Product based planning

Product based planning

Product Based Planning is mandated for PRINCE2 projects and is a method of identifying all of the products and associated work required to complete a project.

Description

Product based planning is intended to ensure that all of the necessary products that will go towards delivering the objectives of the project are identified and captured.

Planning begins by identifying a product breakdown structure which is then repeatedly refined until all of the requisite products are identified. The PBS is thus a hierarchical family tree of all the products and sub-products that comprise your final end-product.

It is important to understand that in this context the term 'product' includes intermediate documentary products that are essential to the work of delivering the project. In this sense the product breakdown structure is a great deal "more" than simply an exploded view of the final end-product. Products included might also be products required to manage the project such as paper based products and quality products such as approvals or quality checks on earlier made products. Examples include such things as requirement specifications, design approvals, test documentation, safety certifications, and so on.

Once a product breakdown structure has been created, work can then begin on creating a 'product flowchart'. The product flowchart identifies the order of precedence of products and will typically include multiple and complex parallel paths. For practical purposes this flowchart is essentially the same as the PERT chart used for Critical path method and leads naturally forward to the development of a project schedule.

A significant advantage of product based planning is the ability to surface critical assumptions and constraints. For example, if your project is to build another floor on top of a house a required "product" will be the floor underneath on which to build the one you are commissioned to deliver. As a "product" you hope that it is there and will be fit for purpose but as you are not commissioned to deliver it, it falls outside your scope - and into your assumptions. In this way, by defining the "whole" product set necessary for the project, and not just those that are in your scope, you can surface and document the critical assumptions. Another advantage compared to activity-based planning has to do with reporting. Products are either finished or not, activities can be 90% finished for a long time even though work is taking place. One tends to forget things that have to be done to complete a project. This method captures them all, reducing the chance that any will be overlooked.This method is used in prince2

Example

A refrigerator is a final product with sub-products being door, shelves, heat exchange unit, fans, ice cube dispensers, lights, etc.

Each of the sub-products are made up of smaller products such as door handle, insulation, magnetic closure strip and internal covering.

ee also

* List of project management topics
* PRINCE2
* Managing Stage Boundaries (SB)


Wikimedia Foundation. 2010.

Игры ⚽ Нужен реферат?

Look at other dictionaries:

  • Assumption based planning — is a post planning method that helps companies to deal with uncertainty. It is used to identify the most important assumptions in a company’s business plans, test these assumptions and think of hedging actions and what if scenarios. Assumption… …   Wikipedia

  • Product breakdown structure — In project management, a product breakdown structure (PBS) is an exhaustive, hierarchical tree structure of components that make up an item, arranged in whole part relationship. A PBS can help clarify what is to be delivered by the project and… …   Wikipedia

  • Product data management — (PDM) is the business function within product lifecycle management that is responsible for the creation, management and publication of product data. Introduction Product data management (PDM) is focused on information relative to core operations… …   Wikipedia

  • Product lifecycle management — (PLM) is the process of managing the entire lifecycle of a product from its conception, through design and manufacture, to service and disposal. [cite web title = About PLM publisher = CIMdata url = http://www.cimdata.com/PLM/aboutPLM.html ] PLM… …   Wikipedia

  • Planning poker — is a consensus based estimation technique for estimating, mostly used to estimate effort or relative size of tasks in software development. It is a variation of the Wideband Delphi method. It is most commonly used in agile software development,… …   Wikipedia

  • planning — plan‧ning [ˈplænɪŋ] noun [uncountable] when you think carefully about something you want to do in the future, and decide exactly how you will do it: • If you want to ensure a trouble free retirement, it s never too early to start financial… …   Financial and business terms

  • Product life cycle management — is the succession of strategies used by management as a product goes through its product life cycle. The conditions in which a product is sold changes over time and must be managed as it moves through its succession of stages. Product life… …   Wikipedia

  • Product software implementation method — A product software implementation method is a systematically structured approach to effectively integrate a software based service or component into the workflow of an organizational structure or an individual end user.This entry focuses on the… …   Wikipedia

  • Commercial planning — is the term commonly used for commercializing a product. The success of a new product depends not only on the idea behind the product, but also on the marketing of the new product before, during and after the product launch. New Product Launching …   Wikipedia

  • New product development — In business and engineering, new product development (NPD) is the term used to describe the complete process of bringing a new product to market. A product is a set of benefits offered for exchange and can be tangible (that is, something physical …   Wikipedia

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”