TGV track construction

TGV track construction

LGV construction is the process by which the land on which TGV trains are to run is prepared for their use, involving carving the trackbed and laying the track. It is similar to the building of standard railway lines, but there are differences. In particular, construction process is more precise in order for the track to be suitable for regular use at 300 km/h (186 mph). The quality of construction was put to the test in particular during the TGV world speed record runs on the LGV Atlantique; the track was used at over 500 km/h (310 mph) without suffering significant damage. This contrasts with previous French world rail speed record attempts which resulted in severe deformation of the track.

Preparing the trackbed

The work on a high-speed line (ligne à grande vitesse, or LGV) begins with earth moving. The trackbed is carved into the landscape, using scrapers, graders, bulldozers and other heavy machinery. All fixed structures are built; these include bridges, flyovers, culverts, game tunnels, and the like. Drainage facilities, most notably the large ditches on either side of the trackbed, are constructed. Supply bases are established near the end of the high-speed tracks, where crews will form work trains to carry rail, sleepers and other supplies to the work site.

Next, a layer of compact gravel is spread on the trackbed. This, after being compacted by rollers, provides an adequate surface for vehicles with tyres. TGV tracklaying then proceeds. The tracklaying process is not particularly specialized to high-speed lines; the same general technique is applicable to any track that uses continuous welded rail. The steps outlined below are used around the world in modern tracklaying. TGV track, however, answers to stringent requirements that dictate materials, dimensions and tolerances.

Laying the track

To begin laying track, a gantry crane that rides on rubber tires is used to lay down panels of prefabricated track. These are laid roughly in the location where one of the tracks will be built (all LGVs have two tracks). Each panel is 18 metres (60 feet) long, and rests on wooden sleepers. No ballast is used at this stage, since the panel track is temporary.

Once the panel track is laid, a work train (pulled by diesel locomotives) can bring in the sections of continuous welded rail that will be used for the permanent way of this first track. The rail comes from the factory in lengths varying from 200 m (660 ft) to 400 m (1310 ft). Such long pieces of rail are just laid across several flatcars; they are very flexible, so this does not pose a problem. A special crane unloads the rail sections and places them on each side of the temporary track, approximately 3.5 m (12 ft) apart. This operation is usually carried out at night, for thermal reasons. The rail itself is standard UIC section, 60 kg/m (40 lb/ft), with a tensile strength of 800 newtons per square millimetre or megapascals (116,000 psi).

For the next step, a gantry crane is used again. This time, however, the crane rides on the two rails that were just laid alongside the temporary track. A train of flatcars, half loaded with LGV sleepers, arrives at the site. It is pushed by a special diesel locomotive, which is low enough to fit underneath the gantry cranes. The cranes remove the panels of temporary track, and stack them onto the empty half of the sleeper train. Next, they pick up sets of 30 LGV sleepers, pre-arranged with the proper spacing (60 cm, or 24 in), using a special fixture. The sleepers are laid on the gravel bed where the panel track was. The sleeper train leaves the worksite loaded with sections of panel track.

The sleepers, sometimes known as bi-bloc sleepers, are U41 twin block reinforced concrete, 2.4 m (7 ft 10 in.) wide, and weigh 245 kg (540 lb) each. They are equipped with hardware for Nabla RNTC spring fasteners, and a 9 mm (3/8 in.) rubber pad. (Rubber pads are always used under the rail on concrete sleepers, to avoid cracking). Next, a rail threader is used to lift the rails onto their final position on the sleepers. This machine rides on the rails just like the gantry cranes, but can also support itself directly on a sleeper. By doing this, it can lift the rails, and shift them inwards over the ends of the sleepers, to the proper gauge (standard gauge). It then lowers them onto the rubber sleeper cushions, and workers use a pneumatically operated machine to bolt down the Nabla clips with a predetermined torque. The rails are canted inward at a slope of 1 in 20.

Joining track sections

The sections of rail are welded together using thermite. Conventional welding (using some type of flame) does not work well on large metal pieces such as rails, since the heat is conducted away too quickly. Thermite is better suited to this job. It is a mix of aluminium powder and rust (iron oxide) powder, which reacts to produce iron, aluminum oxide, and a great deal of heat, making it ideal to weld rail.

Before the rail is joined, its length must be adjusted very accurately. This ensures that the thermal stresses in the rail after it is joined into one continuous piece do not exceed certain limits, resulting in lateral kinks (in hot weather) or fractures (in cold weather). The joining operation is performed by an aluminothermic welding machine which is equipped with a rail saw, a weld shear and a grinder. When the thermite welding process is complete, the weld is ground to the profile of the rail, resulting in a seamless join between rail sections. Stress in the rail due to temperature variations is absorbed without longitudinal strain, except near bridges where an expansion joint is sometimes used.

Adding ballast

The next step consists of stuffing a deep bed of ballast underneath the new track. The ballast arrives in a train of hopper cars pulled by diesel locomotives. Handling this train is challenging, since the ballast must be spread evenly. If the train stops, ballast can pile over the rails and derail it.

