Project 28 is the name given to a U.S. border protection program that runs along a convert|28|mi|km|sing=on stretch of the US/Mexican border in southern Arizona.Randal C. Archibold, [http://www.nytimes.com/2007/06/26/us/26fence.html "28-Mile Virtual Fence Is Rising Along the Border"] , "New York Times", June 26 2007] . The project, the first phase of a much larger program called the "Secure Border Initiative network" (SBInet), was scheduled to be completed in mid-2007, but did not become operational until late 2007. It involves the placement of 9 high-tech surveillance towers that monitor activity using radar, high-resolution cameras, and wireless networking, looking for incursions to report to the Border Patrol.

In February 2008, authorities said that the project did not work as planned nor did it meet the needs of the U.S. Border Patrol. As a result, the deployment of about convert|100|mi|km of virtual fence near Tucson, Yuma, Arizona, and El Paso, Texas is now projected to be completed by the end of 2011, rather than 2008.Spencer S. Hsu, [http://www.washingtonpost.com/wp-dyn/content/article/2008/02/27/AR2008022703747.html "'Virtual Fence' Along Border To Be Delayed: U.S. Retooling High-Tech Barrier After 28-Mile Pilot Project Fails"] , "Washington Post", February 28, 2008]

Costs

In September 2006, Boeing won a contractor competition and was awarded a three-year, $67 million contract by the U.S. government to build and operate Project 28. The initial construction phase had an estimated cost of $20 million. Project 28 is the pilot for SBInet, which has has a total estimated cost of two to eight billion dollars. If Project 28 is successful, hundreds of towers (an estimate in May 2007 was 850 towers)Sean Snyder, [http://www.designnews.com/article/CA6439236.html "Boeing, Department of Homeland Security Implement Project 28 Virtual Fence: SBINet’s Project 28 is underway and scheduled for completion in mid-June"] , "Design News", May 4, 2007] could be placed on the convert|6000|mi|km of the U.S. borders with Mexico and Canada. The Department of Homeland Security (DHS) estimates that the cost to secure each mile of the border with fencing is about $3 million, compared to about $1 million using technology such as that of Project 28.

In a report in February 2007, the Government Accountability Office said that Congress needed to keep a tight rein on the program, because, it said, "SBInet runs the risk of not delivering promised capabilities and benefits on time and within budget." Between 1998 and 2006, the U.S. government spent $429 million on border technology programs that failed. [Sylvia Moreno, [http://www.washingtonpost.com/wp-dyn/content/article/2007/06/09/AR2007060901209.html "For Residents of Arizona Border Town, Towers Are Unwelcome Eyes in the Sky"] , "Washington Post", June 10, 2007]

Technology

Components

The four primary components of the system are the sensor towers, the P28 "Common Operating Picture" (COP), enhanced communications, and upgraded agent vehicles which include a laptop computer and a satellite phone. [ [http://www.boeing.com/ids/advanced_systems/sbinet/sbinet_p28_0407.pdf SBInet Project 28 (pdf)] , Boeing Backgrounder, June 2007, accessed July 3, 2007] The project also incorporates unattended ground sensors that will detect intrusions via magnetic, seismic and acoustic sensors and transmit information that will be distributed via the COP.

Each of the convert|98|ft|m|sing=on-high towers has radar (MSTAR), infrared cameras and other sensors, and data-processing and communications equipment to distribute information to control centers, mobile units, agent vehicles and other law enforcement employees.

Operations

When migrants cross the SBInet's virtual fence, camera and other sensors on the tower are to instantly detect the incursion. These towers then relay real-time electronic images to a private sector communications center. There, a contractor employee will take manual command of the camera, zooming in to identify the number of individuals and their means of transport. After classifying the "threat," the employee will electronically transfer the entrants' coordinates to Border Patrol agents via laptop computers mounted inside Border Patrol vehicles.

Limitations of Project 28

Rather than develop new technology, Boeing took existing cameras, sensors, radar and other equipment and bundled them into a system that although not technologically novel is unlike anything the Border Patrol had used.

Boeing, as the prime contractor, selected nearly 100 of the 900 subcontractors that applied to work on the contract. While Boeing considers the list of subcontractors to be an industrial secret, known subcontractors include Booz Allen Hamilton; Centech, DRS Technologies; Kollsman, Inc.; LGS, L-3 Communications Government Services; Perot Systems, Pinkerton Government Services; Power Contracting, Inc. Reconnaissance Group; Sandia National Laboratories; the Texas Transportation Institute at Texas A&M University; and Unisys.Joseph Richey, [http://www.corpwatch.org/article.php?id=14552 "Fencing the Border: Boeing's High-Tech Plan Falters"] , Corp Watch, July 9, 2007]

As of early June 2007, Boeing had issued 55 requests for proposal for additional technologies to be deployed along the border. Jerry McElwee, a Boeing vice president and the program manager for SBInet, said that the June 2007 version of Project 28 was "a demonstration of our approach and a test bed for incorporating improvements" to SBInet.

