Event chain methodology

Event chain methodology

project management. [Virine, L. and Trumper M., "Project Decisions: The Art and Science" (2007). Management Concepts. Vienna, VA, ISBN 978-1567262179 ] .

Event chain methodology helps to mitigate effect motivational and cognitive biases in estimating and scheduling. [Robyn M. Dawes and Bernard Corrigan, ‘‘Linear Models in Decision Making’’Psychological Bulletin 81, no. 2 (1974): 93–106.] [Tversky, A., and D. Kahneman, ‘‘Judgment under uncertainty: heuristics and biases’’ Science 185 (1972): 1125-1130.] . In many cases, project managers intentionally or unintentionally create project schedules that are impossible to implement [ [http://flyvbjerg.plan.aau.dk/Publications2006/Nobel-PMJ2006.pdf Flyvbjerg, B. ‘‘From Nobel Prize to project management: getting risks right’’. Project Management Journal, (2006): pp 5-15.] ] [ [http://flyvbjerg.plan.aau.dk/JAPAASPUBLISHED.pdf Flyvbjerg, B., M.K.S. Holm, and S.L. Buhl. ‘‘Underestimating costs in public works projects: Error or Lie?’’ Journal of the American Planning Association 68 no 3 (2002): 279-295] ] . The methodology also simplifies the process of defining risks and uncertainties in project schedules, particularly by improving the ability to provide reality checks and to visualize multiple events.Event chain methodology is used to perform more accurate quantitative analysis while taking into account such factors as relationships between different events and actual moments of the events.

Event Chain Methodology Principles

Moment of risk and state of activity

An activity (task) in most real life processes is not a continuous uniform procedure. Tasks are affected by external events, which transform an activity from one state to another. One of the important properties of an event is the moment when an event occurs during the course of an activity. This moment, when an event occurs, in most cases is probabilistic and can be defined using statistical distribution.

Event Chains

Events can cause other events, which will create event chains. These event chains can significantly affect the course of the project. For example, requirement changes can cause an activity to be delayed. To accelerate the activity, the project manager allocates a resource from another activity, which then leads to a missed deadline. Eventually, this can lead to the failure of the project.

Monte Carlo Simulations

Once events and event chains are defined, quantitative analysis using Monte Carlo simulation can be performed to quantify the cumulative effect of the events. Probabilities and effects of risks are used as input data for Monte Carlo simulation of the project schedule [Williams, T. ‘‘Why Monte Carlo simulations of project networks can mislead’’. Project Management Journal, Vol 23. No 3, (2006): 53-61] . In most real life projects, it is necessary to supplement the information regarding the uncertainties expressed as an event, with distributions related to duration, start time, cost, and other parameters.

Critical Event Chains

The single events or the event chains that have the most potential to affect the projects are the “critical events” or “critical chains of events.” By identifying critical events or critical chains of events, we can mitigate their negative effects. These critical chains of events can be identified by analyzing the correlations between the main project parameters, such as project duration or cost, and the event chains.

Performance Tracking with Event Chains

Monitoring the activity's progress ensures that updated information is used to perform the analysis. During the course of the project, the probability and time of the events can be recalculated based on actual data. The main issue with performance tracking is forecasting an activity’s duration and cost if an activity is partially completed and certain events are assigned to the activity. The simple heuristic approach to this problem is to analyze the moment of risk, which is defined as one of the event parameters. Advanced analysis can be performed using a Bayesian approach.

Event Chain Diagrams

Event Chain Diagrams are visualizations that show the relationships between events and tasks and how the events affect each other. The simplest way to represent these chains is to depict them as arrows associated with certain tasks or time intervals on the Gantt chart. Different events and event chains can be displayed using different colors. Events can be global (for all tasks in the project) and local (for a particular task). By using Event Chain Diagrams to visualize events and event chains, the modeling and analysis of risks and uncertainties can be significantly simplified.

Event Chain Methodology Phenomena

Repeated Activities

Sometimes events can cause the start of an activity that has already been completed. This is a very common scenario for real life projects; sometimes a previous activity must be repeated based on the results of a succeeding activity Modeling of these scenarios using event chain methodology is simple. The original project schedule does not need to be updated, as all that is required is to define the event and assign it to an activity that points to the previous activity. In addition, a limit to the number of times an activity can be repeated needs to be defined.

Event Chains and Risk Mitigation

If event or event chain occurs during the course of a project, it may require some mitigation effort. In some cases, mitigation plans can be generated. Mitigation plans are an activity or group of activities (small schedule) that augment the project schedule if a certain event occurs. The solution is to assign the mitigation plan to an event or event chain. These small schedules will be triggered when an event chain occurs. The same mitigation plan can be used for different events.

