did not consign goods, or otherwise serve any settlement save for the railway staff based there. It did not have, at any time during its operation, any road access.

History

Construction

Construction of the Summit station was covered by the Summit Contract. Seven tenders were submitted for the work, with the contract being let to Messrs. Collie, Scott and Wilkinson for the sum of £18,701. It was expected that the contract would be completed between 12 July 1874 and 22 July 1876, and covered the station yard, drainage works and the Summit Tunnel.

The yard was formed by cutting a terrace into the hillside, with the excavated fill being dumped on the opposite side of the yard. Further ground was levelled in the hillside above the yard on which houses were built. Over time, further ground was filled in on which to extend the yard and tracks.

Once the yard had taken shape, work started on the tunnel, which was originally known as Rimutaka Tunnel. It was to be approached through a cutting six chains long and up to 60 feet deep. The line started out at a gradient of 1 in 1,000 on entering the tunnel for 12 chains, 1 in 300 for 11 chains, then got progressively steeper at 1 in 92, 44, 20 and exited the tunnel at 1 in 15. The tunnel had a horseshoe cross-section, with the apex being at 15 feet.

Six weeks into the contract and the approaches to the Wellington end of the yard had been excavated to a depth of 10 feet for about six chains, a depth that had to be increased later. At the Wairarapa end of the workings, the approach cutting to the tunnel had been completed and about 40 feet of the tunnel driven. In December 1874, on learning of the slow progress the contractors were making on the tunnel, the Government made the first of many complaints, which seemed to have the desired effect. The Evening Post, a critic of the railway, reported in the following March that work was proceeding rapidly and satisfactorily.

The following June, work on the tunnel was proceeding at about a chain a month, little faster than before. It would not be until March 1877 before the two headings met. The Public Works Department later lined the tunnel after the rails reached Summit so work trains could be used to bring in supplies. The Summit Contract was finally completed on 10 December 1877, only 17 months late.

Operations

Platelaying was completed from four miles north of Upper Hutt to Summit between October 1877 and March 1878. The Summit yard originally had a simple layout, but increasing traffic brought about additions to the yard as required. The final extended layout was reached in 1903, when full signalling and interlocking was introduced. Although Summit had an engine shed until the 1920s, it seems doubtful whether locomotives were ever actually based there. It had a water service but no coal supply.

Being at, as its name implies, the top of the Rimutaka Ranges, Summit always had an unenviable reputation with regard to its climate. It was often subject to strong winds and high rainfall. Railway staff based there relied on the trains to supply all their needs.

As best as can be determined, the layout of the yard on the commencement of operations in 1878 consisted of the main line, two loops, a short siding from the main line on the north side and a siding to a small engine shed opposite. The capacity of the loops was 33 and 17 wagons respectively, and on the sidings, four and eight wagons. In the early 1880s, safety sidings were laid at both ends of the yard, and in 1898 more sidings were provided. Increasing traffic levels prompted a major reorganisation of the yard in 1903, with the north end extended and a new approach curve established, more sidings laid, and mechanical interlocking installed with a new signal box for the lever frame and associated equipment.

There was never any station building; the only structures on site being the signal box, five or six houses, and a locomotive shed (until the late 1920s). In later years, a larger ashpit, turntable and 15,000 gallon water tank were installed.

Summit was one of the first stations on the Wairarapa Line to receive signals, with them being first listed in the working timetable of 1887. Instructions for the crossing of trains laid down that southbound trains were to take the siding or loop, and northbound trains were to take the main line. The safety sidings had ground discs to indicate the position of the points, and both ends of the yard were protected by home signals. The signals in use at the time were of the slotted post semaphore type. In 1903 when the yard was reorganised, the old slotted post signals were replaced with balance-arm semaphore signals.

The final train to pass through Summit was a Carterton Show Day excursion, on the evening of Saturday 29 October 1955. The station, and the line over the Rimutaka Ranges were closed by the following day while work proceeded on preparing the Rimutaka Deviation to be opened for traffic. Most of the rail between Summit and Cross Creek was removed by March 1956, and the buildings were sold on-site for removal.

Today

The Summit station yard is now part of the Rimutaka Incline rail trail, a public walking/cycling track that was opened on 1 November 1987. A small shelter shed was erected, and picnic facilities provided. There are the remains of some locomotives on display at the northern end of the yard, where the turntable pit can also be seen. A row of large pine trees has been planted on the downward side of the yard. The original approach curve to the northern end of the yard can still be seen.

Future

The Rimutaka Incline Railway, a project of the Rimutaka Incline Railway Heritage Trust to reinstate and operate a heritage railway on the original Wairarapa Line formation between Maymorn and Featherston, plans to incorporate the Summit yard in its operations, including a new station building, turntable and marshalling yards. Though the trust has already participated in tree planting work at the Summit site and Summit operations are included in Stage 1 of the project, operations at the site are some years away as a great deal of work remains to establish the Maymorn site and complete platelaying between Maymorn and Summit.

ee also

* Rimutaka Incline
* Rimutaka Tunnel
* Rimutaka Incline Railway Heritage Trust

References

*


Wikimedia Foundation. 2010.

Игры ⚽ Нужна курсовая?

Look at other dictionaries:

  • Snaefell Summit railway station — is the upper terminus of the Snaefell Mountain Railway on the Isle of Man and is served by the tramway of the same name. The line originally opened in 1895 at which time a wooden chalet type building was erected including a waiting shelter and… …   Wikipedia

  • Summit Tank railway station, New South Wales — Sydneyclosedstation NAME= Summit Tank LINE=Unanderra Moss Vale line DISTANCE= 108.130km via Wollongong PLATFORMS= 1 Side Platform TRACKS= 1 STATUS= In Use OPENED= 20/8/1942 CLOSED= Summit Tank was a railway station on the Unanderra Moss Vale line …   Wikipedia

  • Cross Creek Railway Station — Cross Creek New Zealand Government Railways regional rail Cross Creek station yard, looking west at the start of the incline …   Wikipedia

  • Kaitoke Railway Station — Infobox Station name=Kaitoke type=New Zealand Government Railways Department regional rail image size= image caption=One of the private dwellings now located on the former Kaitoke station precinct. address=Station Drive, Kaitoke coordinates=… …   Wikipedia

  • Oakengates railway station — Oakengates Location Place …   Wikipedia

  • Dava railway station — Contents 1 History 2 Station layout 3 Goods siding 4 Station location 5 Closure …   Wikipedia

  • Ngauranga Railway Station — Ngauranga Metlink regional rail Station statistics …   Wikipedia

  • Maymorn Railway Station — Maymorn Metlink regional rail Maymorn railway station main platform, looking west. Stati …   Wikipedia

  • Mauriceville Railway Station — Mauriceville New Zealand Government Railways (NZGR) regional rail Station statistics …   Wikipedia

  • Grosmont railway station — Infobox UK station name = Grosmont code = GMT caption = Up platform Running in board at Grosmont manager = Northern Rail locale = Grosmont borough = Scarborough start = 1865 (present station) platforms = 4 lowusage0405 = 19,601 lowusage0506 =… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”