A first layer of ballast is dumped directly onto the track, and a tamping-lining-levelling machine, riding on the rails, forces the stones underneath the sleepers. Each pass of this machine can raise the level of the track by 8 cm (3 in), so several passes of ballasting and of the machine are needed to build up a layer of ballast at least 32 cm (1 ft) thick under the sleepers. The ballast is also piled on each side of the track for lateral stability. The machine performs the initial alignment of the track. Next, a ballast regulator distributes the ballast evenly. Finally, a dynamic vibrator machine shakes the track to perform the final tamping, effectively simulating the passing of 2500 axles.

Finishing construction

Now that the first track is almost complete, work begins on the adjacent track. This time, however, it is not necessary to lay a temporary track. Trains running on the first track bring the sleepers, and then the rail, which is unloaded directly onto the sleepers by dispensing arms that swing out to the proper alignment. The Nabla fasteners are secured, and the ballast is stuffed under the track as before.

The two tracks are now essentially complete, but the work on the line is not finished. The catenary masts need to be erected, and the wire strung on them. Catenary installation is not complicated; it will suffice to give a brief summary of specifications. The steel masts are I-beams, placed in a concrete foundation up to 63 m (206 ft) apart. The supports are mounted on glass insulators. The carrier wire is bronze, 65 mm² cross section, 14 kN (3100 lbf) tension. The stitch wire is bronze, 15 m (49.21 ft) long, 35 mm² cross-section. The droppers are 5 mm stranded copper cable. The contact wire is hard drawn copper, 120 mm², flat section on the contact side, 14 kN tension. The maximum depth of the catenary (distance between carrier and contact wires) is 1.4 m (4.59 ft). The contact wire can rise a maximum of 240 mm (9.44 inches) but the normal vertical displacement does not exceed 120 mm (4.72 inches).

Now that the catenary is complete, the track is given final alignment adjustments down to millimeter tolerances. The ballast is then blown to remove smaller gravel fragments and dust, which might be kicked up by trains. This step is especially important on high-speed tracks, since the blast of a passing train is strong. Finally, TGV trains are tested on the line at gradually increasing speeds. The track is qualified at speeds slightly higher than will be used in everyday operations (typically 350 km/h, or 210 mph), before being opened to commercial service.


Wikimedia Foundation. 2010.

Игры ⚽ Поможем написать курсовую

Look at other dictionaries:

  • Track (rail transport) — Permanent way redirects here. For other uses, see Permanent way (disambiguation). Twin rail tracks in a wooded area …   Wikipedia

  • TGV world speed record — The TGV (train à grande vitesse, French for high speed train ) holds a series of world speed records achieved in the context of an active research and development program pursued by SNCF, the French national railway, and its industrial partners.… …   Wikipedia

  • TGV (SNCF) — TGV  Cet article concerne le TGV de la SNCF. Pour les autres trains roulant à grande vitesse, voir Train à grande vitesse. Pour les autres significations, voir TGV (homonymie). Logo …   Wikipédia en Français

  • TGV (train à grande vitesse) — TGV  Cet article concerne le TGV de la SNCF. Pour les autres trains roulant à grande vitesse, voir Train à grande vitesse. Pour les autres significations, voir TGV (homonymie). Logo …   Wikipédia en Français

  • TGV — The TGV ( train à grande vitesse , French for high speed train ) is France s high speed rail service developed by GEC Alsthom (now Alstom) and SNCF, the French national rail operator, and operated primarily by SNCF. Following the inaugural TGV… …   Wikipedia

  • TGV — Cet article concerne le TGV d Alstom. Pour les autres trains roulant à grande vitesse, voir Train à grande vitesse. Pour la grande vitesse ferroviaire en France, voir grande vitesse ferroviaire en France. Pour les articles homonymes, voir TGV… …   Wikipédia en Français

  • Development of the TGV — The idea of a high speed train in France was born about twenty years before the first TGVs entered service. At that time, about 1960, a radical new concept was thought up; combining very high speeds and steep grades would allow a railway to… …   Wikipedia

  • LGV Est — SNCF Name=PAGENAME ColourName=#dddddd The LGV Est européenne (sometimes referred to as LGV Est) is an extension to the French high speed TGV network, connecting Paris and Strasbourg. It provides fast service between Paris and the principal cities …   Wikipedia

  • V150 — The V150 is a specially configured TGV train which broke the world record for conventional rail trains on April 3, 2007. The train is French made and reached a speed of 574.8 kilometers per hour (357 mph). [cite news author=Associated Press title …   Wikipedia

  • T.G.V. — TGV  Cet article concerne le TGV de la SNCF. Pour les autres trains roulant à grande vitesse, voir Train à grande vitesse. Pour les autres significations, voir TGV (homonymie). Logo …   Wikipédia en Français

Share the article and excerpts

Direct link
Do a right-click on the link above
and select “Copy Link”