- Ffos-y-fran
Ffos-y-fran is a district of
Merthyr Tydfil ,Wales (coord|51.73|N|03.36|W|region:GB SO0605).The Ffos-y-fran Land Reclamation Scheme is a joint development undertaken by Miller Argent (South Wales) Ltd, a jointly owned company between The Miller Group Ltd,
Argent Group PLC and Bernard J. Llewellyn JP representing family interests of the land. The scheme development is the last part of the East Merthyr Reclamation scheme, and will extract 10 million tonnes of coal over 15 years, the revenues from which will redevelop the current former industrial workings into residential and recreational use.The
opencast coal mine has provoked criticism at a local and national scale, including objections on health and safety grounds as to the close proximity of housing to the site, concerns of the despoiling of the landscape, and global concerns of the contribution of coal toclimate change . [ [http://www.monbiot.com/archives/2007/10/09/the-new-coal-age/ "The New Coal Age"] George Monbiot,The Guardian , 9 October 2007] [ [http://gristmill.grist.org/story/2007/7/12/11229/8694 "Coal is the enemy of the human race"] DrJames Hansen , 12 July 2007] A number of protests have occurred on and around the site. [http://news.bbc.co.uk/1/hi/wales/south_east/7128984.stm "Protest halts opencast mine work"] BBC News, 5 December 2007]Open-Cast at Ffos-y-fran
Background
Following the 18th century development of Merthyr as an industrial centre, and the shut-down of the deepcast coal mining industry from the 1930s through to the 1980s, the area to the east of Merthyr Tydfil has suffered severe dereliction. The East Merthyr Reclamation Scheme was the initiative of the former Merthyr Tydfil Borough Council and Mid Glamorgan County Council, in partnership with the
Welsh Development Agency in the mid 1980s and was launched by the Secretary of State for Wales following the grant of planning permission. The aim was to extract coal from the area of East Merthyr by the cheapest and most profitable means, rather than detracting from it and its environment.The East Merthyr Reclamation Scheme is a euphemism for
opencast mining. The presentation of plans for this include provisions for subsequent reclamation of the landscape. Phases I and II of the Scheme have been completed, restoring 106ha of derelict land to provide residential, light industrial and recreational uses.The Ffos-y-fran Land Reclamation Scheme is said to be the final stage of the East Merthyr Reclamation Scheme.
Planning
Planning consent for Phase III was granted in November 1988. However, local debates continued over the nature and scale of the development which will lead to the extraction of 10 m tonnes of coal over 15 yearscite news|url=http://news.bbc.co.uk/1/hi/wales/3125045.stm|title=Battle against opencast plan|publisher=
BBC |date=2003-08-05|accessdate=2007-10-19] ; as well as commercial concerns over the size of the coal reserve, together with access rights to the land. Protesters said that if the scheme proceeded, it would mean work taking place just a few hundred metres away from homes in the villages ofDowlais , Mountain Hare, andPenydarren ; some houses would be less than 40 m from the boundary of the site. [cite news|url=http://news.bbc.co.uk/1/hi/wales/4414717.stm|title=Opencast protesters want 'buffer'|publisher=BBC |date=2005-04-06|accessdate=2007-10-19]In 1994 the scheme was revised to claim a larger coal reserve in line with government guidance, termed Phase IIIA. This was withdrawn in May 1999 due to access rights issues.
Access rights were resolved by Miller Argent in 2003, and a new application was brought to Merthyr Council and the
Welsh Assembly . In February 2005 the Welsh Assembly approved the Ffos-y-Fran scheme, but the High Court quashed the decision after it was claimed by local residents that Environment MinisterCarwyn Jones had made his mind up before the planning committee met.Mr Jones denied the claim and the Welsh Assembly took the case to appeal judges, who gave final approval of the scheme on 27 November 2006 [cite news|url=http://news.bbc.co.uk/1/hi/wales/south_east/6185998.stm|title=Go-ahead for huge opencast mine|publisher=
BBC |date=2006-11-27|accessdate=2007-10-19]cale
The Ffos-y-fran Land Reclamation Scheme is the largest of the original three phases and will restore 367ha of derelict land, including the removal of known shafts previously associated with
iron ore and coal workings, to finally complete the original land reclamation scheme.Statistics surrounding the site which include:
*Phase III in total covers convert|3500|acre|km2 of land
*Since 2002 the Council have removed 58 burnt out and stolen cars from the site
*200 people will be employed on the site, with an additional estimated 400 jobs created within the local area
*The scheme at peak production will extract 20,000 tonnes of coal per week
*In total, 30 million tonnes of thegreenhouse gas carbon dioxide will be emitted from the coal extracted from Ffos-y-franReferences