- Big Hill
s and remains so to this day. It cannot be said that the railway ever conquered the mountains, only that the railway copes with the challenge and the mountains tolerate the railway.
To complete the Pacific railway as quickly as possible, a decision was made to delay blasting a lengthy 1400-foot (430 m) tunnel through
Mount Stephen and instead build a temporary eight-mile (13 km) line over it. Instead of the desired 2.2% grade (116 feet to the mile) a steep 4.5% grade was built in 1884 (some sources say 4.4%). This was one of the steepest railway lines anywhere. It descended fromWapta Lake to the base of Mount Stephen, along theKicking Horse River to a point just west of Field, then rose again to meet the original route.Three safety switches were built to protect against runaway trains. These switches led to short spurs with a sharp reverse upgrade and they were kept in the uphill position until the operator was satisfied that the train descending the grade towards him was not out of control. Speed was restricted to eight miles per hour (13 km/h) for passenger trains and six (10 km/h) for freight, and elaborate brake testing was required of trains prior to descending the hill. Nevertheless, disasters occurred with dismaying frequency.
Field was created solely to accommodate the CPR’s need for additional locomotives to be added to trains about to tackle the Big Hill. Here a stone roundhouse with turntable was built at what was first known simply as Third Siding. In December 1884 the CPR renamed it Field after C.W. Field, a Chicago businessman who, the company hoped, might invest in the region after he had visited on a special train they had provided for him.
At that time, standard steam locomotives were
4-4-0 s, capable enough for the prairies and elsewhere, but of little use on the Big Hill.Baldwin Locomotive Works was called upon to build two2-8-0 s for use as Field Hill pusher engines in 1884. At the time they were the most powerful locomotives built. Two more followed in June 1886. The CPR began building its own 2-8-0s in August 1887, and over the years hundreds more were built or bought.The Spiral Tunnels
The Big Hill "temporary" line was to remain the main line for twenty-five years, until the famous Spiral Tunnels were opened on
September 1 ,1909 .The improvement project was started in 1906, under the supervision of
John Edward Schwitzer , the senior engineer of CPR’s western lines. The first proposal had been to extend the length of the climb, and thus reduce the gradient, by bypassing the town of Field at a higher level, on the south side of the Kicking Horse river valley. This idea had quickly been abandoned because of the severe risk of avalanches and landslips on the valley side. Also under consideration was the extension of the route in a loop northwards, using both sides of the valley of the Yoho river to increase the distance, but again the valley sides were found to be prone to avalanches. It was the experience of severe disruption and delay caused by avalanches on other parts of the line (such as at theRogers Pass station, which was destroyed by an avalanche in 1899) that persuaded Schwitzer that the expensive solution of digging "spiral tunnels" was the only practical way forward.The route decided upon called for two tunnels driven in three-quarter circles into the valley walls. The higher tunnel, "number one," was about one thousand yards in length and ran under
Cathedral Mountain , to the south of the original track. When the new line emerged from this tunnel it had doubled back, running beneath itself and fifty feet lower. It then descended the valley side in almost the opposite direction to its previous course before crossing the Kicking Horse River and enteringMount Ogden to the north. This lower tunnel, "number two," was a few yards shorter than "number one" and the descent was again about fifty feet. From the exit of this tunnel the line continued down the valley in the original direction, towards Field. The constructions and extra track would effectively double the length of the climb and reduce theruling gradient to 2.2%.The contract was awarded to
MacDonnell, Gzowski and Company and work started in 1907. The labor force amounted to about a thousand and the cost was about 1.5 million Canadian dollars.Even after the opening of the spiral tunnels,
Field Hill remained a significant challenge and it was necessary to retain the powerful locomotives at Field locomotive depot.ee also
*
Spiral (railway)
*Tehachapi Loop
*Table of turn tunnels References
*
*
*
*
*
*
*External links
* [http://www.scenic-railroads.com www.scenic-railroads.com A gallery of Big Hill and related rail photos]
Wikimedia Foundation. 2010.