Test area

Selection

The area where the project is located was the busiest in the sector in fiscal year 2006, according to Border Patrol officials."We chose the most difficult, highest-trafficked piece of Arizona because we wanted to take on the challenges that we would have to take on someday," said Brian Seagrave, vice president for border security at Unisys Corporation, the company that is providing the information systems expertise. It also includes a Port of Entry (POE) and is representative of terrain conditions found in large areas along the Southwest border. [ [http://www.cbp.gov/linkhandler/cgov/border_security/sbi/sbi_monthly_newsletter/sbi_newsletter.ctt/sbi_newsletter.pdf Secure Border Initiative Monthly, Volume 1, Edition 1 (pdf)] , December 2006, accessed July 4, 2007] Unlike other areas on the border that have stadium lighting, fencing and cameras on convert|40|ft|m|sing=on towers, this area lacks infrastructure and technology.

Location of towers

The nine towers are located on either side of Sasabe, Arizona. Two of the towers are on the land of Tohono O'odham nation west of the Baboquivari range, three are in the Buenos Aires National Wildlife Refuge, and one is located just outside of Arivaca, Arizona, convert|11|mi|km north of the border.

The initial towers are redeployable; at the end of the Project 28 trial, DHS will decide whether to change any locations. The towers will then be moved to the next area being tested, and will be replaced by permanent towers.

Residents of Arivaca who objected to the tower near their town were told in a meeting in May 2007 that the tower was located there because mountains to the south hindered surveillance, and the tower’s closer proximity to the roads near the town would make it easier to maintain. In June 2007, with the system scheduled to become operational shortly, residents were concerned about being under 24-hour surveillance, bright lights in the night sky, and the disruption of recreation and other activities near the tower, including loud alarm blasts from the towers scaring horses on trail rides.Alice Lipowicz, [http://www.washingtontechnology.com/print/22_11/30919-1.html "Not in my backyard: Residents along the border want more say in placement of SBInet towers"] , "Washington Technology", June 25, 2007]

Organizational placement

The convert|28|mi|km of the border near Sasabe that are in Project 28 are the responsibility of the Tucson station of the Border Patrol. The station was arresting 200 to 400 illegal aliens per day as of early 2008. [Jim Lamb, [http://www.gvnews.com/articles/2008/02/16/news/news02.txt "BP warns residents to be wary of illegals"] , "Green Valley News and Sun", February 16, 2008]

Progress of the project

Initial testing

In early April 2007, Boeing announced that it had successfully tested the first integrated mobile sensor tower. Dr. Kirk Evans, the SBInet program manager at CBP, said that "The tower and its components functioned as expected, and we are confident that the design is repeatable for deployment along the border." [ [http://www.boeing.com/news/releases/2007/q2/070404b_nr.html "Boeing Successfully Tests First SBInet Mobile Sensor Tower"] , Boeing news release, April 4, 2007]

The project was originally scheduled to be operational on June 13, 2007. System testing began in the first week of June.Alice Lipowicz, [http://www.washingtontechnology.com/online/1_1/30846-1.html "Boeing to flip the switch on SBI-Net"] , "Washington Technology", June 11, 2007] Agency officials testified publicly on June 7th that Project 28 was on schedule.

Delayed implementation

On June 8th, agency officials said that project completion would be delayed until June 20th. On June 16th, the department said that the project would be delayed beyond June 20th.Dan Caterinicchia, [http://www.forbes.com/feeds/ap/2007/06/21/ap3844508.html DHS Secure Border Initiative Delayed"] , "Associated Press", June 21, 2007]

On June 26th, a DHS spokesman could not say when the project would become operational. "We are working hard to resolve these challenges as quickly as possible so that we can deploy or make this system operational and give the agents the tools they need to better secure the border," he said.Chris Strohm, [http://www.govexec.com/story_page.cfm?articleid=37317&dcn=todaysnews "Border tech program is plagued by early setbacks"] , "Government Executive", June 27, 2007] In mid-July, a DHS spokesman said that programmers were working overtime to make sure the radars, cameras and sensors properly send information to computers in the two command centers and to laptops in Border Patrol vehicles. Boeing is "getting close" but no date has been set for the system to become operational, the spokesman said. [ [http://www.azstarnet.com/news/191719 "Border-fence construction resumes at former key San Diego entry site"] , "Associated Press", July 14, 2007]

In early September, a spokesman at the Customs and Border Patrol said "It could be two, four, six or eight weeks until it’s operating." Boeing and DHS encountered problems integrating the various cameras, radars and other sensors on the nine towers, and there were also problems combining the incoming data seamlessly with communications networks. [Alice Lipowicz, [http://www.washingtontechnology.com/print/22_16/31354-1.html "SBInet struggles through first phase: Boeing, DHS take slow approach as they work out integration kinks"] , "Washington Technology", September 3, 2007] Several days later, DHS Secretary Michael Chertoff said he expected to testing to begin in October.Nicole Gaouette, [http://www.latimes.com/news/printedition/asection/la-na-homeland6sep06,1,1027125.story?coll=la-news-a_section "High-tech border system needs work: Homeland Security chief says that the program is not fully functional, but that security has improved"] , "Los Angeles Times", September 6, 2007]

