- Hai Van Tunnel
The Hai Van Tunnel, the longest tunnel in
Southeast Asia at 6.28km, lies on highway 1 between the two cities ofDanang andHuế in centralVietnam .History
The
Hai Van Pass has long been recognised as a major bottleneck. The concept of a tunnel to bypass the long route over the top had long been sought.Planning and Design
Route planning and design work started in January 1998 by a joint venture between Nippon Koei Company Limited Japan and Louis Berger International Inc., USA with the Vietnamese Transport Engineering Design Corporation (TEDI) providing consultation on the project.
Construction
The project's major constructors were a Vietnam-Japan joint venture, Hazama-Cienco 6, and a joint venture between Korea's Dong Ah construction company and Vietnam's Song Da Construction Corporation.
The tunnel officially opened on
June 5 , 2005.The main tunnel is 11.9 meters wide. A second tunnel running alongside the main tunnel is currently used for maintenance and emergencies but it is planned to expand this at a later date as traffic increases. It is connected to the main tunnel by 15 cross-tunnels. The tunnels have lighting, fire alarms, communication, water supply and treatment, ventilation fans, and radio broadcast systems.
The tunnel subsequently has received an award for quality by the American Construction Management Association. [ [http://english.vietnamnet.vn/biz/2007/01/657251/ VietNamNet - US association awards Hai Van Tunnel ] ]
Operation
Currently the single tunnel has one lane of traffic in each direction. As no overtaking is possible this can result in minor delays if you are stuck behind slow moving traffic. A toll of VND25,000 is payable for cars/mini buses. Motorcycles, cycles and pedestrians are not allowed in the tunnel but a new shuttle service began in November 2006. This shuttle service operates around the clock with a reduced overnight service and a daytime fare of VND12,000 per motorcycle, VND5,000 per bicycle, and VND3,000 per person. A small waiting area is being established at each end of the tunnel where visitors can take photographs and watch a documentary about the making of the tunnel.
The tunnel reduces the distance between
Da Nang andHuế by 20km and saves between 30 minutes and an hour on traveling times over the old Hai Van Pass route.References
External links
* [http://www.hazama.co.jp/japanese/hazamag/genbarepo/0504/genbarepo01_eng.html Construction Site Report]