- Resource Leveling
Resource Leveling is a
project management process used to examine a project for an unbalanced use of resources (usually people) over time, and for resolving over-allocations orconflict s.When performing
project planning activities, the manager will attempt to schedule certain taskssimultaneous ly. When more resources such asmachine s or people are needed than are available, or perhaps a specific person is needed in both tasks, the tasks will have to be rescheduled concurrently or even sequentially to manage the constraint. Project planning resource leveling is the process of resolving these conflicts. It can also be used to balance the workload of primary resources over the course of the project, usually at the expense of one of the traditional triple constraints (time, cost, scope).When using specially designed project software, leveling typically means resolving conflicts or over allocations in the project plan by allowing the software to calculate delays and update tasks
automatic ally. Projectmanagement software leveling requires delaying tasks until resources are available.In either
definition , leveling could result in a later project finish date if the tasks affected are in the critical path.References
Project Management Institute "A Guide to the Project Management Body of Knowledge", Third Edition, 2004 Project Management Institute, Inc. ISBN-10 193069945X, ISBN-13: 978-1930699458
Microsoft Office Online: Project 2003
ee also
*
Resource Allocation
*Project Management External links
* [http://www.pmi.org/info/default.asp Project Management Institute (PMI)]
* [http://office.microsoft.com/en-us/project/HA012316471033.aspx?pid=CH100667251033 Microsoft Office Project 2007]
* [http://www.chachris.com/index_files/unlimited_resource_leveling.htm Unlimited Resource Leveling using Minimum Moment Method and PACK]
* [http://www.openworkbench.org/ Open Workbench, open source free project software]
* [http://www.ce.cmu.edu/pmbook/10_Fundamental_Scheduling_Procedures.html Project Management for Construction, by Chris Hendrickson]
* [http://www.dbcenter.cise.ufl.edu/seek/Publications/RCPSP_YGO.pdf Resource-Constrained Project Scheduling: Past Work and New Directions, by Bibo Yang, Joseph Geunes, William J. O'Brien]
* [http://www.springerlink.com/index/CAGPW559AX96QR0R.pdf Petri Nets for Project Management and Resource Levelling, by V. A. Jeetendra, O. V. Krishnaiah Chetty, J. Prashanth Reddy]
Wikimedia Foundation. 2010.