Earned Schedule

Earned Schedule

Earned Schedule (ES) is an extension to the theory and practice of Earned Value Management (EVM). As of 2005, Earned Schedule is designated as an "emerging practice" by the Project Management Institute. It was introduced in 2003 a seminal article "Schedule is Different" by Walter Lipke, in "The Measurable News", the quarterly magazine of the College of Performance Management, of the Project Management Institute.

Traditionally, EVM tracks schedule variances "not" in units of time, but in units of currency (e.g. dollars) or quantity (e.g. labor hours). Of course, it is more natural to speak of schedule performance in units of time, but the problems with traditional schedule performance metrics are even deeper. Near the end of a project -- when schedule performance is often a primary concern -- the usefulness of traditional schedule metrics is demonstrably poor. In traditional EVM, a schedule variance (SV) of 0 or a schedule performance index (SPI) of 1 indicates that a project is exactly on schedule. However, when a project is completed, its SV is always 0 and SPI is always 1, even if the project was delivered unacceptably late. Similarly, a project can languish near completion (e.g. SPI = 0.95) and never be flagged as outside acceptable numerical tolerance. (Using traditional SV as an exception threshold, it is not uncommon that an SPI > 0.9 is considered acceptable.)

To correct these problems, Earned Schedule theory renames the two traditional measures SV and SPI as SV($) and SPI($), to indicate clearly they are in units of currency or quantity, not time. Then, time-based quantities SV(t) and SPI(t) are created. A stated advantage of Earned Schedule methods is that no new data collection processes are required to implement and test Earned Schedule; it only requires updated formulas. Earned Schedule theory also provides updated formulas for predicting project completion date, using the time-based measures.

It has been stated that Earned Schedule provides a useful link between traditional Earned Value Analysis and traditional project schedule analysis -- a link that some say has been missing in traditional EVM theory.

External links

* [http://www.earnedschedule.com Earned Schedule Web Site]
* [http://sydney.pmichapters-australia.org.au/programs/customer/v_itemcatg.asp?P=31&ICID=105& PMI Sydney Chapter Web Site]


Wikimedia Foundation. 2010.

Игры ⚽ Поможем сделать НИР

Look at other dictionaries:

  • Earned value management — (EVM) is a project management technique for measuring project performance and progress in an objective manner. EVM has the ability to combine measurements of scope, schedule, and cost in a single integrated system. Earned Value Management is… …   Wikipedia

  • Earned premium — is the portion of an insurance written premium which is considered earned by the insurer, based on the part of the policy period that the insurance has been in effect, and during which the insurer has been exposed to loss. For instance, if a 365… …   Wikipedia

  • Earned Value Analysis — Die Earned Value Analysis bzw. Leistungswertanalyse (z.T. auch als Fertigstellungswertmethode oder Arbeitswertanalyse bezeichnet) ist ein Werkzeug des Projektcontrollings. Sie dient zur Fortschrittsbewertung von Projekten. Dabei wird die aktuelle …   Deutsch Wikipedia

  • Earned Value — Die Earned Value Analysis bzw. Leistungswertanalyse (z.T. auch als Fertigstellungswertmethode oder Arbeitswertanalyse bezeichnet) ist ein Werkzeug des Projektcontrollings. Sie dient zur Fortschrittsbewertung von Projekten. Dabei wird die aktuelle …   Deutsch Wikipedia

  • Earned Value Management — Die Earned Value Analysis bzw. Leistungswertanalyse (z.T. auch als Fertigstellungswertmethode oder Arbeitswertanalyse bezeichnet) ist ein Werkzeug des Projektcontrollings. Sie dient zur Fortschrittsbewertung von Projekten. Dabei wird die aktuelle …   Deutsch Wikipedia

  • Earned value analysis — Die Earned Value Analysis bzw. Leistungswertanalyse (z.T. auch als Fertigstellungswertmethode oder Arbeitswertanalyse bezeichnet) ist ein Werkzeug des Projektcontrollings. Sie dient zur Fortschrittsbewertung von Projekten. Dabei wird die aktuelle …   Deutsch Wikipedia

  • Schedule (project management) — In project management, a schedule consists of a list of a project s terminal elements with intended start and finish dates.Creating a project scheduleBefore a project schedule can be created, a project manager should typically have a work… …   Wikipedia

  • Earned income tax credit — The United States federal Earned Income Tax Credit (EITC or EIC) is a refundable tax credit. For tax year 2007, a claimant with one qualifying child can receive a maximum credit of $2,853. For two or more qualifying children, the maximum credit… …   Wikipedia

  • Schedule Performance Index — Der Begriff Planleistungsindex (PLI) oder englisch Schedule Performance Index (SPI) steht für das Verhältnis von geleisteter zu geplanter Arbeit. Nach Project Management Institute heißt dies Schedule Performance Indicator. Anwendung Benutzt wird… …   Deutsch Wikipedia

  • Schedule K-1 — A tax document used to report the incomes, losses and dividends of a business s partners or S corporation s shareholders. Rather than being a financial summary for the entire group, the Schedule K 1 document is prepared for each partner or… …   Investment dictionary

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”