Resource Allocation Based on Events

One potential event is the reassignment of a resource from one activity to another, which can occur under certain conditions. For example, if an activity requires more resources to complete it within a fixed period, this will trigger an event to reallocate the resource from another activity. Reallocation of resources can also occur when activity duration reaches a certain deadline or the cost exceeds a certain value. Events can be used to model different situations with resources, e.g. temporary leave, illness, vacations, etc.

ee also

*Monte Carlo simulation
*List of project management topics
*Program Evaluation and Review Technique
*Project
*Project management
*Project planning
*Work breakdown structure
*List of project management software

Bibliography

*Arnaud Doucet, Nando de Freitas and Neil Gordon, "Sequential Monte Carlo methods in practice", 2001, ISBN 0-387-95146-6.
*Hammond, J.S. and Keeney, R.L. and Raiffa, H., "Smart Choices: A Practical Guide to Making Better Decisions" (1999). Harvard Business School Press
*Keeney, R.L.,"Value-focused thinking -- A Path to Creative Decisionmaking" (1992). Harvard University Press. ISBN 0-674-93197-1
*Matheson, David, and Matheson, Jim, "The Smart Organization: Creating Value through Strategic R&D "(1998). Harvard Business School Press. ISBN 0-87584-765-X
*Raiffa, Howard, "Decision Analysis: Introductory Readings on Choices Under Uncertainty" (1997). McGraw Hill. ISBN 0-07-052579-X
*Robert C.P. and G. Casella. "Monte Carlo Statistical Methods" (second edition). New York: Springer-Verlag, 2004, ISBN 0-387-21239-6
*Skinner, David, "Introduction to Decision Analysis, 2nd Edition" (1999). Probabilistic. ISBN 0-9647938-3-0
*Smith, J.Q., "Decision Analysis: A Bayesian Approach" (1988), Chapman and Hall. ISBN 0-412-27520-1
*Judgement under Uncertainty: Heuristics and Biases, ed. D. Kahneman and A. Tversky,(Cambridge University Press, 1982) ISBN 0-521-28414-7

References

External links

* [http://www.projectdecisions.org/paper/Paper_EventChainMeethodology.pdf Event Chain Methodology in Details]
* [http://yosemite.epa.gov/oswer/ceppoweb.nsf/content/EPAguidance.htm#General U.S. EPA's General Risk Management Program Guidance (April 2004)]
* [http://csrc.nist.gov/publications/nistpubs/800-30/sp800-30.pdf NIST Special Publication 800-30 Risk Management Guide for Information Technology Systems (July 2002)]
* [http://www.intaver.com/Articles/RP_Art_EventChainMethodology.html Project Management Using Event Chain Methodology]
* [http://www.planningengineers.org/publications/papers_download.aspx?id=20 Project Planning Using Event Chain Methodology]
* [http://www.ce.cmu.edu/pmbook/10_Fundamental_Scheduling_Procedures.html Project Management for Construction, by Chris Hendrickson]
* [http://www.dbcenter.cise.ufl.edu/seek/Publications/RCPSP_YGO.pdf Resource-Constrained Project Scheduling: Past Work and New Directions]
* [http://www.springerlink.com/index/CAGPW559AX96QR0R.pdf Petri Nets for Project Management and Resource Levelling]


Wikimedia Foundation. 2010.

Игры ⚽ Нужно решить контрольную?

Look at other dictionaries:

  • Event Chain Diagrams — are visualizations that show the relationships between events and tasks and how the events affect each other. Event chain diagram are introduced as a part of Event chain methodology. Event chain methodology is an uncertainty modeling and schedule …   Wikipedia

  • Event — The word event can have several meanings:In culture and social life:* Festival, for example a musical event * Ceremony, for example a marriage * Competition, for example a sports competition * Party, for example a birthday party * Convention… …   Wikipedia

  • Critical Chain Project Management — (CCPM) is a method of planning and managing projects that puts more emphasis on the resources required to execute project tasks developed by Eliyahu M. Goldratt. This is in contrast to the more traditional Critical Path and PERT methods, which… …   Wikipedia

  • Critical chain project management — Critical Chain redirects here. For the novel, see Critical Chain (novel). Critical chain project management (CCPM) is a method of planning and managing projects that puts the main emphasis on the resources required to execute project tasks. It… …   Wikipedia

  • Project management — is the discipline of planning, organizing, securing, and managing resources to achieve specific goals. A project is a temporary endeavor with a defined beginning and end (usually time constrained, and often constrained by funding or deliverables) …   Wikipedia

  • RiskyProject — Infobox Software name = RiskyProject | caption = RiskyProject developer = Intaver Institute latest release version = RiskyProject 2.1 latest release date = 2007 operating system = Microsoft Windows genre = Project management software license =… …   Wikipedia

  • Risk management — For non business risks, see risk, and the disambiguation page risk analysis Example of risk management: A NASA model showing areas at high risk from impact for the International Space Station. Risk management is the identification, assessment,… …   Wikipedia

  • Risk — takers redirects here. For the Canadian television program, see Risk Takers. For other uses, see Risk (disambiguation). Risk is the potential that a chosen action or activity (including the choice of inaction) will lead to a loss (an undesirable… …   Wikipedia

  • Risk register — A risk register is a tool commonly used in project planning and organisational risk assessments. It is often referred to as a Risk Log (for eg in PRINCE2).This tool is widely used within Risk Management for identifying, analysing and managing… …   Wikipedia

  • List of Theory of Constraints topics — This is a list of topics related to the Theory of Constraints.ABBottleneck (Bn) This is a resource that has just enough capacity or less capacity than is needed to satisfy the demand placed upon it. Bottlenecks may need to be taken into account… …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”