Tenom Pangi Dam is the hydroelectric plant in Tenom, Sabah, Malaysia. It is located 120 km south of Kota Kinabalu on the Padas River. The project is a run-off river hydroelectric power plant.

Power station

The power station is a hydroelectric power station, using 3 turbines of 22 MW installed capacity totaling 66 MW. Continuous power output is 66 MW. Average annual energy output is 400 GWh. The station is operated by Sabah Electricity.

Tenom Pangi Dam

Construction started 1978 and completed in 1984. The dam began operation on 1984. The plant suffered extensive flood damage in 1988, where the trash rack and log boom were washed away and damaged the intake and gate machinery. It was refurbished in 2003.

Tenom Pangi Dam technical specifications

The permanent dam components are as follows:
*Power Intake Structure - 3 bays.
*Spillway- gated concrete weir run-off river type..
*Power Tunnels – 3 exposed penstock..
*Powerhouse
**powerhouse – above ground 4 levels
**with 3 penstocks to powertrains comprising 3 turbines of 22MW each, 4 air-cooled generators of 25MVA each and 3 transformers of 25MVA each.

Notable facts

*Tenom Pangi Dam is the only major hydroelectric dam in Sabah.

ee also

*Tenaga Nasional
*Sabah Electricity
*Batang Ai Dam

References

Japan ODA Bank document [http://www.jbic.go.jp/english/oec/post/2004/pdf/2-23_full.pdf]

External links

Homepage of Sabah Electricity [http://www.sesb.com.my/]


Wikimedia Foundation. 2010.

Игры ⚽ Нужна курсовая?

Look at other dictionaries:

  • Sabah Electricity — Sdn Bhd (SESB) is an electric power generation and transmission and distribution company. It is the only power utility company in Sabah, Malaysia. There are 361,400 customers distributed over an area of 74,000 sq.km. Most (83%) of the customers… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”