In late October, a senior Boeing official testified that the system was substantially improved. The official said that ""The system is consistently able to slew to new radar targets and successfully record people crossing the border," and that "Camera elevation difficulties have been fixed and a solution for radar display delays has been implemented." [Jim Wolf, [http://www.washingtonpost.com/wp-dyn/content/article/2007/10/24/AR2007102402259.html "Boeing criticized over border security glitches"] , "Reuters", October 24, 2007]

Reduced operational testing

As a pilot project for SBInet, Project 28 was originally scheduled to be operational for eight months.Brady McCombs, [http://www.azstarnet.com/dailystar/154728 "High-tech border security will be tested near Sasabe"] , "Arizona Daily Star", November 11, 2006] However, in September 2007, DHS Secretary Michael Chertoff said he expected operational testing to finish by the end of the year, a period of less than three months, assuming that the system did go "live" sometime in October.

Acceptance of first phase

In early December 2007, Homeland Security Department conditionally accepted the delivery of the first phase of Project 28 and awarded Boeing a $64 million contract for the next phase. Part of the next phase involves upgrading the Common Operating Picture (COP) system to display real-time information from the radars, cameras and ground sensors that were installed along the borders. The Border Patrol was to take over Project 28 and run it in an operational mode for 45 days. During that time, Chertoff said that "we will identify further adjustments or fixes that need to be made." [ cite news | url = http://www.govexec.com/dailyfed/1207/121007bb1.htm |title = DHS accepts delivery of electronic fence, with caveats | date = 2007-12-10 | publisher = Government Executive |last=Brewin |first=Bob]

DHS officially accepted the system on February 22, 2008. [cite news| url = http://www.azstarnet.com/sn/border/234033.php |title = Boeing to replace 9 towers at border | date = 2008-04-10 | publisher = Arizona Daily Star | last = McCombs | first = Brady ]

Effectiveness

In February 2008, U.S. Representative Chris Carney, chairman of the House Homeland Security Committee’s Management, Investigations and Oversight Subcommittee, said the system "works about 30 percent of the time". During a visit in early January 2008 to El Paso, Carney said that he saw an incident where two illegal immigrants crossed in front of a project camera. Carney said that a technician tried to electronically reposition the camera to track them, but the picture was out of focus, the camera moved too slowly, and the illegal immigrants got away. [Boris Krawczeniuk, [http://www.thetimes-tribune.com/site/news.cfm?newsid=19312509 "Carney focuses on illegal immigration"] , "Times-Tribune", February 20, 2008]

References

External links

* [http://www.cbp.gov/xp/cgov/newsroom/highlights/cbp_responds/project_28.xml What is Project 28?] , U.S. Customs and Border Protection, December 29, 2006
* [http://www.cbp.gov/xp/cgov/border_security/sbi/ SBInet official website] , U.S. Customs and Border Protection
* [http://www.arivaca.net/project28.htm SBInet Virtual Fence] , www.arivaca.net


Wikimedia Foundation. 2010.

Игры ⚽ Нужно сделать НИР?

Look at other dictionaries:

  • Project 4.1 — was the designation for a medical study conducted by the United States of those residents of the Marshall Islands exposed to radioactive fallout from the March 1, 1954 Castle Bravo nuclear test at Bikini Atoll, which had an unexpectedly large… …   Wikipedia

  • Project A-Ko — プロジェクトA子 (Пуродзэкуто A Ко) Жанр комедия, пародия, меха …   Википедия

  • Project 25 — (P25 or APCO 25) is a suite of standards for digital radio communications for use by federal, state/province and local public safety agencies in North America to enable them to communicate with other agencies and mutual aid response teams in… …   Wikipedia

  • Project IC — is the name used in Malaysia to describe the allegation of systematic granting of citizenship to immigrants (whether illegal or legal immigrants) by giving them identity documents known as IC (identity card), and subsequently, MyKad . The alleged …   Wikipedia

  • Project 21 — is a conservative public policy group that provides broadcasters and the print media with prominent African American conservative commentators as columnists and guests. The organization refers to itself as The National Leadership Network of Black …   Wikipedia

  • Project Q — is the youth program of the Milwaukee LGBT Community Center serving lesbian, gay, bisexual, transgender, queer, questioning, and straight allied young adults ages 24 and under. Established in 1999, Project Q (PQ) has grown to one of the largest… …   Wikipedia

  • Project-X — Project X …   Википедия

  • Project — Proj ect (?; 277), n. [OF. project, F. projet, fr. L. projectus, p. p. of projicere to project; pro forward + jacere to throw. See {Jet} a shooting forth, and cf. {Projet}.] [1913 Webster] 1. The place from which a thing projects, or starts forth …   The Collaborative International Dictionary of English

  • Project G.e.e.K.e.R. — Project G.eeK.eR. is an animated television series that premiered on CBS on September 14, 1996. It was created by Douglas TenNapel, creator of Earthworm Jim , with original music by Shawn Patterson (main title theme by Terry Scott Taylor).… …   Wikipedia

  • Project-x — Éditeur Team17 Développeur Team17 Concepteur Martin Brown (chef de projet) Date de sortie 1992 Genre Shoot them up Mode de jeu …   Wikipédia en Français

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”