- Product based planning
Product Based Planning is mandated for
PRINCE2 projects and is a method of identifying all of the products and associated work required to complete aproject .Description
Product based planning is intended to ensure that all of the necessary products that will go towards delivering the objectives of the project are identified and captured.
Planning begins by identifying a
product breakdown structure which is then repeatedly refined until all of the requisite products are identified. The PBS is thus ahierarchical family tree of all the products and sub-products that comprise your final end-product.It is important to understand that in this context the term 'product' includes intermediate documentary products that are essential to the work of delivering the project. In this sense the product breakdown structure is a great deal "more" than simply an exploded view of the final end-product. Products included might also be products required to manage the project such as paper based products and quality products such as approvals or quality checks on earlier made products. Examples include such things as requirement specifications, design approvals, test documentation, safety certifications, and so on.
Once a product breakdown structure has been created, work can then begin on creating a 'product flowchart'. The product flowchart identifies the order of precedence of products and will typically include multiple and complex parallel paths. For practical purposes this flowchart is essentially the same as the
PERT chart used forCritical path method and leads naturally forward to the development of a project schedule.A significant advantage of product based planning is the ability to surface critical assumptions and constraints. For example, if your project is to build another floor on top of a house a required "product" will be the floor underneath on which to build the one you are commissioned to deliver. As a "product" you hope that it is there and will be fit for purpose but as you are not commissioned to deliver it, it falls outside your scope - and into your assumptions. In this way, by defining the "whole" product set necessary for the project, and not just those that are in your scope, you can surface and document the critical assumptions. Another advantage compared to activity-based planning has to do with reporting. Products are either finished or not, activities can be 90% finished for a long time even though work is taking place. One tends to forget things that have to be done to complete a project. This method captures them all, reducing the chance that any will be overlooked.This method is used in prince2
Example
A
refrigerator is a final product with sub-products being door, shelves, heat exchange unit, fans, ice cube dispensers, lights, etc.Each of the sub-products are made up of smaller products such as door handle, insulation, magnetic closure strip and internal covering.